“KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work”

Project “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work”
Project Code KNRKIIFB1220100P1
Main Project “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work”
Work Category
Funding Agency KIIFB
Client Department Tourism Department
Description “KIIFB Project Comprehensive Development of Muzhappilangad and Dharamadam Beach in Kannur District-Character Area 1-Civil work”-Construction of Promenade structure around 1.4 km along Muzhappilangad beach.
Status
District Kannur
Executing Office Office of GM1
TS Amount (Rs) 783216462
TS Number 160/TS/KIIDC/2021
Technical specification
Contractor M/S Uralungal Labour Contract Co-op Society Ltd (Mob: 9446002401)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 22 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vishnu R
Date: 20/03/2025

Work in progress | 96% Completed

rmour layer 1240-m Filter layer -1240m Geo mat - 1240m Gabion - 1240m M40 Pile 470/470- completed,M30 pile 26/26 completed.STP mechanical work ongoing ,Retaining wall- 1240m Retaining wall base 1240m ,Parapet wall-1240,Beam upto 1240m completed Slab rcc-1240m ,Planter box 1240 m chainage completed, Culvert 5nos were completed,Toilet block@ 220 m chainage- completed,600m ch toilet block work completed ,Earthwork excavation upto 1240 m completed, Filling earth work 1240m completed,GSB laying upto 1240m completed ,storm water drain concrete 1240m completed ,Kiosk-completed, Gaseebo work completed; WTP- work completed Pending work :Light pole fittings, sculpture work, KWA connection Financial progress 84% physical 96%.

Attached images

img img img img img

Vishnu R
Date: 18/02/2025

Work in progress | 93% Completed

Armour layer 1240-m Filter layer -1240m Geo mat - 1240m Gabion - 1240m M40 Pile 470/470- completed,M30 pile 26/26 completed.STP mechanical work ongoing ,Retaining wall- 1240m Retaining wall base 1240m ,Parapet wall-1240,Beam upto 1240m completed Slab rcc-1240m ,Planter box 1240 m chainage completed, Culvert 5nos were completed,Toilet block@ 220 m chainage- completed,600m ch toilet block work completed ,Earthwork excavation upto 1240 m completed, Filling earth work 1240m completed,GSB laying upto 1240m completed ,storm water drain concrete 1240m completed ,Kiosk-completed, Gaseebo work completed; WTP- water proofing work completed, Landscape- irrigation work completed, Substation electrical work remaining, Financial progress 84% physical 93%.

Attached images

img img img