Silpa
Date: 26/07/2024

Work in progress | 95% Completed

0.00% MALAMPUZHA ITI|0% Completed

Civil work - 90% Electrical work - 90% ELV - 90% Fire works - 95% HVAC -95% Ongoing works: False ceiling works, furniture, electrical works and finishing works.

Attached images

img img

Nithish C
Date: 19/03/2024

Work in progress | 87% Completed

0.00% MALAMPUZHA ITI|0% Completed

Door fixing at classroom

Attached images

img

Nithish C
Date: 11/03/2024

Work in progress | 85% Completed

0.00% MALAMPUZHA ITI|0% Completed

Elv works ongoing

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 85% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal painting at class room first floor

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 85% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal painting at class room first floor

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 85% Completed

0.00% MALAMPUZHA ITI|0% Completed

Truss work completed

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 85% Completed

0.00% MALAMPUZHA ITI|0% Completed

Tiling work at ground floor staircase

Attached images

img

Nithish C
Date: 09/11/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Hume pipe laying

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Densified floor concreting at instrument workshop

Attached images

img

Nithish C
Date: 17/10/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Chipping the floor for densified flooring

Attached images

img

Nithish C
Date: 11/10/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 11/10/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 04/10/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work hold due to rain

Nithish C
Date: 18/09/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Blockwork at terrace floor

Attached images

img

Nithish C
Date: 11/09/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 05/09/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 22/08/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Primer applying at First floor smart class room

Attached images

img

Nithish C
Date: 14/08/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 08/08/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 24/07/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Work on hold

Nithish C
Date: 17/04/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Primer applying at external wall

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 11/04/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Primer applying at outside wall

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7819776

Accuracy : 5419.080289885569

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Primer applying at FF Classroom

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Primer applying at FF

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 14/03/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Primer applying at first floor passage

GPS Cordinates

Latitude : 10.8196955

Longitude : 76.6674406

Accuracy : 2200

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Applying primer at LGF ceiling

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Painting work at GF seminar hall

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.7885312

Accuracy : 5843.19891874529

Attached images

img

Nithish C
Date: 21/02/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Painting work at FF smart class room

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 14/02/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Painting work at FF smart classroom

GPS Cordinates

Latitude : 10.7215141

Longitude : 76.8490328

Accuracy : 4422.080452293195

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Priming coat applying at UGF ladies toilet

GPS Cordinates

Latitude : 10.5866868

Longitude : 76.7636187

Accuracy : 106.767

Attached images

img

Nithish C
Date: 31/01/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

UGF seminar hall skirting work

GPS Cordinates

Latitude : 9.9312328

Longitude : 76.2673041

Accuracy : 16893.07305711459

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

White washing at UGF passage area

GPS Cordinates

Latitude : 10.7282432

Longitude : 76.775424

Accuracy : 5226.455840126489

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 80% Completed

0.00% MALAMPUZHA ITI|0% Completed

Tile fixing at UGF seminar hall

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 11/01/2023

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

First floor passage painting work

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 04/01/2023

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

Painting work at FF smart class room

GPS Cordinates

Latitude : 10.8200088

Longitude : 76.6667187

Accuracy : 1700

Attached images

img

Nithish C
Date: 24/12/2022

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

External plastering at stair head room

GPS Cordinates

Latitude : 10.8189584

Longitude : 76.6663578

Accuracy : 1700

Attached images

img

Nithish C
Date: 19/12/2022

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

External plastering at sump tank

GPS Cordinates

Latitude : 10.8188953

Longitude : 76.6649141

Accuracy : 800

Attached images

img

Nithish C
Date: 13/12/2022

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

External plastering works and grill fixing at ground floor

GPS Cordinates

Latitude : 10.7867303

Longitude : 76.6547932

Accuracy : 3516.0181859876857

Attached images

img

Nithish C
Date: 05/12/2022

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

Tile fixing at first floor

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 29/11/2022

Work in progress | 79% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal plastering

