M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Work completed

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 96% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 96% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 96% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 96% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 95% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 95% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 95% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 94% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 93% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 90% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 89% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 89% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 89% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 88% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Casting of tetrapods|100% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 88% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

No work at site

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

only casting work is progressing

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

casting work is progressing only

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

casting work is progressing

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is in progress

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is in progress

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 88% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting work is progressing

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

no work is going .

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

only casting work is progressing

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 88% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Casting of tetrapods|100% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 88% Completed

100.00% Laying of geomat|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Earthwork Excavation|100% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Earthwork Excavation|100% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 88% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 88% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 87% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 87% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 87% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 87% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 86% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Groyne work started at site today

GPS Cordinates

Latitude : 9.1925978

Longitude : 76.4379584

Accuracy : 474.0509948730469

Attached images

img

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 86% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 86% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

No work at site

GPS Cordinates

Latitude : 9.4774606

Longitude : 76.3385831

Accuracy : 2799.9990234375

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 86% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 86% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 86% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

No work at site

GPS Cordinates

Latitude : 9.3155843

Longitude : 76.396739

Accuracy : 1600

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 86% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

No work at site

GPS Cordinates

Latitude : 9.3964337

Longitude : 76.3536967

Accuracy : 135.91900634765625

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 86% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

no work at site

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 86% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 86% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

GPS Cordinates

Latitude : 9.4777125

Longitude : 76.3381613

Accuracy : 20

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 86% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Earthwork Excavation|100% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 86% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 85% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 85% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 85% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 80% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 80% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Earthwork Excavation|100% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

56% of work completed.

GPS Cordinates

Latitude : 9.3932999

Longitude : 76.3534176

Accuracy : 1600

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 0% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 0% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 0% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 0% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 0% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work has started | 6% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Dismantling of stones|100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 5% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 0% Completed

100.00% Dismantling of stones|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 0% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 77% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 76% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Earthwork Excavation|100% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 10% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 76% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 75% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 0% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 0% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Casting of tetrapods|100% Completed

casting completed on may 2022 as per agreed quantity .

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 0% Completed

100.00% Supplying and laying of Boulders|100% Completed

100.00% Casting of tetrapods|100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Earthwork Excavation|100% Completed

100.00% Laying of geomat|100% Completed

100.00% Dismantling of stones|100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 25/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 17/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 10/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 03/03/2025

Work has been completed | 0% Completed

100% work completed

Attached images

img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 0% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 0% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 0% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 0% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 0% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 24/02/2025

Work has been completed | 0% Completed

100% work completed.

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 0% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 0% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 0% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 0% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 0% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 17/02/2025

Work has been completed | 0% Completed

Physically completed

Attached images

img img

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 0% Completed

Work completed

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 0% Completed

Work completed

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 0% Completed

Work completed

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 0% Completed

Work completed

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 0% Completed

Work completed

M A Faseela Nasar
Date: 10/02/2025

Work has been completed | 0% Completed

Work completed

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 0% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 0% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 0% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 0% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 0% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 30/01/2025

Work has been completed | 0% Completed

Work has been completed 100% . only some site clearance left.

Attached images

img img

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done.

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 0% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 0% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 0% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 0% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 0% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 19/08/2024

Work in progress | 0% Completed

Out of 16 groynes 13 were completed and 3 numbers are in progress

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 0% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 0% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 0% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 0% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 0% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 05/08/2024

Work in progress | 0% Completed

work was restarted on 29/07/2024. Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 0% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 0% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 0% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 0% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 0% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 22/07/2024

Work in progress | 0% Completed

Out of 16 groynes 13 nos completed.2T laying in progress for G4,G12. 5T laying progress for G5.

Attached images

img img img

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 0% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 0% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 0% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 0% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 0% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 15/07/2024

Work in progress | 0% Completed

Dumping of boulders has been stopped last week for starting Arattupuzha. laying of tetrapods are in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 0% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 0% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 0% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 0% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 0% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 24/06/2024

Work in progress | 0% Completed

4 T Groyne work in progress

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 0% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 0% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 0% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 0% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 0% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 17/06/2024

Work in progress | 0% Completed

4 T Groynes are in progress.

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 0% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 0% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 0% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 0% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 0% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 10/06/2024

Work in progress | 0% Completed

Only 4 Groynes to be completed out of 16 numbers. 4 T groynes are in progress

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

work in progress. laying of tetrapod in progress for G4 G12 and G13. laying of boulders in progress for G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 0% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 0% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 0% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 0% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 0% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 29/04/2024

Work in progress | 0% Completed

laying of tetrapod in G13 for 5T completed. boulder dumping is progressing for G4 and G5

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

Laying of 5T tetrapods for Groyne G13 was completed. G4, G12 groynes are in progress.

