Project | Thalassery Heritage Project - Kadirur Surya Narayana Temple |
---|---|
Project Code | KNRKIIFB122064P1 |
Main Project | Thalassery Heritage Project - Kadirur Surya Narayana Temple |
Work Category | Funding Agency | KIIFB |
Client Department | Tourism Department |
Description | Thalassery Heritage Project - Kadirur Surya Narayana Temple |
Status | On-going |
District | Kannur |
Executing Office | Office of GM1 |
TS Amount (Rs) | 29543058 |
TS Number | KIIDC/68/THP-Phase 2- Kadirur Surya Narayana Temple/2021 |
Technical specification |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 08 Feb 2021 |
---|
Abhinandh P T |
Date: 14/11/2024 |
Work in progress | 42% Completed
top beam of first floor of ootupura completed.
Abhinandh P T |
Date: 12/08/2024 |
Work in progress | 42% Completed
Lamp post foundation work under progress.