Project | Thalassery Heritage Project - Sree Peralassery Temple |
---|---|
Project Code | KNRKIIFB122058P1 |
Main Project | Thalassery Heritage Project - Sree Peralassery Temple |
Work Category | Funding Agency | KIIFB |
Client Department | Tourism Department |
Description | Sree Peralassery Temple |
Status | On-going |
District | Kannur |
Executing Office | Office of GM1 |
TS Amount (Rs) | 26944220 |
TS Number | KIIDC/86/Thalassery Heritage-Phase 2- Sree Peralassery Temple/2020 |
Technical specification |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 08 Feb 2021 |
---|
VIMAL T T |
Date: 18/11/2024 |
Work in progress | 2% Completed
No activity at site..
VIMAL T T |
Date: 04/11/2024 |
Work in progress | 2% Completed
No activity at site..