Amal Padmu L P
Date: 12/06/2023

Work has been completed | 100% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 05/06/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 29/05/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 22/05/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 15/05/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 07/05/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 02/05/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 24/04/2023

Work in progress | 91% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 17/04/2023

Work in progress | 91% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 11/04/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 03/04/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/03/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 21/03/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 13/03/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 06/03/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/02/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 91% Completed

100.00% Construction of well at RBC|100% Completed

100.00% Fertigation Room|100% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

95.00% Pumping line from Moolathara|95% Completed

80.00% Electrical works|80% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 91% Completed

100.00% Construction of well at RBC|100% Completed

100.00% Fertigation Room|100% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

95.00% Pumping line from Moolathara|95% Completed

80.00% Electrical works|80% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 13/02/2023

Work in progress | 91% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 30/01/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 23/01/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 16/01/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 09/01/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 04/01/2023

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 26/12/2022

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 19/12/2022

Work in progress | 91% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 12/12/2022

Work in progress | 91% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 03/12/2022

Work in progress | 90% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.

Attached images

img

Amal Padmu L P
Date: 29/11/2022

Work in progress | 90% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Electrical work and canal lining works are pending

Attached images

img

Amal Padmu L P
Date: 29/10/2022

Work in progress | 0% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending

GPS Cordinates

Latitude : 10.6911427

Longitude : 76.8683125

Accuracy : 2400

Attached images

img

Amal Padmu L P
Date: 25/10/2022

Work in progress | 0% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Lining work is pending. It can be complete only after the desiltation of canal

GPS Cordinates

Latitude : 10.6897949

Longitude : 76.8690332

Accuracy : 1899.9990234375

Attached images

img

Amal Padmu L P
Date: 19/10/2022

Work in progress | 0% Completed

95.00% Pumping line from Moolathara|95% Completed

80.00% Electrical works|80% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

100.00% Construction of well at RBC|100% Completed

Canal lining work can complete only after the completion of desilting

GPS Cordinates

Latitude : 10.696205

Longitude : 76.8657901

Accuracy : 1700

Attached images

img

Amal Padmu L P
Date: 10/10/2022

Work in progress | 90% Completed

100.00% Construction of well at RBC|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Fertigation Room|100% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 01/10/2022

Work in progress | 90% Completed

100.00% Fertigation Room|100% Completed

80.00% Electrical works|80% Completed

95.00% Pumping line from Moolathara|95% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

100.00% Construction of well at RBC|100% Completed

Lining work for existing canal can only complete after the completion of de siltation work

GPS Cordinates

Latitude : 10.6968022

Longitude : 76.863628

Accuracy : 2000

Attached images

img

Amal Padmu L P
Date: 26/09/2022

Work in progress | 90% Completed

95.00% Pumping line from Moolathara|95% Completed

100.00% Construction of well at RBC|100% Completed

100.00% Fertigation Room|100% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

80.00% Electrical works|80% Completed

Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting

GPS Cordinates

Latitude : 10.6897642

Longitude : 76.8683125

Accuracy : 2000

Attached images

img

Amal Padmu L P
Date: 17/09/2022

Work in progress | 90% Completed

100.00% Construction of well at RBC|100% Completed

100.00% Fertigation Room|100% Completed

99.00% Conversion of abandoned RBC into water storage|99% Completed

95.00% Pumping line from Moolathara|95% Completed

80.00% Electrical works|80% Completed

PWD road crossing for pumping line from moolathara dam to moongilmada is completed

GPS Cordinates

Latitude : 10.6894196

Longitude : 76.8683125

Accuracy : 1899.9990234375

Attached images

img

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 05/06/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 05/06/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 05/06/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 05/06/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 05/06/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 29/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 29/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 29/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 29/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 29/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work

Amal Padmu L P
Date: 22/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 22/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 22/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 22/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 22/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 15/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 15/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 15/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 15/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 15/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 07/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 07/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 07/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 07/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 07/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 02/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 02/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 02/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 02/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 02/05/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 24/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 24/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 24/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 24/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 24/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 17/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 17/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 17/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 17/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 17/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 11/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 11/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 11/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 11/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 11/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 03/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 03/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 03/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 03/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 03/04/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 21/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 21/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 21/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 21/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 21/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 13/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 13/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 13/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 13/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 13/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 06/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 06/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 06/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 06/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 06/03/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 27/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 27/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 27/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 27/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 27/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 20/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 13/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 13/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 13/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 13/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 13/02/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 30/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 30/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 30/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 30/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 30/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 23/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 23/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 23/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 23/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 23/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 16/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 16/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 16/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 16/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 16/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Attached images

img

Amal Padmu L P
Date: 09/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 09/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 09/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 09/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 09/01/2023

Work in progress | 0% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 04/01/2023

Work in progress | 0% Completed

Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 04/01/2023

Work in progress | 0% Completed

Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 04/01/2023

Work in progress | 0% Completed

Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 04/01/2023

Work in progress | 0% Completed

Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 04/01/2023

Work in progress | 0% Completed

Electrical and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work carried out by MGNERGS

Amal Padmu L P
Date: 26/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 26/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 26/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 26/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 26/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 19/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 19/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 19/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 19/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 19/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 12/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 12/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 12/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 12/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 12/12/2022

Work in progress | 0% Completed

Construction of irrigation room completed. Canal lining can be completed only after the completion of desilting work carried out by MGNERGS.

