Vishnu R
Date: 20/03/2025

Work in progress | 80% Completed

% |0% Completed

conservation of pond work ongoing

Attached images

img

Sijo Varghese
Date: 17/02/2025

Work in progress | 72% Completed

% |0% Completed

Temple Shelter works - Drainage works progressing, rest of the works completed. Conservation of Pond - 73 % completed, Compound walls, Light post and other related works are pending.

Sijo Varghese
Date: 26/07/2024

Work in progress | 50% Completed

% |0% Completed

Temple Shelter - Truss, Manglore tile works completed, adittional works such as drainage & Sadharhalli Pavings Progressing. Conservation of Pond - 35 % completed First Bill - 24.25 Lakhs - Passed

Sijo Varghese
Date: 02/04/2024

Work in progress | 18% Completed

% |0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 18% Completed

% |0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 18% Completed

% |0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 18% Completed

% |0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 18% Completed

% |0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 11/03/2024

Work in progress | 18% Completed

% |0% Completed

Nadapanthal / Temple Shelter - Truss work, Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 31/12/2023

Work in progress | 4% Completed

% |0% Completed

Foundation for Nadapanthal Completed.

Attached images

img img img

Vishnu R
Date: 20/03/2025

Work in progress | 0% Completed

conservation of pond work ongoing

Attached images

img

Sijo Varghese
Date: 17/02/2025

Work in progress | 0% Completed

Temple Shelter works - Drainage works progressing, rest of the works completed. Conservation of Pond - 73 % completed, Compound walls, Light post and other related works are pending.

Sijo Varghese
Date: 26/07/2024

Work in progress | 0% Completed

Temple Shelter - Truss, Manglore tile works completed, adittional works such as drainage & Sadharhalli Pavings Progressing. Conservation of Pond - 35 % completed First Bill - 24.25 Lakhs - Passed

Sijo Varghese
Date: 02/04/2024

Work in progress | 0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 25/03/2024

Work in progress | 0% Completed

Nadapanthal / Temple Shelter - Truss work, Manglore Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 11/03/2024

Work in progress | 0% Completed

Nadapanthal / Temple Shelter - Truss work, Tile Paving Completed. Electrical Works ongoing

Sijo Varghese
Date: 31/12/2023

Work in progress | 0% Completed

Foundation for Nadapanthal Completed.

Attached images

img img img