Silppa R
Date: 05/05/2025

Work has been completed | 100% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

100.00% Supply and laying of Boulders|100% Completed

100% work Completed

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 100% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 10/03/2025

Work has been completed | 100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100% work Completed

Silppa R
Date: 10/03/2025

Work has been completed | 100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

28.00% Laying of geomat|28% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

100% work Completed.

Silppa R
Date: 03/03/2025

Work has been completed | 100% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 100% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 99% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 99% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 95% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 95% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

28.00% Laying of geomat|28% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 95% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 95% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 95% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 95% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

100.00% Supply and laying of Boulders|100% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 95% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 95% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 95% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 94% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 94% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 94% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 94% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 94% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 94% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 94% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 93% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 93% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 93% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 93% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 93% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 92% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 92% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 92% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 92% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 91% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 91% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 91% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 91% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 87% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 87% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 86% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

28.00% Laying of geomat|28% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 86% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

28.00% Laying of geomat|28% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

100.00% Supply and laying of Boulders|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

100.00% Supply and laying of Boulders|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 86% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 86% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

28.00% Laying of geomat|28% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 86% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

28.00% Laying of geomat|28% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Dismantling of stones|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 04/03/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 26/02/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 86% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 86% Completed

100.00% Dismantling of stones|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

28.00% Laying of geomat|28% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 86% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 86% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 4% Completed

100.00% Laying of tetrapods|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 4% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 4% Completed

100.00% Supply and laying of Boulders|100% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 63% Completed

100.00% Supply and laying of Boulders|100% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 63% Completed

100.00% Laying of tetrapods|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 63% Completed

100.00% Supply and laying of Boulders|100% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 63% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

100.00% Supply and laying of Boulders|100% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 85% Completed

100.00% Laying of tetrapods|100% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

99.00% Casting of tetrapods|99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 43% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 86% Completed

100.00% Supply and laying of Boulders|100% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

75.00% Earthwork excavation|75% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 43% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Supply and laying of Boulders|100% Completed

75.00% Earthwork excavation|75% Completed

28.00% Laying of geomat|28% Completed

100.00% Dismantling of stones|100% Completed

100.00% Laying of tetrapods|100% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 4% Completed

75.00% Earthwork excavation|75% Completed

100.00% Laying of tetrapods|100% Completed

99.00% Casting of tetrapods|99% Completed

100.00% Dismantling of stones|100% Completed

28.00% Laying of geomat|28% Completed

100.00% Supply and laying of Boulders|100% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img

Silppa R
Date: 05/05/2025

Work has been completed | 0% Completed

100% work Completed

Attached images

img

Silppa R
Date: 05/05/2025

Work has been completed | 0% Completed

100% work Completed

Attached images

img

Silppa R
Date: 05/05/2025

Work has been completed | 0% Completed

100% work Completed

Attached images

img

Silppa R
Date: 05/05/2025

Work has been completed | 0% Completed

100% work Completed

Attached images

img

Silppa R
Date: 05/05/2025

Work has been completed | 0% Completed

100% work Completed

Attached images

img

Silppa R
Date: 05/05/2025

Work has been completed | 0% Completed

100% work Completed

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 07/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 01/04/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 25/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed.

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed.

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed.

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed.

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed.

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed.

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed

Silppa R
Date: 10/03/2025

Work has been completed | 0% Completed

100% work Completed

Silppa R
Date: 03/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 03/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 03/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 03/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 03/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 03/03/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 24/02/2025

Work has been completed | 0% Completed

100% work Completed.

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 17/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 09/02/2025

Work in progress | 0% Completed

Except for the ramp work ,99% of work has been completed and ramp work in progress .

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 23/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 18/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing at G12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 09/09/2024

Work in progress | 0% Completed

10nos Groynes are completed out of 13nos,3nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 28/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing atG12, G13.Tetrapod laying is progressing at G8 and G10.

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 19/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G1

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 05/08/2024

Work in progress | 0% Completed

9nos Groynes are completed out of 13nos,4nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 28/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 22/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 15/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 08/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 01/07/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 24/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 18/06/2024

Work in progress | 0% Completed

8nos Groynes are completed out of 13nos,5nos are in progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 10/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 03/06/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 27/05/2024

Work in progress | 0% Completed

8nos Groynes completed out of 13nos,5nos are progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G10.

