Project | CONSTRUCTION OF Groyne at KATTOOR |
---|---|
Project Code | ALPKIIFB021922P1 |
Main Project | CONSTRUCTION OF Groyne at KATTOOR |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | CONSTRUCTION OF 34 number Groynes in 3.16 kms from Ch.168.465KM TO CH 171.627KM (Old CH 96.643KM TO CH 99.535 KM). |
Status | On-going |
District | Alappuzha |
Executing Office | Office of GM1 |
TS Amount (Rs) | 418350000 |
TS Number | 218/KIIDC/KIIFB/Groyne/Kattoor/2017 |
Technical specification | |
Contractor | M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 23/02/2019 |
---|---|
Scheduled date of Completion as per agreement | 29 Jan 2022 |
Expected date of Completion | 31/01/2023 |
TS Date | 02 Jul 2019 |
---|---|
Date Of Site Handover | 30 Jul 2020 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Dismantling of stones | 556578.88 | 100 % | 5.57 L |
2 | Earthwork excavation | 9056201.19 | 85 % | 76.98 L |
3 | Supply and laying of boulders | 220408088.2 | 100 % | 0 |
4 | Casting of tetrapods | 210670000 | 100 % | 0 |
5 | Laying of tetrapods | 28829320 | 82 % | 236.4 L |
6 | Laying of geomat | 20847438 | 30 % | 0 |
Lekshmi priya |
Date: 12/08/2024 |
Work in progress | 93% Completed
5T LAYING WORK PROGRESS IN G24 GROYNE..
Lekshmi priya |
Date: 12/08/2024 |
Work in progress | 93% Completed
5T LAYING WORK PROGRESS IN G24 GROYNE..