Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Vishnu R
Date: 26/07/2024

Work in progress | 80% Completed

% |0% Completed

Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile - completed(for 1km) completed,STP pile -12 nos completed.STP top Slab completed ,WTP upto prominade level completed, substation first floor slab shuttering work completed,Retaining wall- 1060m Retaining wall base 1060m ,Parapet wall-960,Beam upto 1060m completed Slab rcc-960m ,Planter box 860m chainage completed, Culvert 4nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1060 m completed, Filling earth work 1010m completed,GSB laying upto 1010m completed ,storm water drain concrete 720m completed ,Kiosk 550 m ,690 m Gaseebo 550m work completed; Financial progress 59% physical 80%, All the works were partially affected by heavy rain

Attached images

img img img

Vishnu R
Date: 03/06/2024

Work in progress | 78% Completed

% |0% Completed

Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile -397(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 970m Retaining wall base 970m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 900 m completed ,storm water drain concrete 720 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre

Attached images

img img img

Vishnu R
Date: 27/05/2024

Work in progress | 75% Completed

% |0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 890 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre

Attached images

img img img

Vishnu R
Date: 21/05/2024

Work in progress | 74% Completed

% |0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 14/05/2024

Work in progress | 72% Completed

% |0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 840m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 14/05/2024

Work in progress | 72% Completed

% |0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 840m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 06/05/2024

Work in progress | 70% Completed

% |0% Completed

Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 916m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 29/04/2024

Work in progress | 68% Completed

% |0% Completed

Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 29/04/2024

Work in progress | 68% Completed

% |0% Completed

Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 22/04/2024

Work in progress | 66% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 600m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img

Vishnu R
Date: 18/04/2024

Work in progress | 65% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 900m Pile -391/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 600m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 19/03/2024

Work in progress | 62% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -378/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 620 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 11/03/2024

Work in progress | 60% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,200 m full strech mockup work al most completed,Kiosk 550 m ,Gaseebo 550m work ongoing ; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 11/03/2024

Work in progress | 60% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,Kiosk 550 m ,Gaseebo 550m work ongoing ; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 11/03/2024

Work in progress | 60% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,200 m full strech mockup work al most completed,Kiosk 550 m ,Gaseebo 550m work ongoing; Executed amount 343093893

Attached images

img img img img

Vishnu R
Date: 05/03/2024

Work in progress | 60% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -376/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed,Kiosk 550 m ,Gaseebo 550m work ongoing.

Attached images

img img

Vishnu R
Date: 05/03/2024

Work in progress | 60% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -376/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed ,Kiosk 550 m ,Gaseebo 550m work ongoing.

MIDHUN DAS
Date: 28/02/2024

Work in progress | 60% Completed

% |0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -374/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block 1 nos fully completed ,600m ch toilet block work Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed ,Koisk 3 nos completed/7nos, Gazebo (4nos) Foundation work ongoing,Benches fittings 29 nos completed/34.

Vishnu R
Date: 01/01/2024

Work in progress | 40% Completed

% |0% Completed

Armour layer 650-m Filter layer -650m Geo mat - 650m Gabion - 650m Pile -357/474, Retaining wall- 670m Retaining wall base 720m ,Parapet wall-660,Beam upto 660m completed Slab rcc-660m ,Planter box 30n0s, Culvert 2 nos were completed,Toilet block@ 220 m chainage- structural work completed,Finishing work on going ,Earthwork excavation upto 660 m completed, Filling earth work 350m completed,GSB laying 350 m completed ,storm water drain concrete 200 m completed ,200 m full strech mockup work ongoing.

Attached images

img img img

Vishnu R
Date: 14/11/2023

Work in progress | 30% Completed

% |0% Completed

mour layer 552-m Filter layer -576m Geo mat - 576m Gabion - 576m Pile -297/474, Retaining wall- 570m Retaining wall base 570m ,Parapet wall-360,Beam upto 420m completed Slab rcc-420m ,Planter box 20n0s, Culvert 2 nos were completed,Toilet block@ 220 m chainage- structural work completed,Finishing work pending ,Earthwork excavation upto 550 m completed, Filling earth work 350m completed,GSB laying started ,storm water drain concrete 50 m completed ,200 m full strech mockup work ongoing.

