| Meenu .E. S |
| Date: 30/12/2024 |
| Meenu .E. S |
| Date: 22/07/2024 |
| Meenu .E. S |
| Date: 03/06/2024 |
| Meenu .E. S |
| Date: 20/05/2024 |
| Meenu .E. S |
| Date: 06/05/2024 |
| Meenu .E. S |
| Date: 29/04/2024 |
| Meenu .E. S |
| Date: 15/04/2024 |
Work in progress | 3% Completed
|0% Completed
1.open foundation pier P1 Concrete work started 2.pier P3 Piling work started (2nos completed)
| Meenu .E. S |
| Date: 15/04/2024 |
| Meenu .E. S |
| Date: 15/04/2024 |
| Meenu .E. S |
| Date: 08/04/2024 |
| Meenu .E. S |
| Date: 01/04/2024 |
| Meenu .E. S |
| Date: 25/03/2024 |
| Meenu .E. S |
| Date: 18/03/2024 |
| Meenu .E. S |
| Date: 11/03/2024 |
| Meenu .E. S |
| Date: 04/03/2024 |
| Meenu .E. S |
| Date: 01/03/2024 |
Work in progress | 1% Completed
|0% Completed
1.Palakkad and Malappuram boundary fixing completed 2.Ring bund work in progress
| Arun V V |
| Date: 13/02/2023 |
Not Started
|0% Completed
Technical bid and financial bid was opened. Selection notice to be issued to the lowest bidder.
| Arun V V |
| Date: 30/01/2023 |
Not Started
|0% Completed
Technical bid and financial bid was opened. Selection notice to be issued to the lowest bidder.
| Arun V V |
| Date: 23/01/2023 |
Not Started
|0% Completed
Technical bid and financial bid was opened. Selection notice to be issued to the lowest bidder
| Arun V V |
| Date: 09/01/2023 |
Not Started
|0% Completed
Technical bid and financial bid was opened. Selection notice to be issued to the lowest bidder
| Arun V V |
| Date: 04/01/2023 |
Not Started
|0% Completed
Technical bid and financial bid was opened. Selection notice to be issued to the lowest bidder
| Arun V V |
| Date: 26/12/2022 |
Not Started
|0% Completed
PQ committee has been conducted on 16/12/2022.
| Arun V V |
| Date: 19/12/2022 |
Not Started
|0% Completed
PQ committee has been conducted on 16/12/2022.
| Arun V V |
| Date: 12/12/2022 |
Not Started
|0% Completed
Technical bid has been opened .Steps being taken to conduct the PQ committee
| Arun V V |
| Date: 05/12/2022 |
Not Started
|0% Completed
Technical bid has been opened .Steps being taken to conduct the PQ committee
| Arun V V |
| Date: 02/12/2022 |
Not Started
|0% Completed
Not yet started
| Anu IT Admin |
| Date: 10/10/2022 |
Not Started
|0% Completed
Retendered on 22/09/2022
| Anu IT Admin |
| Date: 03/10/2022 |
Not Started
|0% Completed
Retendered on 22/09/2022
| Anu IT Admin |
| Date: 26/09/2022 |
Not Started
|0% Completed
Re tendered on 22/09/2022
| Anu IT Admin |
| Date: 20/09/2022 |
Not Started
|0% Completed
To be retendered.(tender has become single tender in the first tendering itself)