GPS Cordinates

Latitude : 10.8211889

Longitude : 76.6651766

Accuracy : 28.100000381469727

Attached images

img

Nithish C
Date: 21/11/2022

Work in progress | 0% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal plastering

GPS Cordinates

Latitude : 10.7118592

Longitude : 76.7655936

Accuracy : 4361.8054114012275

Attached images

img

Nithish C
Date: 31/10/2022

Work in progress | 0% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal plastering

GPS Cordinates

Latitude : 10.737113

Longitude : 76.836517

Accuracy : 381

Attached images

img

Nithish C
Date: 22/10/2022

Work in progress | 0% Completed

0.00% MALAMPUZHA ITI|0% Completed

External plastering

GPS Cordinates

Latitude : 10.8196639

Longitude : 76.6667187

Accuracy : 1799.9990234375

Attached images

img

Nithish C
Date: 22/10/2022

Work in progress | 0% Completed

0.00% MALAMPUZHA ITI|0% Completed

External plastering

GPS Cordinates

Latitude : 10.8189584

Longitude : 76.6663578

Accuracy : 1700

Attached images

img

Nithish C
Date: 15/10/2022

Work in progress | 0% Completed

0.00% MALAMPUZHA ITI|0% Completed

Expansion joint coveing

GPS Cordinates

Latitude : 10.8210566

Longitude : 76.6652446

Accuracy : 183.18600463867188

Attached images

img

Nithish C
Date: 10/10/2022

Work in progress | 78% Completed

0.00% MALAMPUZHA ITI|0% Completed

External Plastering

GPS Cordinates

Latitude : 10.8225433

Longitude : 76.6655906

Accuracy : 149.60000610351562

Attached images

img

Nithish C
Date: 03/10/2022

Work in progress | 78% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal plastering

GPS Cordinates

Latitude : 10.7007716

Longitude : 76.750966

Accuracy : 1703.7828267076056

Attached images

img

Nithish C
Date: 26/09/2022

Work in progress | 78% Completed

0.00% MALAMPUZHA ITI|0% Completed

Internal plastering

GPS Cordinates

Latitude : 10.8189584

Longitude : 76.6663578

Accuracy : 1700

Attached images

img

Nithish C
Date: 19/09/2022

Work in progress | 78% Completed

0.00% MALAMPUZHA ITI|0% Completed

External plastering, Electrical work

GPS Cordinates

Latitude : 10.7216896

Longitude : 76.775424

Accuracy : 4980.4551957513095

Attached images

img

Silpa
Date: 26/07/2024

Work in progress | 0% Completed

Civil work - 90% Electrical work - 90% ELV - 90% Fire works - 95% HVAC -95% Ongoing works: False ceiling works, furniture, electrical works and finishing works.

Attached images

img img

Nithish C
Date: 19/03/2024

Work in progress | 0% Completed

Door fixing at classroom

Attached images

img

Nithish C
Date: 11/03/2024

Work in progress | 0% Completed

Elv works ongoing

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 0% Completed

Internal painting at class room first floor

Attached images

img

Nithish C
Date: 05/03/2024

Work in progress | 0% Completed

Internal painting at class room first floor

Attached images

img

Nithish C
Date: 28/02/2024

Work in progress | 0% Completed

Truss work completed

Attached images

img

Nithish C
Date: 01/01/2024

Work in progress | 0% Completed

Tiling work at ground floor staircase

Attached images

img

Nithish C
Date: 09/11/2023

Work in progress | 0% Completed

Hume pipe laying

Attached images

img

Nithish C
Date: 02/11/2023

Work in progress | 0% Completed

Densified floor concreting at instrument workshop

Attached images

img

Nithish C
Date: 17/10/2023

Work in progress | 0% Completed

Chipping the floor for densified flooring

Attached images

img

Nithish C
Date: 11/10/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 11/10/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 04/10/2023

