Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Apr 2022 | upstream length of ring bund gas achieved before the monsoon. due to the extreme monsoon condition, the water level in the river increased tremendously. as per the directions from the irrigation department, they instructed to demolish the ring bund in order to avoid any difficulties to the smooth flow of river. the bund had demolished on 19/07/2022. no works were commenced after monsoon. | Rahul V R |