CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT

Project CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT
Project Code TCRKIIFB032182
Work Category RCB(Regulator Cum Bridge)
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT
Status On-going
District Thrissur
Executing Office Office of GM1
AS Amount (Rs) 273758639
AS Number WRD022-23/APR-6/2021/KIIFB
TS Amount (Rs) 267203000
TS Number KIIDC/134/RCB-Kanathodu-Pudukkad ,Thrissur /2021
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Apr 2022 upstream length of ring bund gas achieved before the monsoon. due to the extreme monsoon condition, the water level in the river increased tremendously. as per the directions from the irrigation department, they instructed to demolish the ring bund in order to avoid any difficulties to the smooth flow of river. the bund had demolished on 19/07/2022. no works were commenced after monsoon. Rahul V R

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/01/2022
Scheduled date of Completion of the Project 13 Jul 2023
Expected date of Completion 13/07/2023

Processing Dates

AS Date 01 Mar 2021
TS Date 23 Feb 2021

Other details

Project Officers View