M A Faseela Nasar |
Date: 25/03/2025 |
Work has been completed | 100% Completed
Supplying and laying of Boulders|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
100% work completed
Attached images
M A Faseela Nasar |
Date: 17/03/2025 |
Work has been completed | 100% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
100% work completed
Attached images
M A Faseela Nasar |
Date: 10/03/2025 |
Work has been completed | 100% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
100% work completed
Attached images
M A Faseela Nasar |
Date: 03/03/2025 |
Work has been completed | 100% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
100% work completed
Attached images
M A Faseela Nasar |
Date: 24/02/2025 |
Work has been completed | 100% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
100% work completed.
Attached images
M A Faseela Nasar |
Date: 17/02/2025 |
Work has been completed | 100% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Physically completed
Attached images
M A Faseela Nasar |
Date: 10/02/2025 |
Work has been completed | 100% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Work completed
M A Faseela Nasar |
Date: 30/01/2025 |
Work has been completed | 100% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Work has been completed 100% . only some site clearance left.
Attached images
M A Faseela Nasar |
Date: 26/08/2024 |
Work in progress | 96% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.
M A Faseela Nasar |
Date: 19/08/2024 |
Work in progress | 96% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Out of 16 groynes 13 were completed and 3 numbers are in progress
Attached images
M A Faseela Nasar |
Date: 05/08/2024 |
Work in progress | 96% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.
Attached images
M A Faseela Nasar |
Date: 22/07/2024 |
Work in progress | 96% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.
Attached images
M A Faseela Nasar |
Date: 15/07/2024 |
Work in progress | 95% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress
M A Faseela Nasar |
Date: 24/06/2024 |
Work in progress | 95% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
4 T Groyne work in progress
M A Faseela Nasar |
Date: 17/06/2024 |
Work in progress | 95% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
4 T Groynes are in progress.
M A Faseela Nasar |
Date: 10/06/2024 |
Work in progress | 94% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress
M A Faseela Nasar |
Date: 20/05/2024 |
Work in progress | 93% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5
M A Faseela Nasar |
Date: 29/04/2024 |
Work in progress | 90% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5
M A Faseela Nasar |
Date: 22/04/2024 |
Work in progress | 89% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.
Attached images
M A Faseela Nasar |
Date: 15/04/2024 |
Work in progress | 89% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed
Attached images
M A Faseela Nasar |
Date: 08/04/2024 |
Work in progress | 89% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed
M A Faseela Nasar |
Date: 01/04/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
T groynes are in progress.
M A Faseela Nasar |
Date: 25/03/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.
M A Faseela Nasar |
Date: 18/03/2024 |
Work in progress | 88% Completed
Laying of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of geomat|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.
Attached images
M A Faseela Nasar |
Date: 18/03/2024 |
Work in progress | 88% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.
Attached images
M A Faseela Nasar |
Date: 11/03/2024 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW
Attached images
M A Faseela Nasar |
Date: 04/03/2024 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.
Attached images
M A Faseela Nasar |
Date: 26/02/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works
M A Faseela Nasar |
Date: 19/02/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.
Attached images
M A Faseela Nasar |
Date: 13/02/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
No work at site
M A Faseela Nasar |
Date: 03/02/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
NO WORK AT SITE.
M A Faseela Nasar |
Date: 29/01/2024 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Casting work is progressing only.
M A Faseela Nasar |
Date: 22/01/2024 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
only casting work is progressing
M A Faseela Nasar |
Date: 15/01/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing only.
Attached images
M A Faseela Nasar |
Date: 08/01/2024 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing.
Attached images
M A Faseela Nasar |
Date: 30/12/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
casting work is progressing only
M A Faseela Nasar |
Date: 23/12/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing.
M A Faseela Nasar |
Date: 18/12/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing only.
M A Faseela Nasar |
Date: 11/12/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
casting work is progressing
M A Faseela Nasar |
Date: 04/12/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
CASTIG WORK IS PROGRESSING
M A Faseela Nasar |
Date: 28/11/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is in progress
M A Faseela Nasar |
Date: 20/11/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing .