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 15/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

Attached images

img img

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

Boulder dumping was completed for G12 and G13 Groynes. G4 and G5 not started yet. out of 16 groynes 12 completed

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 0% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 0% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 0% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 0% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 0% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 01/04/2024

Work in progress | 0% Completed

T groynes are in progress.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 25/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 18/03/2024

Work in progress | 0% Completed

Laying of tetrapod for G13 are in progress. boulder dumping in progress for G12 groyne.

Attached images

img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 0% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 0% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 0% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 0% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 0% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 11/03/2024

Work in progress | 0% Completed

OUT OF 16 GROYNES. 12 COMPLETED 4 T GROYNES N PROGRESS. LAYNG OF TETRAPOD N G13 WILL START TOMORROW

Attached images

img img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 0% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 0% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 0% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 0% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 0% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 04/03/2024

Work in progress | 0% Completed

Groyne work restarted last week. out of 16 nos 12 completed. 4 nos are in progress. Now section cut of G13 (T groyne) is progress at site.

Attached images

img img

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 0% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 0% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 0% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 0% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 0% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 26/02/2024

Work in progress | 0% Completed

T Groynes work has been started at Vattachal. out of 16 12 complteted and 4 ongoing * Weighbridge at Vattachal is using for both Arattupuzha and Vattachal works

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 0% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 0% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 0% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 0% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 0% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 19/02/2024

Work in progress | 0% Completed

work was restarted at vattachal due to the shortage of extended TOC. since the weighbridge at Arattupuzha was permanently break down for more than one year. On May 2023 work at Vattachal was stopped and boulders weighed from Vattachal weighbridge for Arattupuzha Works due site condition at Arattupuzha. Now work at Arattupuzha is almost complete except 2 groynes ( not started due to local issue). hence work at Vattachal was started on last week. 12 groyne completed out of 16 nos. ongoing - 4 nos.

Attached images

img

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/02/2024

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 0% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 0% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 0% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 0% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 0% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 03/02/2024

Work in progress | 0% Completed

NO WORK AT SITE.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 29/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 22/01/2024

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 15/01/2024

Work in progress | 0% Completed

Casting work is progressing only.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 0% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 0% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 0% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 0% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 0% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 08/01/2024

Work in progress | 0% Completed

Casting work is progressing.

Attached images

img

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 0% Completed

casting work is progressing only

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 0% Completed

casting work is progressing only

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 0% Completed

casting work is progressing only

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 0% Completed

casting work is progressing only

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 0% Completed

casting work is progressing only

M A Faseela Nasar
Date: 30/12/2023

Work in progress | 0% Completed

casting work is progressing only

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 0% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 0% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 0% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 0% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 0% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 23/12/2023

Work in progress | 0% Completed

Casting work is progressing.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 18/12/2023

Work in progress | 0% Completed

Casting work is progressing only.

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 11/12/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 0% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 0% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 0% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 0% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 0% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 04/12/2023

Work in progress | 0% Completed

CASTIG WORK IS PROGRESSING

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 28/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 0% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 0% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 0% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 0% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 0% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 20/11/2023

Work in progress | 0% Completed

Casting work is progressing .

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 13/11/2023

Work in progress | 0% Completed

Casting work is in progress

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 08/11/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 30/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 0% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 0% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 0% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 0% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 0% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 25/10/2023

Work in progress | 0% Completed

Only casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 16/10/2023

Work in progress | 0% Completed

casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 09/10/2023

Work in progress | 0% Completed

Casting work is progressing

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 0% Completed

no work is going .

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 0% Completed

no work is going .

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 0% Completed

no work is going .

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 0% Completed

no work is going .

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 0% Completed

no work is going .

M A Faseela Nasar
Date: 03/10/2023

Work in progress | 0% Completed

no work is going .