Attached images

img img img img

Vishnu R
Date: 17/10/2023

Work in progress | 26% Completed

% |0% Completed

rmour layer 540-m Filter layer -546m Geo mat - 546m Gabion - 556m Pile -258/474, Retaining wall- 570m Retaining wall base 570m Beam upto 300m completed Slab rcc-300 m ,Planter box 11n0s, Culvert 3 nos were completed,Toilet block Over head tank work progressing ,200 m full strech mockup work ongoing.

Attached images

img img img img img

MIDHUN DAS
Date: 14/09/2023

Work in progress | 20% Completed

% |0% Completed

Armour layer -394m Filter layer -407m Geo mat - 407m Gabion - 444m Pile -218/512 Retaining wall- 570m Retaining wall base 570m Beam upto 180m completed Slab rcc-122 m ,Planter box 2n0s, Culvert 2 nos were completed,Toilet block foundation work completed ,50 m full strech mockup work ongoing...All works were partially affected due to heavy rain.

Attached images

img img

Vishnu R
Date: 05/09/2023

Work in progress | 20% Completed

% |0% Completed

Armour layer -388m Filter layer -407m Geo mat - 407m Gabion - 440m Pile -213/512 Retaining wall- 570m Retaining wall base 570m Beam upto 122m completed Slab rcc-122 m ,Planter box 1n0s, Culvert 2 nos were completed,vToilet block footing work completed ,50 m full strech mockup work ongoing.

Attached images

img img

Vishnu R
Date: 08/08/2023

Work in progress | 16% Completed

% |0% Completed

Armour layer -216m Filter layer -234m Geo mat - 276m Gabion - 304m Pile -187/512 Retaining wall- 360m Retaining wall base _377.8m Beam upto 80m completed Slab rcc-25 m completed

Attached images

img img

Vishnu R
Date: 07/08/2023

Work in progress | 16% Completed

% |0% Completed

Armour layer -192m Filter layer -222m Geo mat - 246m Gabion - 298m Pile -185/512 Retaining wall- 360m Retaining wall base _377.8m Beam upto 80m completed Slab rcc-25 m completed

Attached images

img

Vishnu R
Date: 31/07/2023

Work in progress | 16% Completed

% |0% Completed

Armour layer-147 m completed ,Filter layer -180 m completed,Geo mat -180 m completed ,Gabbion 232 m completed,pile 174 nos completed ,Retaining wall -330 m completed,Retainin wall base-377.8 m completed,Beam up to 12 pile completed

Attached images

img img

Vishnu R
Date: 19/07/2023

Work in progress | 16% Completed

% |0% Completed

Armour layer 108m completed Filter layer 126m completed Geomatt 126m completed Gabion work 162m Pile 158 nos completed Retaining wall 240m completed,Retaining wall base 347.8m completed

Attached images

img img

Vishnu R
Date: 11/07/2023

Work in progress | 16% Completed

% |0% Completed

14 NOS OF PILES WERE CASTED,RETAINING WALL AND ARMOUR LAYER PACKING WORKS ARE GOING ON THE SITE

Attached images

img

Vishnu R
Date: 27/06/2023

Work in progress | 16% Completed

% |0% Completed

141 nos of pile were completed,250 m Retaining wall base concrete completed,50 m Retaining wall concrete complete, Armour layer packing work started Works were partially affected by the rain

Attached images

img img

Vishnu R
Date: 15/06/2023

Work in progress | 16% Completed

% |0% Completed

130 nos of pile were casted,200 m Retaining wall base concrete completed,20 m Retaining wall completed and the piling works were partially affected by Rain.

