Project | “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work” |
---|---|
Project Code | KNRKIIFB1220100P1 |
Main Project | “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work” |
Work Category | Funding Agency | KIIFB |
Client Department | Tourism Department |
Description | “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work”-Construction of Promenade structure around 1.4 km along Muzhappilangad beach. |
Status | |
District | Kannur |
Executing Office | Office of GM1 |
TS Amount (Rs) | 783216462 |
TS Number | 160/TS/KIIDC/2021 |
Technical specification | |
Contractor | M/S Uralungal Labour Contract Co-op Society Ltd (Mob: 9446002401) |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 22 Mar 2022 |
---|
Vishnu R |
Date: 26/07/2024 |
Work in progress | 80% Completed
Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile - completed(for 1km) completed,STP pile -12 nos completed.STP top Slab completed ,WTP upto prominade level completed, substation first floor slab shuttering work completed,Retaining wall- 1060m Retaining wall base 1060m ,Parapet wall-960,Beam upto 1060m completed Slab rcc-960m ,Planter box 860m chainage completed, Culvert 4nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1060 m completed, Filling earth work 1010m completed,GSB laying upto 1010m completed ,storm water drain concrete 720m completed ,Kiosk 550 m ,690 m Gaseebo 550m work completed; Financial progress 59% physical 80%, All the works were partially affected by heavy rain.
Attached images
Vishnu R |
Date: 03/06/2024 |
Work in progress | 78% Completed
Armour layer 1060-m Filter layer -1060m Geo mat - 1060m Gabion - 1060m Pile -397(for 1km) completed,STP pile -12 nos completed.STP base slab concrete completed ,Retaining wall- 970m Retaining wall base 970m ,Parapet wall-900,Beam upto 900m completed Slab rcc-900m ,Planter box 800m chainage completed, Culvert 3nos were completed,Toilet block@ 220 m chainage- structural work completed-Finishing work completed,600m ch toilet block work Exposed laterite work completed Finishing work pending ,Earthwork excavation upto 1000 m completed, Filling earth work 930m completed,GSB laying upto 900 m completed ,storm water drain concrete 720 m completed ,Kiosk 550 m ,Gaseebo 550m work completed; Financial progress 42%;Bottleneck;..1.The works were fully affected by heavy rain,2.WTP Structural details not completely shaired by CBRE,3.substatio stair details not provided,3.Stp inspection chamber prominade level opening and ladder details not provided by cbre.
Attached images