Vishnu R |
Date: 26/07/2024 |
Work in progress | 80% Completed
|0% Completed
Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile - completed(for 1km) completed,STP pile -12 nos completed.STP top Slab completed ,WTP upto prominade level completed, substation first floor slab shuttering work completed,Retaining wall- 1060m Retaining wall base 1060m ,Parapet wall-960,Beam upto 1060m completed Slab rcc-960m ,Planter box 860m chainage completed, Culvert 4nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1060 m completed, Filling earth work 1010m completed,GSB laying upto 1010m completed ,storm water drain concrete 720m completed ,Kiosk 550 m ,690 m Gaseebo 550m work completed; Financial progress 59% physical 80%, All the works were partially affected by heavy rain
Attached images
Vishnu R |
Date: 03/06/2024 |
Work in progress | 78% Completed
|0% Completed
Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile -397(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 970m Retaining wall base 970m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 900 m completed ,storm water drain concrete 720 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre
Attached images
Vishnu R |
Date: 27/05/2024 |
Work in progress | 75% Completed
|0% Completed
Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 890 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre
Attached images
Vishnu R |
Date: 21/05/2024 |
Work in progress | 74% Completed
|0% Completed
Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 14/05/2024 |
Work in progress | 72% Completed
|0% Completed
Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 840m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 14/05/2024 |
Work in progress | 72% Completed
|0% Completed
Armour layer 1030-m Filter layer -1030m Geo mat - 1030m Gabion - 1054m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 840m completed,GSB laying upto 840 m completed ,storm water drain concrete 690 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 06/05/2024 |
Work in progress | 70% Completed
|0% Completed
Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 916m Pile -401(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 960m Retaining wall base 960m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 29/04/2024 |
Work in progress | 68% Completed
|0% Completed
Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 29/04/2024 |
Work in progress | 68% Completed
|0% Completed
Armour layer 1010-m Filter layer -990m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 750m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 22/04/2024 |
Work in progress | 66% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 900m Pile -395/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 600m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 18/04/2024 |
Work in progress | 65% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 900m Pile -391/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 925m Retaining wall base 925m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 600m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 950m completed,GSB laying upto 770 m completed ,storm water drain concrete 660 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 19/03/2024 |
Work in progress | 62% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -378/401(for 1km),STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 620 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%
Attached images
Vishnu R |
Date: 11/03/2024 |
Work in progress | 60% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,200 m full strech mockup work al most completed,Kiosk 550 m ,Gaseebo 550m work ongoing ; Financial progress 42%
Attached images
Vishnu R |
Date: 11/03/2024 |
Work in progress | 60% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,Kiosk 550 m ,Gaseebo 550m work ongoing ; Financial progress 42%
Attached images
Vishnu R |
Date: 11/03/2024 |
Work in progress | 60% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -377/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 610 m completed ,200 m full strech mockup work al most completed,Kiosk 550 m ,Gaseebo 550m work ongoing; Executed amount 343093893
Attached images
Vishnu R |
Date: 05/03/2024 |
Work in progress | 60% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -376/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed,Kiosk 550 m ,Gaseebo 550m work ongoing.
Attached images
Vishnu R |
Date: 05/03/2024 |
Work in progress | 60% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -376/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed ,Kiosk 550 m ,Gaseebo 550m work ongoing.
MIDHUN DAS |
Date: 28/02/2024 |
Work in progress | 60% Completed
|0% Completed
Armour layer 880-m Filter layer -880m Geo mat - 880m Gabion - 890m Pile -374/401(for 1km),STP pile -12 nos completed.Retaining wall- 780m Retaining wall base 780m ,Parapet wall-740,Beam upto 680m completed Slab rcc-680m ,Planter box 500m chainage completed, Culvert 3nos were completed,Toilet block 1 nos fully completed ,600m ch toilet block work Finishing work pending ,Earthwork excavation upto 800 m completed, Filling earth work 650m completed,GSB laying upto 650 m completed ,storm water drain concrete 600 m completed ,Koisk 3 nos completed/7nos, Gazebo (4nos) Foundation work ongoing,Benches fittings 29 nos completed/34.
