Stephy Sebastian |
Date: 01/09/2023 |
Stephy Sebastian |
Date: 23/08/2023 |
Stephy Sebastian |
Date: 14/08/2023 |
Stephy Sebastian |
Date: 07/08/2023 |
Stephy Sebastian |
Date: 31/07/2023 |
Stephy Sebastian |
Date: 24/07/2023 |
Stephy Sebastian |
Date: 10/07/2023 |
Stephy Sebastian |
Date: 27/06/2023 |
Work has been completed | 100% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed, Final Bill is under preparation
Attached images
Stephy Sebastian |
Date: 19/06/2023 |
Stephy Sebastian |
Date: 05/06/2023 |
Work has been completed | 100% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 22/05/2023 |
Work has been completed | 100% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 15/05/2023 |
Work has been completed | 100% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 08/05/2023 |
Work has been completed | 100% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 24/04/2023 |
Work has been completed | 100% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 17/04/2023 |
Work in progress | 99% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 10/04/2023 |
Work in progress | 99% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 04/04/2023 |
Work in progress | 99% Completed
Boat Landing|100% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 27/03/2023 |
Work in progress | 99% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 13/03/2023 |
Work in progress | 97% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 06/03/2023 |
Work in progress | 97% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 27/02/2023 |
Work in progress | 97% Completed
Boat Landing|82% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Walkway|0% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 20/02/2023 |
Work in progress | 97% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 13/02/2023 |
Work in progress | 97% Completed
Walkway|0% Completed
Solar Lighting|0% Completed
Boat Landing|82% Completed
Pile and Slab Retaining Wall |100% Completed
Pile & Slab retaining wall|0% Completed
Walkway |100% Completed
Solar Lighting |100% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 06/02/2023 |
Work in progress | 97% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 30/01/2023 |
Work in progress | 97% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 23/01/2023 |
Work in progress | 97% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
All works completed Finishing works is pending and in progress
Attached images
Stephy Sebastian |
Date: 16/01/2023 |
Work in progress | 94% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
The interlocking on the pavement started. RE submitted in KIIDC
Attached images
Stephy Sebastian |
Date: 09/01/2023 |
Work in progress | 94% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
The interlocking on the pavement started. RE submitted in KIIDC
Attached images
Stephy Sebastian |
Date: 03/01/2023 |
Work in progress | 94% Completed
Boat Landing|100% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
Walkway|0% Completed
The interlocking on the pavement started. RE submitted in KIIDC
Attached images
Stephy Sebastian |
Date: 26/12/2022 |
Work in progress | 94% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
The RE submitted in KIIDC and all the scheduled works completed.
Attached images
Stephy Sebastian |
Date: 19/12/2022 |
Work in progress | 94% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
The scheduled works completed and only interlock laying and finishing works only pending and in progress
Attached images
Stephy Sebastian |
Date: 12/12/2022 |
Work in progress | 93% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
The intimation reported to CTE. The only pending work is interlock that can be started after 2 days (CTE reporting time)
Attached images
Stephy Sebastian |
Date: 04/12/2022 |
Work in progress | 92% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
The GSB laying is completed in walkway and boat landing Final levels has been taken and intimation will report soon
Attached images
Stephy Sebastian |
Date: 28/11/2022 |
Work in progress | 89% Completed
Boat Landing|82% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Walkway|0% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
The GSB work completed and the levels has been taken
Attached images
Stephy Sebastian |
Date: 30/10/2022 |
Work in progress | 88% Completed
Boat Landing|100% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
Walkway|0% Completed
The GSB laying on the walkway is in progress Rolling the GSB will be accompanied after the laying
Attached images
Stephy Sebastian |
Date: 27/10/2022 |
Work in progress | 83% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
The foundation work for the solar lightning completed. The pole for the same have been erected and the item is included in the RE and is been prepartion is under progress
Attached images
Stephy Sebastian |
Date: 26/10/2022 |
Work in progress | 82% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
Quarry muck filling completed The levels for the same have been reported and the GSB laying will be commenced soon.
