CONSTRUCTION OF Groyne at KATTOOR

Project CONSTRUCTION OF Groyne at KATTOOR
Project Code ALPKIIFB021922
Work Category Coastal Protection Works
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF 34 number Groynes in 3.16 kms from Ch.168.465KM TO CH 171.627KM (Old CH 96.643KM TO CH 99.535 KM).
Status On-going
District Alappuzha
Executing Office Office of GM1
AS Amount (Rs) 498590000
AS Number WRD001-07-PA-01
TS Amount (Rs) 418350000
TS Number te 218/KIIDC/KIIFB/Groyne/Kattoor/2017
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 CONSTRUCTION OF Groyne at KATTOOR Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 19 Nos Groynes are completed out of 34nos,10 Nos are progressing and 5nos to be started. Now the work progress is very slow due to design changes and excess quantity for various items.RE was prepared and submitted to HQ on 28.06.2022 Silppa R
03 Sep 2022 .20m groynes - 3 started out of 3 .30m Groynes-5nos started out of 7 .40m groynes - 19 nos started out of 24 .Total boulders quantity - 174010.85 MT boulders reached out of 174010 MT (100%) .2T TETRAPODS – 21553 nos (99.95%) casted out of 21562 nos. .5T TETRAPODS – 3144 (100%) nos. casted out of 3144 nos. .Geomat - 14015.5m2 .Earthwork Excavation - 31767.090m3 out of 42122 M3 Anu IT Admin

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/02/2019
Scheduled date of Completion of the Project 29 Jan 2022
Expected date of Completion 31/01/2023

Processing Dates

AS Date 23 Feb 2019
TS Date 02 Jul 2019

Other details

Project Officers View