KIIDC IMPROVEMENT WORKS TO ANDHAKARATHODU IN THRIPUNITHURA MUNICIPALITY IN ERANAKULAM DISTRICT PROVIDING STREET LIGHT ALONG THE PATHWAY OF ANTHAKARATHODU

Project KIIDC IMPROVEMENT WORKS TO ANDHAKARATHODU IN THRIPUNITHURA MUNICIPALITY IN ERANAKULAM DISTRICT PROVIDING STREET LIGHT ALONG THE PATHWAY OF ANTHAKARATHODU
Project Code EKMKIIFB041823P1
Main Project KIIDC IMPROVEMENT WORKS TO ANDHAKARATHODU IN THRIPUNITHURA MUNICIPALITY IN ERANAKULAM DISTRICT PROVIDING STREET LIGHT ALONG THE PATHWAY OF ANTHAKARATHODU
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description Anthakarathode is a thode in between Konothupuzha and Chambakkara kayal.Length of thode is 2.17 km.The main aim of the project is clean and improve the thodu and regain it to its past glory. The improved condition of the thodu is expected to give a boost to tourism, navigation, and flood control and become the main attraction of the town.
Status On-going
District Ernakulam
Executing Office Office of GM1
TS Amount (Rs) 6000000
TS Number KIIDC/733/2020-AM2-Anthakarathode street lights
Technical specification
Contractor ESSJAY ELECTROLINKS PVT. LTD. (Mob: 9447152952)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/04/2018
Scheduled date of Completion as per agreement 09 Jun 2021
Expected date of Completion 15/11/2022

Processing Dates

TS Date 16 Oct 2020
Date Of Site Handover 10 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Laying of DWC pipe including Excavation and refilling 700000 100 % 7 L
2 Supplying and laying of armoured cable and copper conductor 797500 92 % 7.18 L
3 Excavation of Earth for foundations 2296.35 100 % 2296.35
4 RCC Form work and concreting 119465.19 100 % 1.19 L
5 Plastering and Painting works 24403.67 50 % 0.12 L
6 Erection of cast iron lamp post and LED lamp top luminaire 3157000 100 % 31.57 L
7 Earthing with GI earth plate 32300 99 % 0.32 L
8 Installation of feeder pillar 194100 100 % 1.94 L

Project Status Updations See All Status Updations

Joel J Varghese
Date: 26/07/2024

Work in progress | 98% Completed

Preparation of snag list and completion report preparation in the process.

Attached images

img

Joel J Varghese
Date: 26/07/2024

Work in progress | 98% Completed

Preparation of snag list and completion report preparation in the process.

Attached images

img