Attached images

img

Vishnu R
Date: 08/06/2023

Work in progress | 16% Completed

% |0% Completed

125 nos of pile were casted,100 m retaining wall base concrete completed

Attached images

img

Vishnu R
Date: 29/05/2023

Work in progress | 16% Completed

% |0% Completed

113 piles were casted,90 m Retaining wall base concrete completed

Attached images

img

Vishnu R
Date: 23/05/2023

Work in progress | 16% Completed

% |0% Completed

106 pile were casted till date, Routine test for grid b-16 pile completed,Routine pile load test for pile grid b48 ongoing

Attached images

img img

Vishnu R
Date: 15/05/2023

Work in progress | 16% Completed

% |0% Completed

98 piles were casted till date, Gabbion work and Retaining wall work on going

Attached images

img img img

Vishnu R
Date: 08/05/2023

Work in progress | 16% Completed

% |0% Completed

96 piles were casted,priliminary works for pile load test started,100 m Gabbion work completed, Retaining wall footing work started

Attached images

img img

Vishnu R
Date: 29/04/2023

Work in progress | 16% Completed

% |0% Completed

96 piles were casted, Retaining wall work an Gabbion work started

Attached images

img img img img img img

Vishnu R
Date: 11/04/2023

Work in progress | 16% Completed

% |0% Completed

94 nos of piles were casted and gabbion work ongoing

Attached images

img img

Vishnu R
Date: 04/04/2023

Work in progress | 14% Completed

% |0% Completed

93 piles were casted , gabbion work started

GPS Cordinates

Latitude : 11.8032527

Longitude : 75.4382964

Accuracy : 699.9990234375

Attached images

img

Vishnu R
Date: 27/03/2023

Work in progress | 14% Completed

% |0% Completed

Piling work is progressing. Total 88 piles were completed. Gabion and retaining wall work is also progressing

GPS Cordinates

Latitude : 11.8473692

Longitude : 75.4327994

Accuracy : 1143.0169677734375

Attached images

img img img

Vishnu R
Date: 21/03/2023

Work in progress | 14% Completed

% |0% Completed

Gabbion structure work started,piling work on progress total 78 nos completed, Retaining wall excavation,pcc,steel work started

GPS Cordinates

Latitude : 11.8028868

Longitude : 75.4379322

Accuracy : 1799.9990234375

Attached images

img img img

Vishnu R
Date: 13/03/2023

Work in progress | 14% Completed

% |0% Completed

Piling work on progress. Total 68 piles were completed.Excavation of Gabion work also progressing

GPS Cordinates

Latitude : 11.8032148

Longitude : 75.4375681

Accuracy : 1799.9990234375

Attached images

img img img

Vishnu R
Date: 06/03/2023

Work in progress | 14% Completed

% |0% Completed

Piling work is progress total 62 piles were comoleted

GPS Cordinates

Latitude : 11.8025399

Longitude : 75.4379322

Accuracy : 1700

Attached images

img img

Vishnu R
Date: 27/02/2023

Work in progress | 14% Completed

% |0% Completed

Work in progress. Total 54 piles were completed

GPS Cordinates

Latitude : 11.8032148

Longitude : 75.4375681

Accuracy : 1799.9990234375

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 14% Completed

% |0% Completed

Pile work on progress. Total 51 piles were completed

GPS Cordinates

Latitude : 11.8029058

Longitude : 75.4382964

Accuracy : 699.9990234375

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 13% Completed

% |0% Completed

Pile work is ongoing. Total 46 pile were completed.

GPS Cordinates

Latitude : 11.8029058

Longitude : 75.4382964

Accuracy : 699.9990234375

Attached images

img img

Vishnu R
Date: 06/02/2023

Work in progress | 12% Completed

% |0% Completed

Total 41 piles were completed.

