Project | CONSTRUCTION OF16 nos Groyne at vattachal in Arattupuzha Gp |
---|---|
Project Code | ALPKIIFB021921P1 |
Main Project | CONSTRUCTION OF16 nos Groyne at vattachal in Arattupuzha Gp |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | CONSTRUCTION OF 16 nos. Groynes in 1.8 kms at Arattupuzhaa GP in Haripad LA |
Status | On-going |
District | Alappuzha |
Executing Office | Office of GM1 |
TS Amount (Rs) | 250500000 |
TS Number | 256/KIIDC/KIIFB/GRONE/VATTACHAL/2017 |
Technical specification | |
Contractor | M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 23/02/2019 |
---|---|
Scheduled date of Completion as per agreement | 29 Jan 2022 |
Expected date of Completion | 31/01/2023 |
TS Date | 02 Jul 2019 |
---|---|
Date Of Site Handover | 30 Jul 2020 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Dismantling of stones | 432274.7 | 100 % | 4.32 L |
2 | Earthwork Excavation | 1341354.9 | 100 % | 0 |
3 | Supplying and laying of Boulders | 128559480.7 | 100 % | 0 |
4 | Casting of tetrapods | 127795000 | 100 % | 0 |
5 | Laying of tetrapods | 15998260 | 99 % | 158.38 L |
6 | Laying of geomat | 14191614 | 95 % | 134.82 L |
M A Faseela Nasar |
Date: 26/08/2024 |
Work in progress | 96% Completed
Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done..
M A Faseela Nasar |
Date: 26/08/2024 |
Work in progress | 96% Completed
Out of 16 groynes 15 numbers are completed and the last one in progress. Ramp work and replenishing has to be done..