CONSTRUCTION OF REGULATOR WITH LOCK ACROSS KONOTHUPUZHA RIVER AT PUTHENKAVU IN UDAYEMPEROOR PANCHAYATH,ERNAKULAM DISTRICT

Project CONSTRUCTION OF REGULATOR WITH LOCK ACROSS KONOTHUPUZHA RIVER AT PUTHENKAVU IN UDAYEMPEROOR PANCHAYATH,ERNAKULAM DISTRICT
Project Code EKMKIIFB07209P1
Main Project CONSTRUCTION OF REGULATOR WITH LOCK ACROSS KONOTHUPUZHA RIVER AT PUTHENKAVU IN UDAYEMPEROOR PANCHAYATH,ERNAKULAM DISTRICT
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description The project aims at preventing saline water intrusion from Vembanad kayal in summer season and there by protecting the agricultural lands scattered in various panchayath including Ambaloor,Udeyamperoor,Mulamthuruthy and Chottanikkara as well as in the areas of Thrippunithura panchayath.This structure is 62m length and contain 3 vents of clear span 12m and 1 vent of 9m.The lock portion is 40m length with clear span pf 6.00m
Status On-going
District Ernakulam
Executing Office Office of GM1
TS Amount (Rs) 257580000
TS Number KIIDC/310/KIIFB-RCB-KNTH/2018
Technical specification
Contractor Marymatha Infrastructure Private Limited. (Mob: 9447358698)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 14/01/2021
Scheduled date of Completion as per agreement 13 Jul 2022
Expected date of Completion 15/04/2023

Processing Dates

TS Date 03 Sep 2020
Date Of Site Handover 14 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Foundation,apron,abutment,piers & lock wall 163306429.6 63 % 538.91 L
2 Ring bund & dewatering 18264780 70 % 49.31 L
3 watchman room 1528933.14 0 % 0
4 road formation 638193.5 0 % 0
5 mechanical works 39869304.63 10 % 0
6 electrical works 839897 0 % 0
7 protection works 19131361.08 15 % 0

Project Status Updations See All Status Updations

Joel J Varghese
Date: 26/07/2024

Work in progress | 62% Completed

Work has been hindrance due to heavy rain and the demolition of the ring bund Mechanical works of shutter fabrication are progressing at the yard.

Attached images

img

Joel J Varghese
Date: 26/07/2024

Work in progress | 62% Completed

Work has been hindrance due to heavy rain and the demolition of the ring bund Mechanical works of shutter fabrication are progressing at the yard.

Attached images