MIDHUN DAS |
Date: 01/04/2025 |
Work in progress | 5% Completed
Renovation of Guest House|5% Completed
Staff Room & Toilet|0% Completed
Modular Kitchen|0% Completed
Renovation of Gate pillar and Compound wall |0% Completed
Plumbing|0% Completed
ELectrification|0% Completed
Landscaping|0% Completed
Toilet block|0% Completed
plumbing work commenced
MIDHUN DAS |
Date: 24/03/2025 |
Work in progress | 5% Completed
Renovation of Gate pillar and Compound wall |0% Completed
Plumbing|0% Completed
Staff Room & Toilet|0% Completed
Modular Kitchen|0% Completed
ELectrification|0% Completed
Landscaping|0% Completed
Toilet block|0% Completed
Renovation of Guest House|5% Completed
dismantling floor and wall tiles from rooms and toilets
MIDHUN DAS |
Date: 17/03/2025 |
Work in progress | 4% Completed
Toilet block|0% Completed
Plumbing|0% Completed
Staff Room & Toilet|0% Completed
Modular Kitchen|0% Completed
Renovation of Guest House|5% Completed
Renovation of Gate pillar and Compound wall |0% Completed
ELectrification|0% Completed
Landscaping|0% Completed
DISMANTLING WALL TILES AND FLOOR TILES ARE IN PROGRESS
MIDHUN DAS |
Date: 10/03/2025 |
Work in progress | 2% Completed
Renovation of Gate pillar and Compound wall |0% Completed
Renovation of Guest House|5% Completed
Toilet block|0% Completed
Landscaping|0% Completed
ELectrification|0% Completed
Modular Kitchen|0% Completed
Staff Room & Toilet|0% Completed
Plumbing|0% Completed
dismantling floor and wall tiles in guesthouse rooms are in progress
MIDHUN DAS |
Date: 24/02/2025 |
Work in progress | 2% Completed
Renovation of Guest House|5% Completed
Plumbing|0% Completed
Staff Room & Toilet|0% Completed
Modular Kitchen|0% Completed
Renovation of Gate pillar and Compound wall |0% Completed
ELectrification|0% Completed
Landscaping|0% Completed
Toilet block|0% Completed
Toilet renovation work in progress
MIDHUN DAS |
Date: 24/02/2025 |
Work in progress | 2% Completed
Plumbing|0% Completed
Staff Room & Toilet|0% Completed
Modular Kitchen|0% Completed
Renovation of Gate pillar and Compound wall |0% Completed
ELectrification|0% Completed
Landscaping|0% Completed
Toilet block|0% Completed
Renovation of Guest House|5% Completed
Toilet renovation work in progress
MIDHUN DAS |
Date: 17/02/2025 |
Work in progress | 1% Completed
Toilet block|0% Completed
Plumbing|0% Completed
Staff Room & Toilet|0% Completed
Modular Kitchen|0% Completed
Renovation of Gate pillar and Compound wall |0% Completed
ELectrification|0% Completed
Landscaping|0% Completed
Renovation of Guest House|5% Completed
The site was handed over to the contractor on 06/02/2025, and the work commenced on 17/02/2025.