| Project | CONSTRUCTION OF Groyne at KATTOOR |
|---|---|
| Project Code | ALPKIIFB021922P1 |
| Main Project | CONSTRUCTION OF Groyne at KATTOOR |
| Work Category | Funding Agency | KIIFB |
| Client Department | Water Resource Department |
| Description | CONSTRUCTION OF 34 number Groynes in 3.16 kms from Ch.168.465KM TO CH 171.627KM (Old CH 96.643KM TO CH 99.535 KM). |
| Status | On-going |
| District | Alappuzha |
| Executing Office | Office of GM1 |
| TS Amount (Rs) | 418350000 |
| TS Number | 218/KIIDC/KIIFB/Groyne/Kattoor/2017 |
| Technical specification | |
| Contractor | M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889) |
Project Progress StatusNotice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 |
Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Project Progress Status |
| Date of start of Package | 23/02/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 29 Jan 2022 |
| Expected date of Completion | 31/01/2023 |
| TS Date | 02 Jul 2019 |
|---|---|
| Date Of Site Handover | 30 Jul 2020 |
| # | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
|---|---|---|---|---|
| 1 | Dismantling of stones | 556578.88 | 100 % | 5.57 L |
| 2 | Earthwork excavation | 9056201.19 | 85 % | 76.98 L |
| 3 | Supply and laying of boulders | 220408088.2 | 100 % | 0 |
| 4 | Casting of tetrapods | 210670000 | 100 % | 0 |
| 5 | Laying of tetrapods | 28829320 | 82 % | 236.4 L |
| 6 | Laying of geomat | 20847438 | 30 % | 0 |
Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Silppa R |
| Date: 05/05/2025 |
Work in progress | 99% Completed
33nos Groynes are completed out of 34nos,Tetrapod laying is progressing in the remaining Groyne G34 and replenishing work is under progress.
Attached images
Notice: Failed saving metadata to metadataCache in /var/www/html/kiidcpms.webapiservices.in/kwa_pask_new/library/Zend/Db/Table/Abstract.php on line 837 Silppa R |
| Date: 05/05/2025 |
Work in progress | 99% Completed
33nos Groynes are completed out of 34nos,Tetrapod laying is progressing in the remaining Groyne G34 and replenishing work is under progress.
Attached images