Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 Pile boring works for both lock portion and regulator portion completed. Total no of piles 72nos(lock wall portion-56nos and regulator portion- 16nos) Due to the heavy rain, as per the request from local bodies, the ring bund across the river partially dismantled to ensure the discharge of water from river and also the river flows over the ring bund of lock portion. After the pile foundation work, it has been difficult to proceed with the pile cap & solid apron work at site since the water level in the river is high due to the heavy rain. Remya P R