Project | CHUNGAM (CHAKREPURAKKAL) – KAYALCHIRA PATHWAY DEVELOPMENT AND BOAT LANDING BY THE SIDE OF PUNNAMADA RIVER, AT ALAPPUZHA DISTRICT |
---|---|
Project Code | ALPTDK081938P1 |
Main Project | CHUNGAM (CHAKREPURAKKAL) – KAYALCHIRA PATHWAY DEVELOPMENT AND BOAT LANDING BY THE SIDE OF PUNNAMADA RIVER, AT ALAPPUZHA DISTRICT |
Work Category | Funding Agency | TDK |
Client Department | Tourism Department |
Description | Improving the boat landing center at Chungam, Alappuzha by providing pile and slab retaining wall and raising the ground, construction of walkway and spreading of paver blocks to develop the tourism activities. |
Status | On-going |
District | Alappuzha |
Executing Office | Office of GM1 |
TS Amount (Rs) | 34000000 |
TS Number | Order No.KIIDC/392/Chungam II/2019 |
Technical specification | |
Contractor | M/s TBAS Construction (Mob: 8547119550) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 22/08/2019 |
---|---|
Scheduled date of Completion as per agreement | 04 Feb 2022 |
Expected date of Completion | Date is not specified |
TS Date | 17 Jan 2020 |
---|---|
Date Of Site Handover | 05 May 2021 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Walkway | 12563500 | 100 % | 114.33 L |
2 | Boat Landing | 7796705.4 | 100 % | 54.58 L |
3 | Pile and Slab Retaining Wall | 7767551.18 | 100 % | 77.68 L |
4 | Solar Lighting | 1700000 | 100 % | 15.3 L |
Stephy Sebastian |
Date: 01/09/2023 |