VIMAL T T |
Date: 02/06/2025 |
Work in progress | 13% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 26/05/2025 |
Work in progress | 13% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 19/05/2025 |
Work in progress | 13% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 12/05/2025 |
Work in progress | 13% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 05/05/2025 |
Work in progress | 13% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 28/04/2025 |
Work in progress | 13% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 14/04/2025 |
Work in progress | 13% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Pond renovation works ongoing. Financial progress- 12.5%
VIMAL T T |
Date: 07/04/2025 |
Work in progress | 12% Completed
Pond Renovation|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
Compound wall works ongoing.
VIMAL T T |
Date: 31/03/2025 |
Work in progress | 12% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Compound wall works ongoing.
VIMAL T T |
Date: 24/03/2025 |
Work in progress | 12% Completed
Renovation of entrance building|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Gallery and Toilet block|15% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Electrification|0% Completed
Compound wall works ongoing.
VIMAL T T |
Date: 10/03/2025 |
Work in progress | 12% Completed
Pond Renovation|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
Pond renovation works in progress.
VIMAL T T |
Date: 03/03/2025 |
Work in progress | 12% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Pond renovation works in progress.
VIMAL T T |
Date: 24/02/2025 |
Work in progress | 11% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Pond renovation works in progress.
VIMAL T T |
Date: 17/02/2025 |
Work in progress | 11% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 10/02/2025 |
Work in progress | 11% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 03/02/2025 |
Work in progress | 11% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Pond renovation works ongoing.
VIMAL T T |
Date: 27/01/2025 |
Work in progress | 10% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Retaining wall works ongoing.
VIMAL T T |
Date: 20/01/2025 |
Work in progress | 10% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Retaining wall works ongoing.
VIMAL T T |
Date: 13/01/2025 |
Work in progress | 9% Completed
Pond Renovation|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
Retaining wall works ongoing.
VIMAL T T |
Date: 06/01/2025 |
Work in progress | 9% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Retaining wall works ongoing.
VIMAL T T |
Date: 30/12/2024 |
Work in progress | 8% Completed
Pathway|2% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Renovation of entrance building|0% Completed
Retaining wall works ongoing.
VIMAL T T |
Date: 23/12/2024 |
Work in progress | 8% Completed
Gallery and Toilet block|15% Completed
Electrification|0% Completed
Renovation of entrance building|0% Completed
Pathway|2% Completed
Landscaping|0% Completed
Pond Renovation|0% Completed
Conservation of mosque|1% Completed
Consrvation of Kulappura|11% Completed
Compound Wall|0% Completed
Plumbing and Miscellaneous|0% Completed
Retaining wall excavation ongoing.
VIMAL T T |
Date: 16/12/2024 |
Work in progress | 8% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Compound wall works ongoing.
VIMAL T T |
Date: 09/12/2024 |
Work in progress | 8% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Compound wall works ongoing.
VIMAL T T |
Date: 02/12/2024 |
Work in progress | 8% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Compound wall works ongoing.
VIMAL T T |
Date: 25/11/2024 |
Work in progress | 7% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Pond restoration works ongoing.
VIMAL T T |
Date: 18/11/2024 |
Work in progress | 7% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Pond restoration works ongoing.
VIMAL T T |
Date: 11/11/2024 |
Work in progress | 7% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Pond restoration works ongoing.
VIMAL T T |
Date: 04/11/2024 |
Work in progress | 6% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
Pond restoration works ongoing.
VIMAL T T |
Date: 28/10/2024 |
Work in progress | 6% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 21/10/2024 |
Work in progress | 6% Completed
Pond Renovation|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 14/10/2024 |
Work in progress | 6% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 07/10/2024 |
Work in progress | 6% Completed
Pathway|2% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 30/09/2024 |
Work in progress | 6% Completed
Gallery and Toilet block|15% Completed
Electrification|0% Completed
Renovation of entrance building|0% Completed
Pathway|2% Completed
Landscaping|0% Completed
Pond Renovation|0% Completed
Conservation of mosque|1% Completed
Consrvation of Kulappura|11% Completed
Compound Wall|0% Completed
Plumbing and Miscellaneous|0% Completed
No activity at site.
VIMAL T T |
Date: 23/09/2024 |
Work in progress | 6% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Pond renovation works ongoing.
VIMAL T T |
Date: 16/09/2024 |
Work in progress | 5% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Plinth beam for pond renovation works completed.
VIMAL T T |
Date: 09/09/2024 |
Work in progress | 4% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 02/09/2024 |
Work in progress | 4% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 26/08/2024 |
Work in progress | 4% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 19/08/2024 |
Work in progress | 4% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 12/08/2024 |
Work in progress | 4% Completed
Gallery and Toilet block|15% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Electrification|0% Completed
No activity at site.
VIMAL T T |
Date: 05/08/2024 |
Work in progress | 4% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 29/07/2024 |
Work in progress | 4% Completed
Electrification|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Landscaping|0% Completed
Pathway|2% Completed
Renovation of entrance building|0% Completed
Gallery and Toilet block|15% Completed
No activity at site.
VIMAL T T |
Date: 22/07/2024 |
Work in progress | 4% Completed
Renovation of entrance building|0% Completed
Plumbing and Miscellaneous|0% Completed
Compound Wall|0% Completed
Consrvation of Kulappura|11% Completed
Conservation of mosque|1% Completed
Pond Renovation|0% Completed
Gallery and Toilet block|15% Completed
Landscaping|0% Completed
Pathway|2% Completed
Electrification|0% Completed
Restoration of entrance building 40% completed.