UP-GRADATION OF GOVT ITI CHENGANNUR ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1- REV 3

Project UP-GRADATION OF GOVT ITI CHENGANNUR ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1- REV 3
Project Code KTMGOK121644P1
Main Project UP-GRADATION OF GOVT ITI CHENGANNUR ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1- REV 3
Work Category
Funding Agency KIIFB
Client Department KASE
Description It aims in providing Modern facilities in campus including International standard roads, pathways, gardens, lighting etc. Construction of a new Main building with Smart Class Rooms with integrated provisions for learning including modernized IT ready classrooms. The new Main building serves as an upgraded Administration Block for the Institute with all facilities ready to welcome International guests, Multinational Companies for setting up Production Centres.
Status On-going
District Alappuzha
Executing Office Office of GM1
TS Amount (Rs) 206445672
TS Number KASE-20/2016
Technical specification
Contractor M/s. Creators Constrictions (Mob: 9447023053)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/12/2016
Scheduled date of Completion as per agreement 29 Apr 2023
Expected date of Completion 20/07/2023

Processing Dates

TS Date 15 Feb 2020
Date Of Site Handover 23 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 ITI CHENGANNUR 186623471 99 % 0

Project Status Updations See All Status Updations

Joel J Varghese
Date: 26/07/2024

Work has been completed | 100% Completed

Work was completed on 25/06/2024 and the snag list has been prepared. The preparation of handing over documents in progress.

Attached images

img img img img

Joel J Varghese
Date: 26/07/2024

Work has been completed | 100% Completed

Work was completed on 25/06/2024 and the snag list has been prepared. The preparation of handing over documents in progress.

Attached images

img img img img