Abhinandh P T |
Date: 14/11/2024 |
Work in progress | 42% Completed
|0% Completed
top beam of first floor of ootupura completed
Abhinandh P T |
Date: 12/08/2024 |
Work in progress | 42% Completed
|0% Completed
Lamp post foundation work under progress
Abhinandh P T |
Date: 26/07/2024 |
Work in progress | 42% Completed
|0% Completed
Appendix A: Oottupura slab concrete has been completed. Appendix B: Pavement and Toilet Block - Toilet Block: 90% completed; ceiling tile and electrification works remain. - Pavement: Due to the single entrance to the temple, this can only be completed at the final stage of the work. Appendix C: Kulapura: 0% completed. Appendix D: Saraswathi Mandapam: 90% of the work has been completed; electrification and ceiling tile works remain. Appendix E: Pond: Reviving lamp post foundation works have been completed.
Attached images
Abhinandh P T |
Date: 23/07/2024 |
Work in progress | 42% Completed
|0% Completed
Lamp post foundation work under progress
Abhinandh P T |
Date: 19/07/2024 |
Work in progress | 42% Completed
|0% Completed
Lamp post foundation work under progress
Abhinandh P T |
Date: 01/07/2024 |
Work in progress | 42% Completed
|0% Completed
Lamp post foundation work under progress
Abhinandh P T |
Date: 25/06/2024 |
Work in progress | 42% Completed
|0% Completed
Lamp post foundation work under progress
Abhinandh P T |
Date: 11/06/2024 |
Work in progress | 22% Completed
|0% Completed
Slab concrete completed
Abhinandh P T |
Date: 27/05/2024 |
Work in progress | 20% Completed
|0% Completed
slab and beam shuttering work in progress
Abhinandh P T |
Date: 20/05/2024 |
Work in progress | 20% Completed
|0% Completed
column work completed
Abhinandh P T |
Date: 13/05/2024 |
Work in progress | 19% Completed
|0% Completed
column work under progress
Abhinandh P T |
Date: 06/05/2024 |
Work in progress | 18% Completed
|0% Completed
plinth beam concrete completed
Abhinandh P T |
Date: 30/04/2024 |
Work in progress | 17% Completed
|0% Completed
ootupura - plinth beam work started
Abhinandh P T |
Date: 22/04/2024 |
Work in progress | 17% Completed
|0% Completed
ootupura - footing completed
Abhinandh P T |
Date: 15/04/2024 |
Work in progress | 16% Completed
|0% Completed
ootupura pcc completed
Abhinandh P T |
Date: 01/04/2024 |
Work in progress | 15% Completed
|0% Completed
drainage work completed - pond work will start this week
Abhinandh P T |
Date: 18/03/2024 |
Work in progress | 15% Completed
|0% Completed
drainage work under progress
Abhinandh P T |
Date: 11/03/2024 |
Abhinandh P T |
Date: 04/03/2024 |
Work in progress | 15% Completed
|0% Completed
Toilet block - 90% completed Saraswathi mandapam - 90% completed pond work expected to start in coming week
Abhinandh P T |
Date: 28/02/2024 |
Work in progress | 15% Completed
|0% Completed
Toilet block -90% completed saraswathi mandapam - 90% completed
Abhinandh P T |
Date: 24/01/2024 |
Work in progress | 14% Completed
|0% Completed
Toilet block -90% completed saraswathi mandapam - 90% completed
Abhinandh P T |
Date: 30/12/2023 |
Abhinandh P T |
Date: 22/12/2023 |
Work in progress | 14% Completed
|0% Completed
toilet block -90% completed saraswathi mandapam - 90% completed
Abhinandh P T |
Date: 14/11/2023 |
Work in progress | 13% Completed
|0% Completed
toilet block - show wall work under progress saraswathi mandapam - flooring work started
Abhinandh P T |
Date: 09/11/2023 |
Work in progress | 13% Completed
|0% Completed
toilet block - show wall work under progress saraswathi mandapam - flooring work started
Abhinandh P T |
Date: 30/10/2023 |
Work in progress | 10% Completed
|0% Completed
toilet block - lintel work completed saraswathi mandapam - roof tile work completed
Abhinandh P T |
Date: 26/10/2023 |
Work in progress | 10% Completed
|0% Completed
toilet block - lintel work completed saraswathi mandapam - roof tile work completed
Abhinandh P T |
Date: 03/10/2023 |
Work in progress | 7% Completed
|0% Completed
toilet block - wall completed mandapam - structural work started
Abhinandh P T |
Date: 18/09/2023 |
Work in progress | 4% Completed
|0% Completed
toilet block plinth beam completed
Abhinandh P T |
Date: 11/09/2023 |
Work in progress | 4% Completed
|0% Completed
toilet block plinth beam completed
Abhinandh P T |
Date: 14/08/2023 |
Work in progress | 4% Completed
|0% Completed
toilet block plinth beam completed
Abhinandh P T |
Date: 07/08/2023 |
Work in progress | 4% Completed
|0% Completed
toilet block plinth beam work under progress
Abhinandh P T |
Date: 02/08/2023 |
Work in progress | 3% Completed
|0% Completed
toilet block foundation completed
Abhinandh P T |
Date: 27/07/2023 |
Work in progress | 1% Completed
|0% Completed
toilet block foundation work in progress
Abhinandh P T |
Date: 13/07/2023 |
Work in progress | 1% Completed
|0% Completed
The work was delayed due to the unavailability of the GFC drawing