GPS Cordinates

Latitude : 11.8026652

Longitude : 75.4379757

Accuracy : 20

Attached images

img img

Vishnu R
Date: 30/01/2023

Work in progress | 12% Completed

% |0% Completed

Piling work is ongoing, total 41 no of pile were casted.

GPS Cordinates

Latitude : 11.7714169

Longitude : 75.4683723

Accuracy : 104.0999984741211

Attached images

img

Vishnu R
Date: 25/01/2023

Work in progress | 11% Completed

% |0% Completed

Piling work is ongoing, total 36 no of pile were casted, Dismantling and Demolishing work in progress.

GPS Cordinates

Latitude : 11.8032148

Longitude : 75.4375681

Accuracy : 1700

Attached images

img img

Vishnu R
Date: 23/01/2023

Work in progress | 10% Completed

% |0% Completed

pile work is on going,32 nos of piles were casted

Attached images

img img img

Vishnu R
Date: 16/01/2023

Work in progress | 10% Completed

% |0% Completed

Piling work is ongoing, total 27 no of pile were casted, Dismantling and Demolishing work in progress.

GPS Cordinates

Latitude : 11.8032338

Longitude : 75.4379322

Accuracy : 1700

Attached images

img img img

Vishnu R
Date: 13/01/2023

Work in progress | 9% Completed

% |0% Completed

Piling work on going, Total 24 nos of piles were casted, Dismantling and Demolishing works in progress

GPS Cordinates

Latitude : 11.8032338

Longitude : 75.4379322

Accuracy : 1799.9990234375

Attached images

img img img

Vishnu R
Date: 09/01/2023

Work in progress | 8% Completed

% |0% Completed

20 nos of piles were casted, Dismantling and demolishing work is in progress

Attached images

img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 7% Completed

% |0% Completed

14 nos of pile casted, Dissmantling and Demolishing work is in progress

Attached images

img img

Vishnu R
Date: 26/12/2022

Work in progress | 6% Completed

% |0% Completed

5 nos of pile concrete completed, Dismantling and Demolishing works in progress

GPS Cordinates

Latitude : 11.8032338

Longitude : 75.4379322

Accuracy : 1799.9990234375

Attached images

img

Vishnu R
Date: 26/12/2022

Work in progress | 6% Completed

% |0% Completed

5 nos of pile concrete completed, Dismantling and Demolishing works in progress

GPS Cordinates

Latitude : 11.8028868

Longitude : 75.4379322

Accuracy : 1799.9990234375

Attached images

img img

Vishnu R
Date: 19/12/2022

Work in progress | 5% Completed

% |0% Completed

pile work and Demolishing and dismantling of Existing structures are going on the site

Attached images

img img img img

Vishnu R
Date: 12/12/2022

Work in progress | 5% Completed

% |0% Completed

Demolishing and dismantling work on progress , locating pile points in progress

Attached images

img img

Vishnu R
Date: 05/12/2022

Work in progress | 4% Completed

% |0% Completed

Initial pile load test completed, The promenade slab level is fixed as+4.5 and the same is marked at edakkad beach entrance side, Marking of pile point location are progress on the site

Attached images

img img img

Vishnu R
Date: 30/11/2022

Work in progress | 3% Completed

% |0% Completed

Dismantling and Demolishing work of existing structures are going on the site,3 no's of Test pile- concrete completed, Initial pile load test for test pile are progress on the site

Attached images

img img img img

Vishnu R
Date: 26/07/2024

Work in progress | 0% Completed

Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile - completed(for 1km) completed,STP pile -12 nos completed.STP top Slab completed ,WTP upto prominade level completed, substation first floor slab shuttering work completed,Retaining wall- 1060m Retaining wall base 1060m ,Parapet wall-960,Beam upto 1060m completed Slab rcc-960m ,Planter box 860m chainage completed, Culvert 4nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1060 m completed, Filling earth work 1010m completed,GSB laying upto 1010m completed ,storm water drain concrete 720m completed ,Kiosk 550 m ,690 m Gaseebo 550m work completed; Financial progress 59% physical 80%, All the works were partially affected by heavy rain