Vishnu R |
Date: 01/01/2024 |
Work in progress | 40% Completed
|0% Completed
Armour layer 650-m Filter layer -650m Geo mat - 650m Gabion - 650m Pile -357/474, Retaining wall- 670m Retaining wall base 720m ,Parapet wall-660,Beam upto 660m completed Slab rcc-660m ,Planter box 30n0s, Culvert 2 nos were completed,Toilet block@ 220 m chainage- structural work completed,Finishing work on going ,Earthwork excavation upto 660 m completed, Filling earth work 350m completed,GSB laying 350 m completed ,storm water drain concrete 200 m completed ,200 m full strech mockup work ongoing.
Attached images
Vishnu R |
Date: 14/11/2023 |
Work in progress | 30% Completed
|0% Completed
mour layer 552-m Filter layer -576m Geo mat - 576m Gabion - 576m Pile -297/474, Retaining wall- 570m Retaining wall base 570m ,Parapet wall-360,Beam upto 420m completed Slab rcc-420m ,Planter box 20n0s, Culvert 2 nos were completed,Toilet block@ 220 m chainage- structural work completed,Finishing work pending ,Earthwork excavation upto 550 m completed, Filling earth work 350m completed,GSB laying started ,storm water drain concrete 50 m completed ,200 m full strech mockup work ongoing.
Attached images
Vishnu R |
Date: 17/10/2023 |
Work in progress | 26% Completed
|0% Completed
rmour layer 540-m Filter layer -546m Geo mat - 546m Gabion - 556m Pile -258/474, Retaining wall- 570m Retaining wall base 570m Beam upto 300m completed Slab rcc-300 m ,Planter box 11n0s, Culvert 3 nos were completed,Toilet block Over head tank work progressing ,200 m full strech mockup work ongoing.
Attached images
MIDHUN DAS |
Date: 14/09/2023 |
Work in progress | 20% Completed
|0% Completed
Armour layer -394m Filter layer -407m Geo mat - 407m Gabion - 444m Pile -218/512 Retaining wall- 570m Retaining wall base 570m Beam upto 180m completed Slab rcc-122 m ,Planter box 2n0s, Culvert 2 nos were completed,Toilet block foundation work completed ,50 m full strech mockup work ongoing...All works were partially affected due to heavy rain.
Attached images
Vishnu R |
Date: 05/09/2023 |
Work in progress | 20% Completed
|0% Completed
Armour layer -388m Filter layer -407m Geo mat - 407m Gabion - 440m Pile -213/512 Retaining wall- 570m Retaining wall base 570m Beam upto 122m completed Slab rcc-122 m ,Planter box 1n0s, Culvert 2 nos were completed,vToilet block footing work completed ,50 m full strech mockup work ongoing.
Attached images
Vishnu R |
Date: 08/08/2023 |
Vishnu R |
Date: 07/08/2023 |
Vishnu R |
Date: 31/07/2023 |
Vishnu R |
Date: 19/07/2023 |
Vishnu R |
Date: 11/07/2023 |
Vishnu R |
Date: 27/06/2023 |
Vishnu R |
Date: 15/06/2023 |
Vishnu R |
Date: 08/06/2023 |
Vishnu R |
Date: 29/05/2023 |
Vishnu R |
Date: 23/05/2023 |
Vishnu R |
Date: 15/05/2023 |
Vishnu R |
Date: 08/05/2023 |
Vishnu R |
Date: 29/04/2023 |
Vishnu R |
Date: 11/04/2023 |
Vishnu R |
Date: 04/04/2023 |
Vishnu R |
Date: 27/03/2023 |
Vishnu R |
Date: 21/03/2023 |
Vishnu R |
Date: 13/03/2023 |
Vishnu R |
Date: 06/03/2023 |
Vishnu R |
Date: 27/02/2023 |
Vishnu R |
Date: 20/02/2023 |
Vishnu R |
Date: 13/02/2023 |
Vishnu R |
Date: 06/02/2023 |
Vishnu R |
Date: 30/01/2023 |
Vishnu R |
Date: 25/01/2023 |
Vishnu R |
Date: 23/01/2023 |
Vishnu R |
Date: 16/01/2023 |
Vishnu R |
Date: 13/01/2023 |
Vishnu R |
Date: 09/01/2023 |
Vishnu R |
Date: 03/01/2023 |
Vishnu R |
Date: 26/12/2022 |
Vishnu R |
Date: 26/12/2022 |
Vishnu R |
Date: 19/12/2022 |
Vishnu R |
Date: 12/12/2022 |
Vishnu R |
Date: 05/12/2022 |