Project | CONSTRUCTION OF Groyne at KATTOOR |
---|---|
Project Code | ALPKIIFB021922 |
Work Category | Coastal Protection Works | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | CONSTRUCTION OF 34 number Groynes in 3.16 kms from Ch.168.465KM TO CH 171.627KM (Old CH 96.643KM TO CH 99.535 KM). |
Status | On-going |
District | Alappuzha |
Executing Office | Office of GM1 |
AS Amount (Rs) | 498590000 |
AS Number | WRD001-07-PA-01 |
TS Amount (Rs) | 418350000 |
TS Number | te 218/KIIDC/KIIFB/Groyne/Kattoor/2017 |
Actual Project Completion Date | Date is not specified |
Coverage |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Sep 2022 | 19 Nos Groynes are completed out of 34nos,10 Nos are progressing and 5nos to be started. Now the work progress is very slow due to design changes and excess quantity for various items.RE was prepared and submitted to HQ on 28.06.2022 | Silppa R | |
03 Sep 2022 | .20m groynes - 3 started out of 3 .30m Groynes-5nos started out of 7 .40m groynes - 19 nos started out of 24 .Total boulders quantity - 174010.85 MT boulders reached out of 174010 MT (100%) .2T TETRAPODS – 21553 nos (99.95%) casted out of 21562 nos. .5T TETRAPODS – 3144 (100%) nos. casted out of 3144 nos. .Geomat - 14015.5m2 .Earthwork Excavation - 31767.090m3 out of 42122 M3 | Anu IT Admin |
Date of start of Project | 23/02/2019 |
---|---|
Scheduled date of Completion of the Project | 29 Jan 2022 |
Expected date of Completion | 31/01/2023 |
AS Date | 23 Feb 2019 |
---|---|
TS Date | 02 Jul 2019 |
Project Officers | View |
---|