Attached images

img img img

Vishnu R
Date: 03/06/2024

Work in progress | 0% Completed

Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile -397(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 970m Retaining wall base 970m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 900 m completed ,storm water drain concrete 720 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre

Attached images

img img img

Vishnu R
Date: 27/05/2024

Work in progress | 0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 890 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre

Attached images

img img img

Vishnu R
Date: 21/05/2024

Work in progress | 0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 14/05/2024

Work in progress | 0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 840m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 14/05/2024

Work in progress | 0% Completed

Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 840m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 06/05/2024

Work in progress | 0% Completed

Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 916m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 29/04/2024

Work in progress | 0% Completed

Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 29/04/2024

Work in progress | 0% Completed

Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 22/04/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 600m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img

Vishnu R
Date: 18/04/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 900m Pile -391/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 600m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 19/03/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -378/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 620 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%

Attached images

img img img

Vishnu R
Date: 11/03/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,200 m full strech mockup work al most completed,Kiosk 550 m ,Gaseebo 550m work ongoing ; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 11/03/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,Kiosk 550 m ,Gaseebo 550m work ongoing ; Financial progress 42%

Attached images

img img img img

Vishnu R
Date: 11/03/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,200 m full strech mockup work al most completed,Kiosk 550 m ,Gaseebo 550m work ongoing; Executed amount 343093893

Attached images

img img img img

Vishnu R
Date: 05/03/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -376/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed,Kiosk 550 m ,Gaseebo 550m work ongoing.

Attached images

img img

Vishnu R
Date: 05/03/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -376/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed ,Kiosk 550 m ,Gaseebo 550m work ongoing.

MIDHUN DAS
Date: 28/02/2024

Work in progress | 0% Completed

Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -374/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block 1 nos fully completed ,600m ch toilet block work Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed ,Koisk 3 nos completed/7nos, Gazebo (4nos) Foundation work ongoing,Benches fittings 29 nos completed/34.

Vishnu R
Date: 01/01/2024

Work in progress | 0% Completed

Armour layer 650-m Filter layer -650m Geo mat - 650m Gabion - 650m Pile -357/474, Retaining wall- 670m Retaining wall base 720m ,Parapet wall-660,Beam upto 660m completed Slab rcc-660m ,Planter box 30n0s, Culvert 2 nos were completed,Toilet block@ 220 m chainage- structural work completed,Finishing work on going ,Earthwork excavation upto 660 m completed, Filling earth work 350m completed,GSB laying 350 m completed ,storm water drain concrete 200 m completed ,200 m full strech mockup work ongoing.

Attached images

img img img

Vishnu R
Date: 14/11/2023

Work in progress | 0% Completed

mour layer 552-m Filter layer -576m Geo mat - 576m Gabion - 576m Pile -297/474, Retaining wall- 570m Retaining wall base 570m ,Parapet wall-360,Beam upto 420m completed Slab rcc-420m ,Planter box 20n0s, Culvert 2 nos were completed,Toilet block@ 220 m chainage- structural work completed,Finishing work pending ,Earthwork excavation upto 550 m completed, Filling earth work 350m completed,GSB laying started ,storm water drain concrete 50 m completed ,200 m full strech mockup work ongoing.

Attached images

img img img img

Vishnu R
Date: 17/10/2023

Work in progress | 0% Completed

rmour layer 540-m Filter layer -546m Geo mat - 546m Gabion - 556m Pile -258/474, Retaining wall- 570m Retaining wall base 570m Beam upto 300m completed Slab rcc-300 m ,Planter box 11n0s, Culvert 3 nos were completed,Toilet block Over head tank work progressing ,200 m full strech mockup work ongoing.