Attached images

img

Amal Padmu L P
Date: 03/12/2022

Work in progress | 0% Completed

Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.

Attached images

img

Amal Padmu L P
Date: 03/12/2022

Work in progress | 0% Completed

Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.

Attached images

img

Amal Padmu L P
Date: 03/12/2022

Work in progress | 0% Completed

Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.

Attached images

img

Amal Padmu L P
Date: 03/12/2022

Work in progress | 0% Completed

Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.

Attached images

img

Amal Padmu L P
Date: 03/12/2022

Work in progress | 0% Completed

Construction of pump house completed. lining work for the abandoned canal is pending. it can only carried out after the de-siltation of canal Electrical work at moolathara dam is pending. it is informed to Electrical wing to complete the pending electrical works.

Attached images

img

Amal Padmu L P
Date: 29/11/2022

Work in progress | 0% Completed

Electrical work and canal lining works are pending

Attached images

img

Amal Padmu L P
Date: 29/11/2022

Work in progress | 0% Completed

Electrical work and canal lining works are pending

Attached images

img

Amal Padmu L P
Date: 29/11/2022

Work in progress | 0% Completed

Electrical work and canal lining works are pending

Attached images

img

Amal Padmu L P
Date: 29/11/2022

Work in progress | 0% Completed

Electrical work and canal lining works are pending

Attached images

img

Amal Padmu L P
Date: 29/11/2022

Work in progress | 0% Completed

Electrical work and canal lining works are pending

Attached images

img

Amal Padmu L P
Date: 29/10/2022

Work in progress | 0% Completed

Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending

Attached images

img

Amal Padmu L P
Date: 29/10/2022

Work in progress | 0% Completed

Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending

Attached images

img

Amal Padmu L P
Date: 29/10/2022

Work in progress | 0% Completed

Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending

Attached images

img

Amal Padmu L P
Date: 29/10/2022

Work in progress | 0% Completed

Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending

Attached images

img

Amal Padmu L P
Date: 29/10/2022

Work in progress | 0% Completed

Construction of Irrigation room -100% Electrical works -50℅ Lining works on existing canal - pending

Attached images

img

Amal Padmu L P
Date: 25/10/2022

Work in progress | 0% Completed

Lining work is pending. It can be complete only after the desiltation of canal

Attached images

img

Amal Padmu L P
Date: 25/10/2022

Work in progress | 0% Completed

Lining work is pending. It can be complete only after the desiltation of canal

Attached images

img

Amal Padmu L P
Date: 25/10/2022

Work in progress | 0% Completed

Lining work is pending. It can be complete only after the desiltation of canal

Attached images

img

Amal Padmu L P
Date: 25/10/2022

Work in progress | 0% Completed

Lining work is pending. It can be complete only after the desiltation of canal

Attached images

img

Amal Padmu L P
Date: 25/10/2022

Work in progress | 0% Completed

Lining work is pending. It can be complete only after the desiltation of canal

Attached images

img

Amal Padmu L P
Date: 19/10/2022

Work in progress | 0% Completed

Canal lining work can complete only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 19/10/2022

Work in progress | 0% Completed

Canal lining work can complete only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 19/10/2022

Work in progress | 0% Completed

Canal lining work can complete only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 19/10/2022

Work in progress | 0% Completed

Canal lining work can complete only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 19/10/2022

Work in progress | 0% Completed

Canal lining work can complete only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 10/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 10/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 10/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 10/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 10/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 01/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 01/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 01/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 01/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 01/10/2022

Work in progress | 0% Completed

Lining work for existing canal can only complete after the completion of de siltation work

Attached images

img

Amal Padmu L P
Date: 26/09/2022

Work in progress | 0% Completed

Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 26/09/2022

Work in progress | 0% Completed

Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 26/09/2022

Work in progress | 0% Completed

Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 26/09/2022

Work in progress | 0% Completed

Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 26/09/2022

Work in progress | 0% Completed

Construction work for Fertigation room is completed Canal lining can be completed only after the completion of desilting

Attached images

img

Amal Padmu L P
Date: 17/09/2022

Work in progress | 0% Completed

PWD road crossing for pumping line from moolathara dam to moongilmada is completed

Attached images

img

Amal Padmu L P
Date: 17/09/2022

Work in progress | 0% Completed

PWD road crossing for pumping line from moolathara dam to moongilmada is completed

Attached images

img

Amal Padmu L P
Date: 17/09/2022

Work in progress | 0% Completed

PWD road crossing for pumping line from moolathara dam to moongilmada is completed

Attached images

img

Amal Padmu L P
Date: 17/09/2022

Work in progress | 0% Completed

PWD road crossing for pumping line from moolathara dam to moongilmada is completed

Attached images

img

Amal Padmu L P
Date: 17/09/2022

Work in progress | 0% Completed

PWD road crossing for pumping line from moolathara dam to moongilmada is completed

Attached images

img