Project | “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work” |
---|---|
Project Code | KNRKIIFB1220100P1 |
Main Project | “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work” |
Work Category | Funding Agency | KIIFB |
Client Department | Tourism Department |
Description | “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work”-Construction of Promenade structure around 1.4 km along Muzhappilangad beach. |
Status | |
District | Kannur |
Executing Office | Office of GM1 |
TS Amount (Rs) | 783216462 |
TS Number | 160/TS/KIIDC/2021 |
Technical specification | |
Contractor | M/S Uralungal Labour Contract Co-op Society Ltd (Mob: 9446002401) |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 22 Mar 2022 |
---|
Vishnu R |
Date: 20/03/2025 |
Work in progress | 96% Completed
rmour layer 1240-m Filter layer -1240m Geo mat - 1240m Gabion - 1240m M40 Pile 470/470- completed,M30 pile 26/26 completed.STP mechanical work ongoing ,Retaining wall- 1240m Retaining wall base 1240m ,Parapet wall-1240,Beam upto 1240m completed Slab rcc-1240m ,Planter box 1240 m chainage completed, Culvert 5nos were completed,Toilet block@ 220 m chainage- completed,600m ch toilet block work completed ,Earthwork excavation upto 1240 m completed, Filling earth work 1240m completed,GSB laying upto 1240m completed ,storm water drain concrete 1240m completed ,Kiosk-completed, Gaseebo work completed; WTP- work completed Pending work :Light pole fittings, sculpture work, KWA connection Financial progress 84% physical 96%.
Attached images
Vishnu R |
Date: 18/02/2025 |
Work in progress | 93% Completed
Armour layer 1240-m Filter layer -1240m Geo mat - 1240m Gabion - 1240m M40 Pile 470/470- completed,M30 pile 26/26 completed.STP mechanical work ongoing ,Retaining wall- 1240m Retaining wall base 1240m ,Parapet wall-1240,Beam upto 1240m completed Slab rcc-1240m ,Planter box 1240 m chainage completed, Culvert 5nos were completed,Toilet block@ 220 m chainage- completed,600m ch toilet block work completed ,Earthwork excavation upto 1240 m completed, Filling earth work 1240m completed,GSB laying upto 1240m completed ,storm water drain concrete 1240m completed ,Kiosk-completed, Gaseebo work completed; WTP- water proofing work completed, Landscape- irrigation work completed, Substation electrical work remaining, Financial progress 84% physical 93%.
Attached images