Attached images

img img img img img

MIDHUN DAS
Date: 14/09/2023

Work in progress | 0% Completed

Armour layer -394m Filter layer -407m Geo mat - 407m Gabion - 444m Pile -218/512 Retaining wall- 570m Retaining wall base 570m Beam upto 180m completed Slab rcc-122 m ,Planter box 2n0s, Culvert 2 nos were completed,Toilet block foundation work completed ,50 m full strech mockup work ongoing...All works were partially affected due to heavy rain.

Attached images

img img

Vishnu R
Date: 05/09/2023

Work in progress | 0% Completed

Armour layer -388m Filter layer -407m Geo mat - 407m Gabion - 440m Pile -213/512 Retaining wall- 570m Retaining wall base 570m Beam upto 122m completed Slab rcc-122 m ,Planter box 1n0s, Culvert 2 nos were completed,vToilet block footing work completed ,50 m full strech mockup work ongoing.

Attached images

img img

Vishnu R
Date: 08/08/2023

Work in progress | 0% Completed

Armour layer -216m Filter layer -234m Geo mat - 276m Gabion - 304m Pile -187/512 Retaining wall- 360m Retaining wall base _377.8m Beam upto 80m completed Slab rcc-25 m completed

Attached images

img img

Vishnu R
Date: 07/08/2023

Work in progress | 0% Completed

Armour layer -192m Filter layer -222m Geo mat - 246m Gabion - 298m Pile -185/512 Retaining wall- 360m Retaining wall base _377.8m Beam upto 80m completed Slab rcc-25 m completed

Attached images

img

Vishnu R
Date: 31/07/2023

Work in progress | 0% Completed

Armour layer-147 m completed ,Filter layer -180 m completed,Geo mat -180 m completed ,Gabbion 232 m completed,pile 174 nos completed ,Retaining wall -330 m completed,Retainin wall base-377.8 m completed,Beam up to 12 pile completed

Attached images

img img

Vishnu R
Date: 19/07/2023

Work in progress | 0% Completed

Armour layer 108m completed Filter layer 126m completed Geomatt 126m completed Gabion work 162m Pile 158 nos completed Retaining wall 240m completed,Retaining wall base 347.8m completed

Attached images

img img

Vishnu R
Date: 11/07/2023

Work in progress | 0% Completed

14 NOS OF PILES WERE CASTED,RETAINING WALL AND ARMOUR LAYER PACKING WORKS ARE GOING ON THE SITE

Attached images

img

Vishnu R
Date: 27/06/2023

Work in progress | 0% Completed

141 nos of pile were completed,250 m Retaining wall base concrete completed,50 m Retaining wall concrete complete, Armour layer packing work started Works were partially affected by the rain

Attached images

img img

Vishnu R
Date: 15/06/2023

Work in progress | 0% Completed

130 nos of pile were casted,200 m Retaining wall base concrete completed,20 m Retaining wall completed and the piling works were partially affected by Rain.

Attached images

img

Vishnu R
Date: 08/06/2023

Work in progress | 0% Completed

125 nos of pile were casted,100 m retaining wall base concrete completed

Attached images

img

Vishnu R
Date: 29/05/2023

Work in progress | 0% Completed

113 piles were casted,90 m Retaining wall base concrete completed

Attached images

img

Vishnu R
Date: 23/05/2023

Work in progress | 0% Completed

106 pile were casted till date, Routine test for grid b-16 pile completed,Routine pile load test for pile grid b48 ongoing

Attached images

img img

Vishnu R
Date: 15/05/2023

Work in progress | 0% Completed

98 piles were casted till date, Gabbion work and Retaining wall work on going

Attached images

img img img

Vishnu R
Date: 08/05/2023

Work in progress | 0% Completed

96 piles were casted,priliminary works for pile load test started,100 m Gabbion work completed, Retaining wall footing work started

