Silppa R |
Date: 05/05/2025 |
Silppa R |
Date: 07/04/2025 |
Silppa R |
Date: 01/04/2025 |
Silppa R |
Date: 25/03/2025 |
Silppa R |
Date: 17/03/2025 |
Silppa R |
Date: 10/03/2025 |
Work has been completed | 100% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
100% work Completed
Silppa R |
Date: 10/03/2025 |
Work has been completed | 100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Laying of geomat|28% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
100% work Completed.
Silppa R |
Date: 03/03/2025 |
Silppa R |
Date: 24/02/2025 |
Silppa R |
Date: 17/02/2025 |
Work in progress | 99% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Except for the ramp work ,99% of work has been completed and ramp work in progress
Attached images
Silppa R |
Date: 09/02/2025 |
Work in progress | 99% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Except for the ramp work ,99% of work has been completed and ramp work in progress .
Attached images
Silppa R |
Date: 23/09/2024 |
Work in progress | 95% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.
Attached images
Silppa R |
Date: 18/09/2024 |
Work in progress | 95% Completed
Dismantling of stones|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
Laying of geomat|28% Completed
10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.
Attached images
Silppa R |
Date: 09/09/2024 |
Work in progress | 95% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.
Attached images
Silppa R |
Date: 28/08/2024 |
Work in progress | 95% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.
Attached images
Silppa R |
Date: 19/08/2024 |
Work in progress | 95% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1
Attached images
Silppa R |
Date: 05/08/2024 |
Work in progress | 95% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
Supply and laying of Boulders|100% Completed
9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10
Attached images
Silppa R |
Date: 28/07/2024 |
Work in progress | 95% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10
Attached images
Silppa R |
Date: 22/07/2024 |
Work in progress | 95% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10
Attached images
Silppa R |
Date: 15/07/2024 |
Work in progress | 95% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10
Attached images
Silppa R |
Date: 08/07/2024 |
Work in progress | 94% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.
Attached images
Silppa R |
Date: 01/07/2024 |
Work in progress | 94% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.
Attached images
Silppa R |
Date: 24/06/2024 |
Work in progress | 94% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10
Attached images
Silppa R |
Date: 18/06/2024 |
Work in progress | 94% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.
Attached images
Silppa R |
Date: 10/06/2024 |
Work in progress | 94% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.
Attached images
Silppa R |
Date: 03/06/2024 |
Work in progress | 94% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.
Attached images
Silppa R |
Date: 27/05/2024 |
Work in progress | 94% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.
Attached images
Silppa R |
Date: 20/05/2024 |
Work in progress | 93% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11
Attached images
Silppa R |
Date: 12/05/2024 |
Work in progress | 93% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11
Attached images
Silppa R |
Date: 12/05/2024 |
Work in progress | 93% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11
Attached images
Silppa R |
Date: 06/05/2024 |
Work in progress | 93% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11
Attached images
Silppa R |
Date: 28/04/2024 |
Work in progress | 93% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12
Attached images
Silppa R |
Date: 22/04/2024 |
Work in progress | 92% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12
Attached images
Silppa R |
Date: 14/04/2024 |
Work in progress | 92% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12
Attached images
Silppa R |
Date: 08/04/2024 |
Work in progress | 92% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.
Attached images
Silppa R |
Date: 31/03/2024 |
Work in progress | 92% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.
Attached images
Silppa R |
Date: 24/03/2024 |
Work in progress | 91% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9
Attached images
Silppa R |
Date: 17/03/2024 |
Work in progress | 91% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.
Attached images
Silppa R |
Date: 10/03/2024 |
Work in progress | 91% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8
Attached images
Silppa R |
Date: 10/03/2024 |
Work in progress | 91% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8
Attached images
Silppa R |
Date: 03/03/2024 |
Work in progress | 87% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8
Attached images
Silppa R |
Date: 26/02/2024 |
Work in progress | 87% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8
Attached images
Silppa R |
Date: 19/02/2024 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.
Attached images
Silppa R |
Date: 12/02/2024 |
Work in progress | 86% Completed
Dismantling of stones|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Laying of geomat|28% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.
Attached images
Silppa R |
Date: 04/02/2024 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.
Attached images
Silppa R |
Date: 29/01/2024 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.
Attached images
Silppa R |
Date: 21/01/2024 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.
Attached images
Silppa R |
Date: 14/01/2024 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8
Attached images
Silppa R |
Date: 14/01/2024 |
Work in progress | 86% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8
Attached images
Silppa R |
Date: 07/01/2024 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.
Attached images
Silppa R |
Date: 31/12/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7
Attached images
Silppa R |
Date: 24/12/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.
Attached images
Silppa R |
Date: 16/12/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.
Attached images
Silppa R |
Date: 10/12/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing
Attached images
Silppa R |
Date: 03/12/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing
Attached images
Silppa R |
Date: 26/11/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing
Attached images
Silppa R |
Date: 19/11/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing
Attached images
Silppa R |
Date: 12/11/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing
Attached images
Silppa R |
Date: 06/11/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of geomat|28% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.