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 20/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 12/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9,G10 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 06/05/2024

Work in progress | 0% Completed

7nos Groynes completed out of 13nos,6nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G8,G9 and G11

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 28/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 22/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 14/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 08/04/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 31/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G13,Tetrapod laying is progressing at G7 , G8,G9 and G12.

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 24/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 17/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 , G8 and G9.

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 10/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 03/03/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 26/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,7 nos are progressing Tetrapod casting is progressing and boulders dumping is progressing at G12&G13,Tetrapod laying is progressing at G7 and G8

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 19/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,6 nos are in progress and1no is to be started. Tetrapod casting is progressing and boulders dumping is progressing at G11&G12,Tetrapod laying is progressing at G7 and G8.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 12/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 04/02/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G9&10,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 29/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,5 nos are in progress and 2nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G8&G9,Tetrapod laying is progressing at G7.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 21/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7,G8&G9.

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 14/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 07/01/2024

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,4 nos are in progress and 3nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7&G8.

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 31/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 24/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 16/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Tetrapod casting is progressing and boulders dumping is progressing at G7.

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 10/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 03/12/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 26/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 19/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 12/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 06/11/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Only tetrapod casting is progressing.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 29/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 24/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 14/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 07/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 01/10/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 23/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work is started and progressing at G7,Tetrapod casting is also in progress.

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 16/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/09/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 19/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 12/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 05/08/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 29/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 22/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 17/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 09/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 02/07/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 24/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder. Tetrapod casting is in progress

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 18/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The boulders dumping work has now been stopped due to non-availability of Boulder.tetrapod casting is in progress.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 12/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 05/06/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. The work has now been stopped due to non-availability of Boulder.

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 19/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 04/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 04/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 04/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 04/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 04/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 04/03/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Silppa R
Date: 26/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 26/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 18/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 12/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 05/02/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 29/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 23/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. To carry out the rest of the Groynes fields with more numbers of tetra pods, sanction of the revised estimate is essential

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 15/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 08/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 01/01/2023

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 25/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 19/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 12/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 05/12/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 29/11/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ .Boulders dumping is progressing at Groyne G7.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 83% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 83% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 83% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 83% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 83% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 23/11/2022

Work in progress | 83% Completed

Boulders dumping is started.

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 30/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 23/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 16/10/2022

Work in progress | 63% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 09/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos,3nos are in progress and 4nos are to be started .Now no work can be done without RE sanction due to the design changes and change of various items

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 02/10/2022

Work in progress | 0% Completed

6nos Groynes are completed out of 13 Nos.No work can be done without RE sanction due to the design changes and change of various items.

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 0% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 0% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 0% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 0% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 0% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 25/09/2022

Work in progress | 0% Completed

Now work progress is very slow due to the design changes and excess quantity for various items.RE was submitted to HQ on 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 17/09/2022

Work in progress | 0% Completed

6nos Groynes completed out of 13nos,3 nos are in progress and 4nos are to be started. Now the work progress is very slow due to design changes and excess quantity for various items. RE was prepared and submitted to HQ 28.06.2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 16/04/2022

Work in progress | 99% Completed

As per agreement quantity ,the component tetrapod casting was completed 100% on 16-04-2022

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 83% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 83% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 83% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 83% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 83% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 09/04/2022

Work in progress | 83% Completed

As per agreement quantity , the component boulders were 83% completed.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 28% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 28% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 28% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 28% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 28% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 05/04/2022

Work in progress | 28% Completed

Geomat item was only used for some percentage. Currently the work is stopped and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 75% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 75% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 75% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 75% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 75% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 12/08/2021

Work in progress | 75% Completed

As per agreement quantity , the component earthwork excavation was 100% completed. and waiting for RE sanction.

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 75% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 75% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 75% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 75% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 75% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img

Silppa R
Date: 03/08/2021

Work in progress | 75% Completed

As per agreement quantity, the component Dismantling of stones were 100% completed on 03-08-2022

Attached images

img