Attached images

img img

Vishnu R
Date: 29/04/2023

Work in progress | 0% Completed

96 piles were casted, Retaining wall work an Gabbion work started

Attached images

img img img img img img

Vishnu R
Date: 11/04/2023

Work in progress | 0% Completed

94 nos of piles were casted and gabbion work ongoing

Attached images

img img

Vishnu R
Date: 04/04/2023

Work in progress | 0% Completed

93 piles were casted , gabbion work started

Attached images

img

Vishnu R
Date: 27/03/2023

Work in progress | 0% Completed

Piling work is progressing. Total 88 piles were completed. Gabion and retaining wall work is also progressing

Attached images

img img img

Vishnu R
Date: 21/03/2023

Work in progress | 0% Completed

Gabbion structure work started,piling work on progress total 78 nos completed, Retaining wall excavation,pcc,steel work started

Attached images

img img img

Vishnu R
Date: 13/03/2023

Work in progress | 0% Completed

Piling work on progress. Total 68 piles were completed.Excavation of Gabion work also progressing

Attached images

img img img

Vishnu R
Date: 06/03/2023

Work in progress | 0% Completed

Piling work is progress total 62 piles were comoleted

Attached images

img img

Vishnu R
Date: 27/02/2023

Work in progress | 0% Completed

Work in progress. Total 54 piles were completed

Attached images

img img

Vishnu R
Date: 20/02/2023

Work in progress | 0% Completed

Pile work on progress. Total 51 piles were completed

Attached images

img img

Vishnu R
Date: 13/02/2023

Work in progress | 0% Completed

Pile work is ongoing. Total 46 pile were completed.

Attached images

img img

Vishnu R
Date: 06/02/2023

Work in progress | 0% Completed

Total 41 piles were completed.

Attached images

img img

Vishnu R
Date: 30/01/2023

Work in progress | 0% Completed

Piling work is ongoing, total 41 no of pile were casted.

Attached images

img

Vishnu R
Date: 25/01/2023

Work in progress | 0% Completed

Piling work is ongoing, total 36 no of pile were casted, Dismantling and Demolishing work in progress.

Attached images

img img

Vishnu R
Date: 23/01/2023

Work in progress | 0% Completed

pile work is on going,32 nos of piles were casted

Attached images

img img img

Vishnu R
Date: 16/01/2023

Work in progress | 0% Completed

Piling work is ongoing, total 27 no of pile were casted, Dismantling and Demolishing work in progress.

Attached images

img img img

Vishnu R
Date: 13/01/2023

Work in progress | 0% Completed

Piling work on going, Total 24 nos of piles were casted, Dismantling and Demolishing works in progress

Attached images

img img img

Vishnu R
Date: 09/01/2023

Work in progress | 0% Completed

20 nos of piles were casted, Dismantling and demolishing work is in progress

Attached images

img img img img

Vishnu R
Date: 03/01/2023

Work in progress | 0% Completed

14 nos of pile casted, Dissmantling and Demolishing work is in progress

Attached images

img img

Vishnu R
Date: 26/12/2022

Work in progress | 0% Completed

5 nos of pile concrete completed, Dismantling and Demolishing works in progress

Attached images

img

Vishnu R
Date: 26/12/2022

Work in progress | 0% Completed

5 nos of pile concrete completed, Dismantling and Demolishing works in progress

Attached images

img img

Vishnu R
Date: 19/12/2022

Work in progress | 0% Completed

pile work and Demolishing and dismantling of Existing structures are going on the site

Attached images

img img img img

Vishnu R
Date: 12/12/2022

Work in progress | 0% Completed

Demolishing and dismantling work on progress , locating pile points in progress

Attached images

img img

Vishnu R
Date: 05/12/2022

Work in progress | 0% Completed

Initial pile load test completed, The promenade slab level is fixed as+4.5 and the same is marked at edakkad beach entrance side, Marking of pile point location are progress on the site

Attached images

img img img

Vishnu R
Date: 30/11/2022

Work in progress | 0% Completed

Dismantling and Demolishing work of existing structures are going on the site,3 no's of Test pile- concrete completed, Initial pile load test for test pile are progress on the site

Attached images

img img img img