M A Faseela Nasar |
Date: 13/11/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is in progress
M A Faseela Nasar |
Date: 08/11/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing
M A Faseela Nasar |
Date: 30/10/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
casting work is progressing
M A Faseela Nasar |
Date: 25/10/2023 |
Work in progress | 88% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Only casting work is progressing
M A Faseela Nasar |
Date: 16/10/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
casting work is progressing
M A Faseela Nasar |
Date: 09/10/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting work is progressing
M A Faseela Nasar |
Date: 03/10/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
no work is going .
M A Faseela Nasar |
Date: 25/09/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
only casting work is progressing
M A Faseela Nasar |
Date: 18/09/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
No work is going at Vattachal site.
M A Faseela Nasar |
Date: 11/09/2023 |
Work in progress | 88% Completed
Laying of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of geomat|100% Completed
Casting of tetrapods|100% Completed
Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl
M A Faseela Nasar |
Date: 03/09/2023 |
Work in progress | 88% Completed
Laying of geomat|100% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Dismantling of stones|100% Completed
Earthwork Excavation|100% Completed
Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal
M A Faseela Nasar |
Date: 21/08/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Dismantling of stones|100% Completed
Earthwork Excavation|100% Completed
No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal
M A Faseela Nasar |
Date: 14/08/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal
M A Faseela Nasar |
Date: 07/08/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
No work at site due to weigh bridge complaint
M A Faseela Nasar |
Date: 31/07/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.
M A Faseela Nasar |
Date: 24/07/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
work was very slow due to the climatic conditions.
M A Faseela Nasar |
Date: 17/07/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
No work at site due to the climatic condition.
M A Faseela Nasar |
Date: 10/07/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
work was stopped due to heavy rain
M A Faseela Nasar |
Date: 03/07/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
No work at site due to bad climatic condition and rough sea
M A Faseela Nasar |
Date: 26/06/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
no work at site due to high tide.
M A Faseela Nasar |
Date: 19/06/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
work has been stopped last week due to high tide.
M A Faseela Nasar |
Date: 12/06/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
G5 and G12 groynes are in progress. work is very slow due high tide.
M A Faseela Nasar |
Date: 05/06/2023 |
Work in progress | 88% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Profile correction in progress for G12 and G13. 12 groynes completed out of 16
Attached images
M A Faseela Nasar |
Date: 29/05/2023 |
Work in progress | 88% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
G12 and G13 - boulder work in progress
M A Faseela Nasar |
Date: 22/05/2023 |
Work in progress | 87% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Boulder work in progress for G12 and G13 groyne
Attached images
M A Faseela Nasar |
Date: 15/05/2023 |
Work in progress | 87% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress
M A Faseela Nasar |
Date: 08/05/2023 |
Work in progress | 87% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress
Attached images
M A Faseela Nasar |
Date: 24/04/2023 |
Work in progress | 87% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods in progress Boulder work restarted for G12
Attached images
M A Faseela Nasar |
Date: 11/04/2023 |
Work in progress | 86% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Groyne work started at site today
GPS Cordinates
Latitude : 9.1925978
Longitude : 76.4379584
Accuracy : 474.0509948730469
Attached images
M A Faseela Nasar |
Date: 03/04/2023 |
Work in progress | 86% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods restarted at Vattachal from 30/03/2023
M A Faseela Nasar |
Date: 13/03/2023 |
Work in progress | 86% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
No work at site
GPS Cordinates
Latitude : 9.4774606
Longitude : 76.3385831
Accuracy : 2799.9990234375
M A Faseela Nasar |
Date: 06/03/2023 |
Work in progress | 86% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
No work at site
M A Faseela Nasar |
Date: 27/02/2023 |
Work in progress | 86% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
No work at site
M A Faseela Nasar |
Date: 20/02/2023 |
Work in progress | 86% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
No work at site
GPS Cordinates
Latitude : 9.3155843
Longitude : 76.396739
Accuracy : 1600
M A Faseela Nasar |
Date: 06/02/2023 |
Work in progress | 86% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
No work at site
GPS Cordinates
Latitude : 9.3964337
Longitude : 76.3536967
Accuracy : 135.91900634765625
M A Faseela Nasar |
Date: 30/01/2023 |
Work in progress | 86% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
no work at site
M A Faseela Nasar |
Date: 23/01/2023 |
Work in progress | 86% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
No work at site due to completion of agreed quantity.
