Abhinandh P T
Date: 14/11/2024

Work in progress | 42% Completed

% |0% Completed

top beam of first floor of ootupura completed

Abhinandh P T
Date: 12/08/2024

Work in progress | 42% Completed

% |0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 26/07/2024

Work in progress | 42% Completed

% |0% Completed

Appendix A: Oottupura slab concrete has been completed. Appendix B: Pavement and Toilet Block - Toilet Block: 90% completed; ceiling tile and electrification works remain. - Pavement: Due to the single entrance to the temple, this can only be completed at the final stage of the work. Appendix C: Kulapura: 0% completed. Appendix D: Saraswathi Mandapam: 90% of the work has been completed; electrification and ceiling tile works remain. Appendix E: Pond: Reviving lamp post foundation works have been completed.

Attached images

img img img img

Abhinandh P T
Date: 23/07/2024

Work in progress | 42% Completed

% |0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 19/07/2024

Work in progress | 42% Completed

% |0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 01/07/2024

Work in progress | 42% Completed

% |0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 25/06/2024

Work in progress | 42% Completed

% |0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 11/06/2024

Work in progress | 22% Completed

% |0% Completed

Slab concrete completed

Abhinandh P T
Date: 27/05/2024

Work in progress | 20% Completed

% |0% Completed

slab and beam shuttering work in progress

Abhinandh P T
Date: 20/05/2024

Work in progress | 20% Completed

% |0% Completed

column work completed

Abhinandh P T
Date: 13/05/2024

Work in progress | 19% Completed

% |0% Completed

column work under progress

Abhinandh P T
Date: 06/05/2024

Work in progress | 18% Completed

% |0% Completed

plinth beam concrete completed

Abhinandh P T
Date: 30/04/2024

Work in progress | 17% Completed

% |0% Completed

ootupura - plinth beam work started

Abhinandh P T
Date: 22/04/2024

Work in progress | 17% Completed

% |0% Completed

ootupura - footing completed

Abhinandh P T
Date: 15/04/2024

Work in progress | 16% Completed

% |0% Completed

ootupura pcc completed

Abhinandh P T
Date: 01/04/2024

Work in progress | 15% Completed

% |0% Completed

drainage work completed - pond work will start this week

Abhinandh P T
Date: 18/03/2024

Work in progress | 15% Completed

% |0% Completed

drainage work under progress

Abhinandh P T
Date: 11/03/2024

Work in progress | 15% Completed

% |0% Completed

drainage work under progress

Attached images

img

Abhinandh P T
Date: 04/03/2024

Work in progress | 15% Completed

% |0% Completed

Toilet block - 90% completed Saraswathi mandapam - 90% completed pond work expected to start in coming week

Abhinandh P T
Date: 28/02/2024

Work in progress | 15% Completed

% |0% Completed

Toilet block -90% completed saraswathi mandapam - 90% completed

Abhinandh P T
Date: 24/01/2024

Work in progress | 14% Completed

% |0% Completed

Toilet block -90% completed saraswathi mandapam - 90% completed

Abhinandh P T
Date: 30/12/2023

Work in progress | 14% Completed

% |0% Completed

toilet block -90% completed saraswathi mandapam - 90% completed

Attached images

img img

Abhinandh P T
Date: 22/12/2023

Work in progress | 14% Completed

% |0% Completed

toilet block -90% completed saraswathi mandapam - 90% completed

Abhinandh P T
Date: 14/11/2023

Work in progress | 13% Completed

% |0% Completed

toilet block - show wall work under progress saraswathi mandapam - flooring work started

Abhinandh P T
Date: 09/11/2023

Work in progress | 13% Completed

% |0% Completed

toilet block - show wall work under progress saraswathi mandapam - flooring work started

Abhinandh P T
Date: 30/10/2023

Work in progress | 10% Completed

% |0% Completed

toilet block - lintel work completed saraswathi mandapam - roof tile work completed

Abhinandh P T
Date: 26/10/2023

Work in progress | 10% Completed

% |0% Completed

toilet block - lintel work completed saraswathi mandapam - roof tile work completed

Abhinandh P T
Date: 03/10/2023

Work in progress | 7% Completed

% |0% Completed

toilet block - wall completed mandapam - structural work started

Abhinandh P T
Date: 18/09/2023

Work in progress | 4% Completed

% |0% Completed

toilet block plinth beam completed

Abhinandh P T
Date: 11/09/2023

Work in progress | 4% Completed

% |0% Completed

toilet block plinth beam completed

Abhinandh P T
Date: 14/08/2023

Work in progress | 4% Completed

% |0% Completed

toilet block plinth beam completed

Abhinandh P T
Date: 07/08/2023

Work in progress | 4% Completed

% |0% Completed

toilet block plinth beam work under progress

Abhinandh P T
Date: 02/08/2023

Work in progress | 3% Completed

% |0% Completed

toilet block foundation completed

Abhinandh P T
Date: 27/07/2023

Work in progress | 1% Completed

% |0% Completed

toilet block foundation work in progress

Abhinandh P T
Date: 13/07/2023

Work in progress | 1% Completed

% |0% Completed

The work was delayed due to the unavailability of the GFC drawing

Abhinandh P T
Date: 14/11/2024

Work in progress | 0% Completed

top beam of first floor of ootupura completed

Abhinandh P T
Date: 12/08/2024

Work in progress | 0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 26/07/2024

