KIIDC-Providing Community micro irrigation Moongilmada LIS -Construction of fertigation room,pump,pipe line,sump tank and electrification for micro irrigation work at eruthenpathy Panchayath palakkad district

Project KIIDC-Providing Community micro irrigation Moongilmada LIS -Construction of fertigation room,pump,pipe line,sump tank and electrification for micro irrigation work at eruthenpathy Panchayath palakkad district
Project Code PKDRKI121925P2
Main Project KIIDC-Providing Community micro irrigation at Moongilmada LIS in eruthenpathy Panchayath palakkad district
Work Category
Funding Agency RKI
Client Department Water Resource Department
Description Construction of fertigation room,pump,pipe line,sump tank and electrification work to Irrigate 250 acres of agricultural land
Status On-going
District Palakkad
Executing Office Office of GM2
TS Amount (Rs) 18800000
TS Number Order No.KIIDC/578/Micro Irrigation-Moongilmada
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 07/12/2019
Scheduled date of Completion as per agreement 26 Sep 2021
Expected date of Completion 30/10/2022

Processing Dates

TS Date 04 Sep 2020
Date Of Site Handover 03 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Construction of well at RBC 87934.58 100 % 0
2 Fertigation Room 1491211.56 100 % 0
3 Conversion of abandoned RBC into water storage 6392392.96 99 % 0
4 Pumping line from Moolathara 6970684.91 95 % 0
5 Electrical works 479998 80 % 0

Project Status Updations See All Status Updations

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.

Amal Padmu L P
Date: 12/06/2023

Work has been completed | 100% Completed

Electrical work at Moolathara regulator and canal lining works are pending. Canal lining works can be completed only after the completion of desilting work.