M A Faseela Nasar |
Date: 16/01/2023 |
Work in progress | 86% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Work was very slow progress. Agreed qty has been finished for most of the items.
GPS Cordinates
Latitude : 9.4777125
Longitude : 76.3381613
Accuracy : 20
M A Faseela Nasar |
Date: 08/01/2023 |
Work in progress | 86% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Dismantling of stones|100% Completed
Earthwork Excavation|100% Completed
very slow progress of work at site due the decision pending of RE from KIIFB.
M A Faseela Nasar |
Date: 02/01/2023 |
Work in progress | 86% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
laying of boulders for T groynes are in very slow progress at site.
M A Faseela Nasar |
Date: 26/12/2022 |
Work in progress | 85% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Out of 16 numbers 12 completed . Agreed Quantity completed for boulders
M A Faseela Nasar |
Date: 19/12/2022 |
Work in progress | 85% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE
M A Faseela Nasar |
Date: 12/12/2022 |
Work in progress | 85% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE
M A Faseela Nasar |
Date: 05/12/2022 |
Work in progress | 80% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
M A Faseela Nasar |
Date: 28/11/2022 |
Work in progress | 80% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Dismantling of stones|100% Completed
Earthwork Excavation|100% Completed
1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16
M A Faseela Nasar |
Date: 24/11/2022 |
Work in progress | 0% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
56% of work completed.
GPS Cordinates
Latitude : 9.3932999
Longitude : 76.3534176
Accuracy : 1600
M A Faseela Nasar |
Date: 21/11/2022 |
Work in progress | 0% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Estimate quantity completed on 14.05.2022
M A Faseela Nasar |
Date: 30/10/2022 |
Work in progress | 0% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.
M A Faseela Nasar |
Date: 30/10/2022 |
Work in progress | 0% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Agreed quantity has been completed 100%. physically 80% completed
M A Faseela Nasar |
Date: 30/10/2022 |
Work in progress | 0% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Laying of boulders 80% completed physically. 98% of agreed quantity has been completed
M A Faseela Nasar |
Date: 30/10/2022 |
Work in progress | 0% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.
M A Faseela Nasar |
Date: 30/10/2022 |
Work has started | 6% Completed
Earthwork Excavation|100% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Dismantling of stones|100% Completed
Dismantling of stones has been completed 100% at Vattachal
Attached images
M A Faseela Nasar |
Date: 30/10/2022 |
Work in progress | 5% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
As per agreement quantity 100% casting works are completed at site.
M A Faseela Nasar |
Date: 23/10/2022 |
Work in progress | 0% Completed
Dismantling of stones|100% Completed
Earthwork Excavation|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity
M A Faseela Nasar |
Date: 17/10/2022 |
Work in progress | 0% Completed
Dismantling of stones|100% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.
M A Faseela Nasar |
Date: 09/10/2022 |
Work in progress | 77% Completed
Dismantling of stones|100% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.
Attached images
M A Faseela Nasar |
Date: 02/10/2022 |
Work in progress | 76% Completed
Dismantling of stones|100% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Laying of geomat|100% Completed
Earthwork Excavation|100% Completed
Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.
Attached images
M A Faseela Nasar |
Date: 01/10/2022 |
Work in progress | 10% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
Laying of Geo mat in the shore area was completed 90% at site
Attached images
M A Faseela Nasar |
Date: 26/09/2022 |
Work in progress | 76% Completed
Casting of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.
Attached images
M A Faseela Nasar |
Date: 21/09/2022 |
Work in progress | 75% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.
Attached images
M A Faseela Nasar |
Date: 16/06/2022 |
Work in progress | 0% Completed
Casting of tetrapods|100% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.
M A Faseela Nasar |
Date: 14/05/2022 |
Work in progress | 0% Completed
Supplying and laying of Boulders|100% Completed
Earthwork Excavation|100% Completed
Dismantling of stones|100% Completed
Laying of geomat|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|100% Completed
casting completed on may 2022 as per agreed quantity .
M A Faseela Nasar |
Date: 14/05/2022 |
Work in progress | 0% Completed
Supplying and laying of Boulders|100% Completed
Casting of tetrapods|100% Completed
Laying of tetrapods|100% Completed
Earthwork Excavation|100% Completed
Laying of geomat|100% Completed
Dismantling of stones|100% Completed
Agreed quantity completed on 14.05.2022.