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 25/09/2023

Work in progress | 0% Completed

only casting work is progressing

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 0% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 0% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 0% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 0% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 0% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 18/09/2023

Work in progress | 0% Completed

No work is going at Vattachal site.

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 0% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 0% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 0% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 0% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 0% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 11/09/2023

Work in progress | 0% Completed

Arattupuzha weigh bridge is not working. Due to emergency at arattupuzha boulders are weighing from vattachal weigh bridge.so no work is going in vattacahl

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 0% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 0% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 0% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 0% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 0% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 03/09/2023

Work in progress | 0% Completed

Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 21/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 14/08/2023

Work in progress | 0% Completed

No work at site. Arattupuzha weighbridge is not working for the last 7 month. Hence, due to the emergency at Arattupuzha boulders are weighing from Vattachal weighbridge. So no work is going in Vattachal

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 0% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 0% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 0% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 0% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 0% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 07/08/2023

Work in progress | 0% Completed

No work at site due to weigh bridge complaint

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 0% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 0% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 0% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 0% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 0% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 31/07/2023

Work in progress | 0% Completed

Physical completion - 88% out of 16 Groynes 12 numbers were completed 100% . balance 4 numbers are in progress.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 0% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 0% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 0% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 0% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 0% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 24/07/2023

Work in progress | 0% Completed

work was very slow due to the climatic conditions.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 0% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 0% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 0% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 0% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 0% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 17/07/2023

Work in progress | 0% Completed

No work at site due to the climatic condition.

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

work was stopped due to heavy rain

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 0% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 0% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 0% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 0% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 0% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 03/07/2023

Work in progress | 0% Completed

No work at site due to bad climatic condition and rough sea

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 0% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 0% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 0% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 0% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 0% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 26/06/2023

Work in progress | 0% Completed

no work at site due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 0% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 0% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 0% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 0% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 0% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 19/06/2023

Work in progress | 0% Completed

work has been stopped last week due to high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 0% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 0% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 0% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 0% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 0% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 12/06/2023

Work in progress | 0% Completed

G5 and G12 groynes are in progress. work is very slow due high tide.

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 0% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 0% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 0% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 0% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 0% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 05/06/2023

Work in progress | 0% Completed

Profile correction in progress for G12 and G13. 12 groynes completed out of 16

Attached images

img

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 0% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 0% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 0% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 0% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 0% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 29/05/2023

Work in progress | 0% Completed

G12 and G13 - boulder work in progress

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 0% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 0% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 0% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 0% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 0% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 22/05/2023

Work in progress | 0% Completed

Boulder work in progress for G12 and G13 groyne

Attached images

img img

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 15/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1310.68 MT boulders reached at site. casting of terapods also in progress

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 08/05/2023

Work in progress | 0% Completed

Groyne works are in progress. last week 1255.22 MT boulders reached at site. casting of terapods also in progress

Attached images

img img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 0% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 0% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 0% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 0% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 0% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 24/04/2023

Work in progress | 0% Completed

Casting of tetrapods in progress Boulder work restarted for G12

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 0% Completed

Groyne work started at site today

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 0% Completed

Groyne work started at site today

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 0% Completed

Groyne work started at site today

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 0% Completed

Groyne work started at site today

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 0% Completed

Groyne work started at site today

Attached images

img

M A Faseela Nasar
Date: 11/04/2023

Work in progress | 0% Completed

Groyne work started at site today

Attached images

img

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 0% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 0% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 0% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 0% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 0% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 03/04/2023

Work in progress | 0% Completed

Casting of tetrapods restarted at Vattachal from 30/03/2023

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 13/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/03/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 27/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 20/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 06/02/2023

Work in progress | 0% Completed

No work at site

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 0% Completed

no work at site

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 0% Completed

no work at site

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 0% Completed

no work at site

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 0% Completed

no work at site

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 0% Completed

no work at site

M A Faseela Nasar
Date: 30/01/2023

Work in progress | 0% Completed

no work at site

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 0% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 0% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 0% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 0% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 0% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 23/01/2023

Work in progress | 0% Completed

No work at site due to completion of agreed quantity.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 0% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 0% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 0% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 0% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 0% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

M A Faseela Nasar
Date: 16/01/2023

Work in progress | 0% Completed

Work was very slow progress. Agreed qty has been finished for most of the items.

