Amal Padmu L P |
Date: 12/06/2023 |
Work has been completed | 100% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work
Amal Padmu L P |
Date: 05/06/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work
Amal Padmu L P |
Date: 29/05/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work
Amal Padmu L P |
Date: 22/05/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 15/05/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 07/05/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 02/05/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 24/04/2023 |
Work in progress | 91% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 17/04/2023 |
Work in progress | 91% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 11/04/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 03/04/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 27/03/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 21/03/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 13/03/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 06/03/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.
Amal Padmu L P |
Date: 27/02/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 20/02/2023 |
Work in progress | 91% Completed
Construction of well at RBC|100% Completed
Fertigation Room|100% Completed
Conversion of abandoned RBC into water storage|99% Completed
Pumping line from Moolathara|95% Completed
Electrical works|80% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 20/02/2023 |
Work in progress | 91% Completed
Construction of well at RBC|100% Completed
Fertigation Room|100% Completed
Conversion of abandoned RBC into water storage|99% Completed
Pumping line from Moolathara|95% Completed
Electrical works|80% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 13/02/2023 |
Work in progress | 91% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 30/01/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Attached images
Amal Padmu L P |
Date: 23/01/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 16/01/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Attached images
Amal Padmu L P |
Date: 09/01/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 04/01/2023 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS
Amal Padmu L P |
Date: 26/12/2022 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.
Attached images
Amal Padmu L P |
Date: 19/12/2022 |
Work in progress | 91% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.
Attached images
Amal Padmu L P |
Date: 12/12/2022 |
Work in progress | 91% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.
Attached images
Amal Padmu L P |
Date: 03/12/2022 |
Work in progress | 90% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.
Attached images
Amal Padmu L P |
Date: 29/11/2022 |
Work in progress | 90% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Electrical work and canal lining works are pending
Attached images
Amal Padmu L P |
Date: 29/10/2022 |
Work in progress | 0% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending
GPS Cordinates
Latitude : 10.6911427
Longitude : 76.8683125
Accuracy : 2400
Attached images
Amal Padmu L P |
Date: 25/10/2022 |
Work in progress | 0% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Lining work is pending. It can be complete only after the desiltation of canal
GPS Cordinates
Latitude : 10.6897949
Longitude : 76.8690332
Accuracy : 1899.9990234375
Attached images
Amal Padmu L P |
Date: 19/10/2022 |
Work in progress | 0% Completed
Pumping line from Moolathara|95% Completed
Electrical works|80% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Construction of well at RBC|100% Completed
Canal lining work can complete only after the completion of desilting
GPS Cordinates
Latitude : 10.696205
Longitude : 76.8657901
Accuracy : 1700
Attached images
Amal Padmu L P |
Date: 10/10/2022 |
Work in progress | 90% Completed
Construction of well at RBC|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Fertigation Room|100% Completed
Lining work for existing canal can only complete after the completion of de siltation work
Attached images
Amal Padmu L P |
Date: 01/10/2022 |
Work in progress | 90% Completed
Fertigation Room|100% Completed
Electrical works|80% Completed
Pumping line from Moolathara|95% Completed
Conversion of abandoned RBC into water storage|99% Completed
Construction of well at RBC|100% Completed
Lining work for existing canal can only complete after the completion of de siltation work
GPS Cordinates
Latitude : 10.6968022
Longitude : 76.863628
Accuracy : 2000
Attached images
Amal Padmu L P |
Date: 26/09/2022 |
Work in progress | 90% Completed
Pumping line from Moolathara|95% Completed
Construction of well at RBC|100% Completed
Fertigation Room|100% Completed
Conversion of abandoned RBC into water storage|99% Completed
Electrical works|80% Completed
Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting
GPS Cordinates
Latitude : 10.6897642
Longitude : 76.8683125
Accuracy : 2000
Attached images
Amal Padmu L P |
Date: 17/09/2022 |
Work in progress | 90% Completed
Construction of well at RBC|100% Completed
Fertigation Room|100% Completed
Conversion of abandoned RBC into water storage|99% Completed
Pumping line from Moolathara|95% Completed
Electrical works|80% Completed
PWD road crossing for pumping line from moolathara dam to moongilmada is completed