Work in progress | 0% Completed

Work hold due to rain

Nithish C
Date: 18/09/2023

Work in progress | 0% Completed

Blockwork at terrace floor

Attached images

img

Nithish C
Date: 11/09/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 05/09/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 22/08/2023

Work in progress | 0% Completed

Primer applying at First floor smart class room

Attached images

img

Nithish C
Date: 14/08/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 08/08/2023

Work in progress | 0% Completed

Work on hold

Attached images

img

Nithish C
Date: 01/08/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 24/07/2023

Work in progress | 0% Completed

Work on hold

Nithish C
Date: 17/04/2023

Work in progress | 0% Completed

Primer applying at external wall

Attached images

img

Nithish C
Date: 11/04/2023

Work in progress | 0% Completed

Primer applying at outside wall

Attached images

img

Nithish C
Date: 28/03/2023

Work in progress | 0% Completed

Primer applying at FF Classroom

Attached images

img

Nithish C
Date: 20/03/2023

Work in progress | 0% Completed

Primer applying at FF

Attached images

img

Nithish C
Date: 14/03/2023

Work in progress | 0% Completed

Primer applying at first floor passage

Attached images

img

Nithish C
Date: 06/03/2023

Work in progress | 0% Completed

Applying primer at LGF ceiling

Attached images

img

Nithish C
Date: 27/02/2023

Work in progress | 0% Completed

Painting work at GF seminar hall

Attached images

img

Nithish C
Date: 21/02/2023

Work in progress | 0% Completed

Painting work at FF smart class room

Attached images

img

Nithish C
Date: 14/02/2023

Work in progress | 0% Completed

Painting work at FF smart classroom

Attached images

img

Nithish C
Date: 06/02/2023

Work in progress | 0% Completed

Priming coat applying at UGF ladies toilet

Attached images

img

Nithish C
Date: 31/01/2023

Work in progress | 0% Completed

UGF seminar hall skirting work

Attached images

img

Nithish C
Date: 23/01/2023

Work in progress | 0% Completed

White washing at UGF passage area

Attached images

img

Nithish C
Date: 16/01/2023

Work in progress | 0% Completed

Tile fixing at UGF seminar hall

Attached images

img

Nithish C
Date: 11/01/2023

Work in progress | 0% Completed

First floor passage painting work

Attached images

img

Nithish C
Date: 04/01/2023

Work in progress | 0% Completed

Painting work at FF smart class room

Attached images

img

Nithish C
Date: 24/12/2022

Work in progress | 0% Completed

External plastering at stair head room

Attached images

img

Nithish C
Date: 19/12/2022

Work in progress | 0% Completed

External plastering at sump tank

Attached images

img

Nithish C
Date: 13/12/2022

Work in progress | 0% Completed

External plastering works and grill fixing at ground floor

Attached images

img

Nithish C
Date: 05/12/2022

Work in progress | 0% Completed

Tile fixing at first floor

Attached images

img

Nithish C
Date: 29/11/2022

Work in progress | 0% Completed

Internal plastering

Attached images

img

Nithish C
Date: 21/11/2022

Work in progress | 0% Completed

Internal plastering

Attached images

img

Nithish C
Date: 31/10/2022

Work in progress | 0% Completed

Internal plastering

Attached images

img

Nithish C
Date: 22/10/2022

Work in progress | 0% Completed

External plastering

Attached images

img

Nithish C
Date: 22/10/2022

Work in progress | 0% Completed

External plastering

Attached images

img

Nithish C
Date: 15/10/2022

Work in progress | 0% Completed

Expansion joint coveing

Attached images

img

Nithish C
Date: 10/10/2022

Work in progress | 0% Completed

External Plastering

Attached images

img

Nithish C
Date: 03/10/2022

Work in progress | 0% Completed

Internal plastering

Attached images

img

Nithish C
Date: 26/09/2022

Work in progress | 0% Completed

Internal plastering

Attached images

img

Nithish C
Date: 19/09/2022

Work in progress | 0% Completed

External plastering, Electrical work

Attached images

img