CONSTRUCTION OF REGULATOR WITH LOCK ACROSS KONOTHUPUZHA RIVER AT PUTHENKAVU IN UDAYEMPEROOR PANCHAYATH,ERNAKULAM DISTRICT

Project CONSTRUCTION OF REGULATOR WITH LOCK ACROSS KONOTHUPUZHA RIVER AT PUTHENKAVU IN UDAYEMPEROOR PANCHAYATH,ERNAKULAM DISTRICT
Project Code EKMKIIFB07209
Work Category RCB(Regulator Cum Bridge)
Funding Agency KIIFB
Client Department Water Resource Department
Description The project aims at preventing saline water intrusion from Vembanad kayal in summer season and there by protecting the agricultural lands scattered in various panchayath including Ambaloor,Udeyamperoor,Mulamthuruthy and Chottanikkara as well as in the areas of Thrippunithura panchayath.This structure is 62m length and contain 3 vents of clear span 12m and 1 vent of 9m.The lock portion is 40m length with clear span pf 6.00m
Status On-going
District Ernakulam
Executing Office Office of GM1
AS Amount (Rs) 257580000
AS Number WRD-022-10/APR-6/2020 KIIFB
TS Amount (Rs) 257580000
TS Number KIIDC/310/KIIFB-RCB-KNTH/2018
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 CONSTRUCTION OF REGULATOR WITH LOCK ACROSS KONOTHUPUZHA RIVER AT PUTHENKAVU IN UDAYEMPEROOR PANCHAYATH,ERNAKULAM DISTRICT Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 Pile boring works for both lock portion and regulator portion completed. Total no of piles 72nos(lock wall portion-56nos and regulator portion- 16nos) Due to the heavy rain, as per the request from local bodies, the ring bund across the river partially dismantled to ensure the discharge of water from river and also the river flows over the ring bund of lock portion. After the pile foundation work, it has been difficult to proceed with the pile cap & solid apron work at site since the water level in the river is high due to the heavy rain. Remya P R

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/01/2021
Scheduled date of Completion of the Project 13 Jul 2022
Expected date of Completion 15/04/2023

Processing Dates

AS Date 28 Jul 2020