Project | PUNNAMADA – STARTING POINT PATHWAY AND BOAT LANDING AT ALAPPUZHA DISTRICT |
---|---|
Project Code | ALPTDK081937P1 |
Main Project | PUNNAMADA – STARTING POINT PATHWAY AND BOAT LANDING AT ALAPPUZHA DISTRICT |
Work Category | Funding Agency | TDK |
Client Department | Tourism Department |
Description | Improving the boat landing center at Punnamada by raising the ground and retaining wall including spreading of paver blocks and solar lighting. |
Status | Physically Completed |
District | Alappuzha |
Executing Office | Office of GM1 |
TS Amount (Rs) | 12700000 |
TS Number | Order No.KIIDC/402/Punnamada-SPP&BL ALP/2019 |
Technical specification | |
Contractor | M/s TBAS Construction (Mob: 8547119550) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 22/08/2019 |
---|---|
Scheduled date of Completion as per agreement | 04 Nov 2021 |
Expected date of Completion | 30/09/2022 |
TS Date | 17 Jan 2020 |
---|---|
Date Of Site Handover | 05 May 2021 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Pathway | 8331210 | 100 % | 75.81 L |
2 | Solar Lighting | 2720000 | 100 % | 27.2 L |
Stephy Sebastian |
Date: 01/09/2023 |
Work has been completed | 100% Completed
Work has been completed.
Stephy Sebastian |
Date: 01/09/2023 |
Work has been completed | 100% Completed
Work has been completed.