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 0% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 0% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 0% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 0% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 0% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 08/01/2023

Work in progress | 0% Completed

very slow progress of work at site due the decision pending of RE from KIIFB.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 0% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 0% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 0% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 0% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 0% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 02/01/2023

Work in progress | 0% Completed

laying of boulders for T groynes are in very slow progress at site.

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 0% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 0% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 0% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 0% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 0% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 26/12/2022

Work in progress | 0% Completed

Out of 16 numbers 12 completed . Agreed Quantity completed for boulders

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 19/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 12/12/2022

Work in progress | 0% Completed

100% of the agreed quantity was completed. But 4 numbers of T GROYNES are not completed physically due to insufficient quantity of boulders and tetrapods. Hence no work at site and waiting for RE

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 05/12/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 28/11/2022

Work in progress | 0% Completed

1. Dismantling - 100% completed 2. Earthwork - 100% completed 3. Supplying and laying of Boulders - 100% agreed quantity layed for Groynes. out of 16 only 12 numbers completed with the agreed quantity of boulders, Balance 4 numbers were not completed. 4. casting of tetrapods - 100% completed 5. Laying of tetrapod - 12 Groynes completed out of 16

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

56% of work completed.

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

56% of work completed.

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

56% of work completed.

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

56% of work completed.

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

56% of work completed.

M A Faseela Nasar
Date: 24/11/2022

Work in progress | 0% Completed

56% of work completed.

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 21/11/2022

Work in progress | 100% Completed

Estimate quantity completed on 14.05.2022

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Agreed quantity has been completed 100%. physically 80% completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Laying of boulders 80% completed physically. 98% of agreed quantity has been completed

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 80% Completed

Overall progress - 80% out of 16 numbers of Groynes 12 numbers completed. Another 4 Groynes are T sections, which are in progress. Current week Progress - laying of boulders in T groynes are progressing.

M A Faseela Nasar
Date: 30/10/2022

Work has started | 100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work has started | 100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work has started | 100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work has started | 100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work has started | 100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work has started | 100% Completed

Dismantling of stones has been completed 100% at Vattachal

Attached images

img

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 99% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 99% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 99% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 99% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 99% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 30/10/2022

Work in progress | 99% Completed

As per agreement quantity 100% casting works are completed at site.

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 80% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 80% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 80% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 80% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 80% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 23/10/2022

Work in progress | 80% Completed

Supplying and Laying of Boulders for last week - 2100 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to excess in quantity

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 78% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 78% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 78% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 78% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 78% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 17/10/2022

Work in progress | 78% Completed

Supplying and Laying of Boulders for last week - 1820 MT . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing. G4, G12, and G13 are T groynes which are stopped due to the quantity variations in calculation sheet from the actual quantity required due to some calculation mistakes and depth variations.

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 09/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 2195.93 T . Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 02/10/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 70 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 95% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 95% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 95% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 95% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 95% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 01/10/2022

Work in progress | 95% Completed

Laying of Geo mat in the shore area was completed 90% at site

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 26/09/2022

Work in progress | 0% Completed

Supplying and Laying of Boulders for last week - 1400 T Groyne G2, G3, G6, G7, G8, G9, G10, G11, G14, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. G1, G4, G12, G13 ongoing.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 0% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 0% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 0% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 0% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 0% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 21/09/2022

Work in progress | 0% Completed

T tetrapod casted - 0 nos. 5T tetrapod casted - 0 nos. Supplying and Laying of Boulders - nil Groyne G2, G3, G6, G7, G8, G9, G11, G15, G16 completed. 1881 5T tetrapods layed 5458 2T layed. no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 16/06/2022

Work in progress | 100% Completed

estimated quantity on 16.06.2022. Hence excess quantity needed to complete the profile of groyne.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

casting completed on may 2022 as per agreed quantity .

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

Agreed quantity completed on 14.05.2022.

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

casting completed on may 2022 as per agreed quantity .

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

casting completed on may 2022 as per agreed quantity .

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

casting completed on may 2022 as per agreed quantity .

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

casting completed on may 2022 as per agreed quantity .

M A Faseela Nasar
Date: 14/05/2022

Work in progress | 100% Completed

casting completed on may 2022 as per agreed quantity .