Attached images
Silppa R |
Date: 29/10/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
Supply and laying of Boulders|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.
Attached images
Silppa R |
Date: 29/10/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
Supply and laying of Boulders|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.
Attached images
Silppa R |
Date: 24/10/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress
Attached images
Silppa R |
Date: 24/10/2023 |
Work in progress | 86% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress
Attached images
Silppa R |
Date: 14/10/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress
Attached images
Silppa R |
Date: 07/10/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress
Attached images
Silppa R |
Date: 01/10/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress
Attached images
Silppa R |
Date: 23/09/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.
Attached images
Silppa R |
Date: 16/09/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 09/09/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 02/09/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 19/08/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 12/08/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 05/08/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 29/07/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 22/07/2023 |
Work in progress | 86% Completed
Dismantling of stones|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Laying of geomat|28% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 17/07/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 09/07/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 02/07/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 24/06/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress
Attached images
Silppa R |
Date: 18/06/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.
Attached images
Silppa R |
Date: 12/06/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.
Attached images
Silppa R |
Date: 05/06/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder
Attached images
Silppa R |
Date: 29/05/2023 |
Work in progress | 86% Completed
Dismantling of stones|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Laying of geomat|28% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder
Attached images
Silppa R |
Date: 22/05/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder
Attached images
Silppa R |
Date: 14/05/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder
Attached images
Silppa R |
Date: 08/05/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder
Attached images
Silppa R |
Date: 30/04/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.
Attached images
Silppa R |
Date: 23/04/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.
Attached images
Silppa R |
Date: 16/04/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.
Attached images
Silppa R |
Date: 09/04/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.
Attached images
Silppa R |
Date: 02/04/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
Dismantling of stones|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 26/03/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 19/03/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 12/03/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 04/03/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Silppa R |
Date: 26/02/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 18/02/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 12/02/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 05/02/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 29/01/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 23/01/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential
Attached images
Silppa R |
Date: 15/01/2023 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7
Attached images
Silppa R |
Date: 08/01/2023 |
Work in progress | 86% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7
Attached images
Silppa R |
Date: 01/01/2023 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.
Attached images
Silppa R |
Date: 25/12/2022 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.
Attached images
Silppa R |
Date: 19/12/2022 |
Work in progress | 86% Completed
Dismantling of stones|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Laying of geomat|28% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7
Attached images
Silppa R |
Date: 12/12/2022 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.
Attached images
Silppa R |
Date: 05/12/2022 |
Work in progress | 86% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.
Attached images
Silppa R |
Date: 29/11/2022 |
Work in progress | 86% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.
Attached images
Silppa R |
Date: 23/11/2022 |
Silppa R |
Date: 30/10/2022 |
Work in progress | 4% Completed
Laying of tetrapods|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items
Attached images
Silppa R |
Date: 23/10/2022 |
Work in progress | 4% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.
Attached images
Silppa R |
Date: 16/10/2022 |
Work in progress | 4% Completed
Supply and laying of Boulders|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.
Attached images
Silppa R |
Date: 09/10/2022 |
Work in progress | 63% Completed
Supply and laying of Boulders|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items
Attached images
Silppa R |
Date: 02/10/2022 |
Work in progress | 63% Completed
Laying of tetrapods|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.
Attached images
Silppa R |
Date: 25/09/2022 |
Work in progress | 63% Completed
Supply and laying of Boulders|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022
Attached images
Silppa R |
Date: 17/09/2022 |
Work in progress | 63% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
Supply and laying of Boulders|100% Completed
6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022
Attached images
Silppa R |
Date: 16/04/2022 |
Work in progress | 85% Completed
Laying of tetrapods|100% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Casting of tetrapods|99% Completed
As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022
Attached images
Silppa R |
Date: 09/04/2022 |
Work in progress | 43% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
As per agreement quantity , the component boulders were 83% completed.
Attached images
Silppa R |
Date: 05/04/2022 |
Work in progress | 86% Completed
Supply and laying of Boulders|100% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Earthwork excavation|75% Completed
Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.
Attached images
Silppa R |
Date: 12/08/2021 |
Work in progress | 43% Completed
Casting of tetrapods|99% Completed
Supply and laying of Boulders|100% Completed
Earthwork excavation|75% Completed
Laying of geomat|28% Completed
Dismantling of stones|100% Completed
Laying of tetrapods|100% Completed
As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.
Attached images
Silppa R |
Date: 03/08/2021 |
Work in progress | 4% Completed
Earthwork excavation|75% Completed
Laying of tetrapods|100% Completed
Casting of tetrapods|99% Completed
Dismantling of stones|100% Completed
Laying of geomat|28% Completed
Supply and laying of Boulders|100% Completed
As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022
Attached images