UPGRADATION OF GOVT ITI MALAMPUZHA ON PAR WITH INTERNATIONAL STANDARDS-PHASE1

Project UPGRADATION OF GOVT ITI MALAMPUZHA ON PAR WITH INTERNATIONAL STANDARDS-PHASE1
Project Code PKDKIIFB121648P1
Main Project UPGRADATION OF GOVT ITI MALAMPUZHA ON PAR WITH INTERNATIONAL STANDARDS-PHASE1
Work Category
Funding Agency KIIFB
Client Department KASE
Description Modern facilities in campus including international standard roads ,pathways, gardens , lighting etc proposed. Construction of new main buildings basement+G+1 with smart classrooms(8 nos.) with integrated provisions for learning including modernized IT ready classrooms. The new main building serves as the Upgraded Administration block for the institute with all facilities ready to welcome international guests ,multinational companies for setting up production centers.
Status On-going
District Palakkad
Executing Office Office of GM1
TS Amount (Rs) 134692599
TS Number KASE-20/2016
Technical specification
Contractor M/s PERFECT ENGINEERS AND CONTRACTOR (Mob: 9447045566)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/12/2016
Scheduled date of Completion as per agreement 05 Sep 2021
Expected date of Completion 05/09/2021

Processing Dates

TS Date 27 Dec 2020
Date Of Site Handover 16 Mar 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 MALAMPUZHA ITI 116193745 0 % 0

Project Status Updations See All Status Updations

Silpa
Date: 26/07/2024

Work in progress | 95% Completed

Civil work - 90% Electrical work - 90% ELV - 90% Fire works - 95% HVAC -95% Ongoing works: False ceiling works, furniture, electrical works and finishing works..

Attached images

img img

Nithish C
Date: 19/03/2024

Work in progress | 87% Completed

Door fixing at classroom .

Attached images

img