VIMAL T T |
Date: 24/03/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 17/03/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 10/03/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 03/03/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 24/02/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 17/02/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 10/02/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 03/02/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 27/01/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 20/01/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 13/01/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 06/01/2025 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 30/12/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 23/12/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 16/12/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 09/12/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 02/12/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 25/11/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 18/11/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 04/11/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 28/10/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 21/10/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 14/10/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 07/10/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 30/09/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 23/09/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 16/09/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 09/09/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 02/09/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 26/08/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 19/08/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 12/08/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 05/08/2024 |
Work in progress | 2% Completed
|0% Completed
No activity at site.
VIMAL T T |
Date: 29/07/2024 |
Work in progress | 2% Completed
|0% Completed
Open excavation of main building with formation levels completed.