| Project | Maintenance Work of Kerala House Kanyakumari |
|---|---|
| Project Code | TVMTDK0724124P1 |
| Main Project | Maintenance Work of Kerala House Kanyakumari |
| Work Category | Funding Agency | TDK |
| Client Department | Tourism Department |
| Description | Maintenance Work of Kerala House Kanyakumari |
| Status | On-going |
| District | Thiruvananthapuram |
| Executing Office | Office of GM1 |
| TS Amount (Rs) | 58800000 |
| TS Number | IRR/KIIDC/EST_TS/2521/2024_5_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 06/02/2025 |
|---|---|
| Scheduled date of Completion as per agreement | 05 Aug 2026 |
| Expected date of Completion | 05/08/2026 |
| TS Date | 21 Oct 2024 |
|---|---|
| Tender Publish Date | 23 Oct 2024 |
| Tender Extension Date | 13 Nov 2024 |
| Tender Opening Date | 11 Nov 2024 |
| Technical Bid Opening Date | 18 Nov 2024 |
| Selection Notice Issued Date | 27 Dec 2024 |
| Date Of Site Handover | 06 Feb 2025 |
| # | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
|---|---|---|---|---|
| 1 | Renovation of Guest House | 29663959.6 | 5 % | 0 |
| 2 | Renovation of Gate pillar and Compound wall | 3537932.01 | 0 % | 0 |
| 3 | Modular Kitchen | 830144.56 | 0 % | 0 |
| 4 | Toilet block | 1562697.12 | 0 % | 0 |
| 5 | Staff Room & Toilet | 1975750.02 | 0 % | 0 |
| 6 | Plumbing | 622462.3 | 0 % | 0 |
| 7 | ELectrification | 8757585.09 | 0 % | 0 |
| 8 | Landscaping | 1493043.3 | 0 % | 0 |
| MIDHUN DAS |
| Date: 30/08/2025 |
Work in progress | 7% Completed
window maintenance and rectification work in progress.
| MIDHUN DAS |
| Date: 30/08/2025 |
Work in progress | 7% Completed
window maintenance and rectification work in progress.