Attached images
Stephy Sebastian |
Date: 26/10/2022 |
Work in progress | 65% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
The foundation of solar light has been completed and solar light fixing is included in RE for approval of the brand
Attached images
Stephy Sebastian |
Date: 26/10/2022 |
Work in progress | 64% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
The GSB laying of the walkway completed
Attached images
Stephy Sebastian |
Date: 25/10/2022 |
Work in progress | 35% Completed
Walkway |100% Completed
Walkway|0% Completed
Solar Lighting|0% Completed
Boat Landing|82% Completed
Pile and Slab Retaining Wall |100% Completed
Pile & Slab retaining wall|0% Completed
Solar Lighting |100% Completed
1. The filling of boat landing and pathway completed 2. The levels had been taken and will report 25/10/2022 CTE 3. Truss work of shed is 70 % completed. 4. Anchor beam and block work is in progress . 4. GSB work in boat landing and walkway is in progress.
Attached images
Stephy Sebastian |
Date: 17/10/2022 |
Not Started
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
1. The filling of boat landing and pathway completed 2. The levels had been taken and will report 17/10/2022 CTE 3. Truss work of shed is 70 % completed. 4. Anchor beam and block work is in progress . 4. GSB work in boat landing and walkway is in progress.
Attached images
Stephy Sebastian |
Date: 09/10/2022 |
Work in progress | 81% Completed
Walkway|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Solar Lighting|0% Completed
1. The filling of boat landing and pathway completed 2. The levels had been taken and to report on 07/10/2022 to CTE 3. Truss work of shed is 50 % completed. 4. Anchor beam and block work is in progress
Attached images
Stephy Sebastian |
Date: 03/10/2022 |
Work in progress | 80% Completed
Solar Lighting |100% Completed
Walkway|0% Completed
Solar Lighting|0% Completed
Boat Landing|82% Completed
Pile and Slab Retaining Wall |100% Completed
Pile & Slab retaining wall|0% Completed
Walkway |100% Completed
1. The filling of boat landing and pathway completed 2. The levels had been taken for reporting and the calculations are checking and trying to report 3/10/2022 to CTE 3. Truss work of shed is 35 % completed. 4. Anchor beam and block work is in progress.
Attached images
Stephy Sebastian |
Date: 25/09/2022 |
Work in progress | 79% Completed
Solar Lighting|0% Completed
Solar Lighting |100% Completed
Walkway |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Pile and Slab Retaining Wall |100% Completed
Walkway|0% Completed
1. The filling of boat landing and pathway completed 2. The levels had been taken for reporting CTE 3. Truss work of shed is 25 % completed
Attached images
Stephy Sebastian |
Date: 19/09/2022 |
Work in progress | 76% Completed
Solar Lighting|0% Completed
Walkway |100% Completed
Solar Lighting |100% Completed
Pile & Slab retaining wall|0% Completed
Boat Landing|100% Completed
Walkway|0% Completed
Pile and Slab Retaining Wall |100% Completed
Backfilling of earth and Construction of Rubble masonry Retaining wall for Pathway and Boat landing Backfilling behind Pile and slab retaining wall Anchor belt and beam- 69 completed. 30 to be completed. Filling of pavement completed using earth final levels of the earth filling have been taken in accompany with initial level of GSB Filling of quarry muck and red earth had been completed and levels and RE is in progress
Attached images
Stephy Sebastian |
Date: 30/12/2021 |
Work in progress | 61% Completed
Walkway |100% Completed
Walkway|0% Completed
Solar Lighting|0% Completed
Boat Landing|82% Completed
Pile and Slab Retaining Wall |100% Completed
Pile & Slab retaining wall|0% Completed
Solar Lighting |100% Completed
The Pile slab work physically completed
Attached images