KIIFB Project- Construction of 13nos Groyne at Pathiyankara in bet.ch. 60.1 to 61.6 km at Thrikkunnapuzha

Project KIIFB Project- Construction of 13nos Groyne at Pathiyankara in bet.ch. 60.1 to 61.6 km at Thrikkunnapuzha
Project Code ALPKIIFB021920P1
Main Project KIIFB Project- Construction of 13nos Groyne at Pathiyankara in bet.ch. 60.1 to 61.6 km at Thrikkunnapuzha
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description Construction of Groyne at Thrikkunnapuzha, Haripad Constituency for protecting the seacoast of 1.50km length with 13 nos. of Groynes using boulders and tetrapods
Status On-going
District Alappuzha
Executing Office Office of GM1
TS Amount (Rs) 173300000
TS Number 255/KIIDC/KIIFB/GRONE/PATHIYANKARA/2017
Technical specification
Contractor M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/02/2019
Scheduled date of Completion as per agreement 29 Jan 2022
Expected date of Completion 31/01/2023

Processing Dates

TS Date 02 Jul 2019
Date Of Site Handover 30 Jul 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Dismantling of stones 346317.4 75 % 2.6 L
2 Earthwork excavation 893170.2 75 % 6.7 L
3 Supply and laying of Boulders 94421805 85 % 783.7 L
4 Casting of tetrapods 85291000 99 % 844.38 L
5 Laying of tetrapods 11743900 63 % 73.99 L
6 Laying of geomat 8153310 28 % 22.83 L

Project Status Updations See All Status Updations

Silppa R
Date: 23/09/2024

Work in progress | 95% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10..

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 95% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10..

Attached images

img