CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT

Project CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT
Project Code TCRKIIFB032182P1
Main Project CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF KANATHODU REGULATOR CUM BRIDGE ACROSS KURUMALI PUZHA AT KUNDUKADAVU IN PUDUKKAD PANCHAYATH, THRISSUR DISTRICT
Status On-going
District Thrissur
Executing Office Office of GM1
TS Amount (Rs) 267203000
TS Number KIIDC/134/RCB-Kanathodu-Pudukkad ,Thrissur /2021
Technical specification
Contractor Paulose George Construction Company Pvt Ltd (Mob: 9846438199)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 13/01/2022
Scheduled date of Completion as per agreement 13 Jul 2023
Expected date of Completion 13/07/2023

Processing Dates

TS Date 23 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Ring bund & dewatering 12063684 60 % 16.89 L
2 regulator cum bridge 126102001.1 58 % 0
3 approach road 39044820 3 % 0
4 river protection works 50839164 72 % 0
5 operator cum generator room 1753986.99 0 % 0
6 mechanical works 29995739.21 30 % 0
7 electrical work 2554086 0 % 0

Project Status Updations See All Status Updations

Rahul V R
Date: 22/07/2024

Work in progress | 67% Completed

Financial progress: 64.85% All the works were suspended due to heavy rainfall and rise in water level. .

Attached images

img

Rahul V R
Date: 22/07/2024

Work in progress | 67% Completed

Financial progress: 64.85% All the works were suspended due to heavy rainfall and rise in water level. .