Stephy Sebastian |
Date: 01/09/2023 |
Work has been completed | 100% Completed
Pathway|91% Completed
Solar Lighting|100% Completed
Solar Lighting|0% Completed
Work has been completed
Stephy Sebastian |
Date: 23/08/2023 |
Work has been completed | 100% Completed
Solar Lighting|0% Completed
Solar Lighting|100% Completed
Pathway|100% Completed
Work has been completed
Stephy Sebastian |
Date: 14/08/2023 |
Work has been completed | 100% Completed
Solar Lighting|0% Completed
Solar Lighting|100% Completed
Pathway|100% Completed
Work has been completed
Stephy Sebastian |
Date: 07/08/2023 |
Stephy Sebastian |
Date: 31/07/2023 |
Stephy Sebastian |
Date: 24/07/2023 |
Stephy Sebastian |
Date: 10/07/2023 |
Stephy Sebastian |
Date: 27/06/2023 |
Stephy Sebastian |
Date: 19/06/2023 |
Stephy Sebastian |
Date: 05/06/2023 |
Stephy Sebastian |
Date: 22/05/2023 |
Stephy Sebastian |
Date: 08/05/2023 |
Stephy Sebastian |
Date: 24/04/2023 |
Stephy Sebastian |
Date: 17/04/2023 |
Stephy Sebastian |
Date: 10/04/2023 |
Stephy Sebastian |
Date: 04/04/2023 |
Stephy Sebastian |
Date: 27/03/2023 |
Stephy Sebastian |
Date: 13/03/2023 |
Stephy Sebastian |
Date: 06/03/2023 |
Stephy Sebastian |
Date: 27/02/2023 |
Stephy Sebastian |
Date: 20/02/2023 |
Stephy Sebastian |
Date: 13/02/2023 |
Stephy Sebastian |
Date: 06/02/2023 |
Stephy Sebastian |
Date: 30/01/2023 |
Stephy Sebastian |
Date: 23/01/2023 |
Stephy Sebastian |
Date: 16/01/2023 |
Stephy Sebastian |
Date: 09/01/2023 |
Stephy Sebastian |
Date: 03/01/2023 |
Stephy Sebastian |
Date: 26/12/2022 |
Stephy Sebastian |
Date: 19/12/2022 |
Stephy Sebastian |
Date: 12/12/2022 |
Stephy Sebastian |
Date: 04/12/2022 |
Stephy Sebastian |
Date: 30/10/2022 |
Stephy Sebastian |
Date: 30/10/2022 |
Work in progress | 69% Completed
Solar Lighting|0% Completed
Solar Lighting|100% Completed
Pathway|100% Completed
1. All scheduled work completed 2. RE work is sanctioned 3. Report regarding RE submitted in Tourism department for approval 4. The approval from Tourism is not obtained for RE work. 5. Intimation from tourism DD not yet received.
Attached images
Stephy Sebastian |
Date: 17/10/2022 |
Not Started
Solar Lighting|0% Completed
Solar Lighting|100% Completed
Pathway|100% Completed
1. All scheduled work completed 2. RE work is sanctioned 3. Report regarding RE submitted in Tourism department for approval 4. The approval from Tourism is not obtained for RE work. 5. Intimation from tourism DD not yet received.
Attached images
Stephy Sebastian |
Date: 09/10/2022 |
Work in progress | 91% Completed
Solar Lighting|0% Completed
Solar Lighting|100% Completed
Pathway|100% Completed
1. All scheduled work completed 2. RE work is sanctioned 3. Report regarding RE submitted in Tourism department for approval 4. The approval from Tourism is not obtained for RE work
Attached images
Stephy Sebastian |
Date: 03/10/2022 |
Work in progress | 91% Completed
Solar Lighting|0% Completed
Solar Lighting|100% Completed
Pathway|100% Completed
1. All scheduled work completed 2. RE work is sanctioned 3. Report regarding RE submitted in Tourism department for approval 4. The approval from Tourism is not obtained for RE works
Attached images
Stephy Sebastian |
Date: 25/09/2022 |
Stephy Sebastian |
Date: 19/09/2022 |
Work in progress | 90% Completed
Pathway|91% Completed
Solar Lighting|100% Completed
Solar Lighting|0% Completed
Laying GSB Laying paver blocks Landscaping works Erection of solar LightLights Truss work for waiting sheds All work completed as per schedule some RE work is only pending. coconut pile casting is included in the Revised estimate. Letter regarding the same is given to DD of tourism and work can be proceed only after getting intimation from Tourism dept
Attached images