Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

UP-GRADATION OF GOVT ITI CHENGANNUR ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1- REV 3

Project UP-GRADATION OF GOVT ITI CHENGANNUR ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1- REV 3
Project Code KTMGOK121644
Work Category Buildings
Funding Agency KIIFB
Client Department KASE
Description It aims in providing Modern facilities in campus including International standard roads, pathways, gardens, lighting etc. Construction of a new Main building with Smart Class Rooms with integrated provisions for learning including modernized IT ready classrooms. The new Main building serves as an upgraded Administration Block for the Institute with all facilities ready to welcome International guests, Multinational Companies for setting up Production Centres.
Status On-going
District Alappuzha
Executing Office Office of GM1
AS Amount (Rs) 712200000
AS Number GO(Rt)No.1568/2016/Lbr
TS Amount (Rs) 206445672
TS Number KASE-20/2016
Actual Project Completion Date 29 Apr 2023
Coverage

Packages

No. Project Name Location View
1 UP-GRADATION OF GOVT ITI CHENGANNUR ON PAR WITH INTERNATIONAL STANDARDS - PHASE 1- REV 3 Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Aug 2023 Roadwork Levelling and GSB laying work is in progress. MAMATHA B S
16 Aug 2023 Road work- levelling work is in progress. GSB laying started. MAMATHA B S
11 Jul 2023 Finishing work is in progress MAMATHA B S
10 Jul 2023 On going works- Side drainage pcc completed, shuttering completed.. Half portion concrete completed.. Main Building - Hand rails@ second floor completed, toilet doors completed, Electrical fitting work progressing. Pump room- trusswork completed DG room truss worrk completed Water treatment plants installed Road work pending - Hindrance due to rain MAMATHA B S
01 Jul 2023 The work is almost in the finishing stage...The finishing civil works is ongoing. MAMATHA B S

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/12/2016
Scheduled date of Completion of the Project 24 Apr 2022
Expected date of Completion 30/06/2023

Processing Dates

AS Date 23 Dec 2016
TS Date 15 Feb 2020

Other details

Project Officers View