Work in progress | 0% Completed

Appendix A: Oottupura slab concrete has been completed. Appendix B: Pavement and Toilet Block - Toilet Block: 90% completed; ceiling tile and electrification works remain. - Pavement: Due to the single entrance to the temple, this can only be completed at the final stage of the work. Appendix C: Kulapura: 0% completed. Appendix D: Saraswathi Mandapam: 90% of the work has been completed; electrification and ceiling tile works remain. Appendix E: Pond: Reviving lamp post foundation works have been completed.

Attached images

img img img img

Abhinandh P T
Date: 23/07/2024

Work in progress | 0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 19/07/2024

Work in progress | 0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 01/07/2024

Work in progress | 0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 25/06/2024

Work in progress | 0% Completed

Lamp post foundation work under progress

Abhinandh P T
Date: 11/06/2024

Work in progress | 0% Completed

Slab concrete completed

Abhinandh P T
Date: 27/05/2024

Work in progress | 0% Completed

slab and beam shuttering work in progress

Abhinandh P T
Date: 20/05/2024

Work in progress | 0% Completed

column work completed

Abhinandh P T
Date: 13/05/2024

Work in progress | 0% Completed

column work under progress

Abhinandh P T
Date: 06/05/2024

Work in progress | 0% Completed

plinth beam concrete completed

Abhinandh P T
Date: 30/04/2024

Work in progress | 0% Completed

ootupura - plinth beam work started

Abhinandh P T
Date: 22/04/2024

Work in progress | 0% Completed

ootupura - footing completed

Abhinandh P T
Date: 15/04/2024

Work in progress | 0% Completed

ootupura pcc completed

Abhinandh P T
Date: 01/04/2024

Work in progress | 0% Completed

drainage work completed - pond work will start this week

Abhinandh P T
Date: 18/03/2024

Work in progress | 0% Completed

drainage work under progress

Abhinandh P T
Date: 11/03/2024

Work in progress | 0% Completed

drainage work under progress

Attached images

img

Abhinandh P T
Date: 04/03/2024

Work in progress | 0% Completed

Toilet block - 90% completed Saraswathi mandapam - 90% completed pond work expected to start in coming week

Abhinandh P T
Date: 28/02/2024

Work in progress | 0% Completed

Toilet block -90% completed saraswathi mandapam - 90% completed

Abhinandh P T
Date: 24/01/2024

Work in progress | 0% Completed

Toilet block -90% completed saraswathi mandapam - 90% completed

Abhinandh P T
Date: 30/12/2023

Work in progress | 0% Completed

toilet block -90% completed saraswathi mandapam - 90% completed

Attached images

img img

Abhinandh P T
Date: 22/12/2023

Work in progress | 0% Completed

toilet block -90% completed saraswathi mandapam - 90% completed

Abhinandh P T
Date: 14/11/2023

Work in progress | 0% Completed

toilet block - show wall work under progress saraswathi mandapam - flooring work started

Abhinandh P T
Date: 09/11/2023

Work in progress | 0% Completed

toilet block - show wall work under progress saraswathi mandapam - flooring work started

Abhinandh P T
Date: 30/10/2023

Work in progress | 0% Completed

toilet block - lintel work completed saraswathi mandapam - roof tile work completed

Abhinandh P T
Date: 26/10/2023

Work in progress | 0% Completed

toilet block - lintel work completed saraswathi mandapam - roof tile work completed

Abhinandh P T
Date: 03/10/2023

Work in progress | 0% Completed

toilet block - wall completed mandapam - structural work started

Abhinandh P T
Date: 18/09/2023

Work in progress | 0% Completed

toilet block plinth beam completed

Abhinandh P T
Date: 11/09/2023

Work in progress | 0% Completed

toilet block plinth beam completed

Abhinandh P T
Date: 14/08/2023

Work in progress | 0% Completed

toilet block plinth beam completed

Abhinandh P T
Date: 07/08/2023

Work in progress | 0% Completed

toilet block plinth beam work under progress

Abhinandh P T
Date: 02/08/2023

Work in progress | 0% Completed

toilet block foundation completed

Abhinandh P T
Date: 27/07/2023

Work in progress | 0% Completed

toilet block foundation work in progress

Abhinandh P T
Date: 13/07/2023

Work in progress | 0% Completed

The work was delayed due to the unavailability of the GFC drawing