Project | CONSTRUCTION OF REGULATOR CUM BRIDGE IN THE U/S OF PERINCHERIKADAVU ACROSS KUTTIADY RIVER IN KOZHIKODE DISTRICT |
---|---|
Project Code | CLTKIIFB09198P1 |
Main Project | CONSTRUCTION OF REGULATOR CUM BRIDGE IN THE U/S OF PERINCHERIKADAVU ACROSS KUTTIADY RIVER IN KOZHIKODE DISTRICT. |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | The project aims at preventing saline water intrusion from Arabian sea and there by protecting the agricultural lands scattered in various panchayath including Velom and Cheruvannur panchayath as wellas in the areas of vadakara panchayath.it plays a major role by assuring the drinking water availability provided by the KWA pumping stations at koorankode near Gulikapuzha Bridge. The RCB connects the Cheruvannur panchayath and Velom panchayath.it helps in providing irrigation for an ayacut area of 1720 hectare. |
Status | On-going |
District | Kozhikkode |
Executing Office | Office of GM1 |
TS Amount (Rs) | 639000000 |
TS Number | 24/TS/KIIDC/2019-20 |
Technical specification | |
Contractor | M/s TBAS Construction (Mob: 8547119550) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 07/09/2019 |
---|---|
Scheduled date of Completion as per agreement | 16 Mar 2022 |
Expected date of Completion | 01/03/2024 |
TS Date | 22 Nov 2019 |
---|---|
Date Of Site Handover | 17 Sep 2020 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | regulator cum bridge | 289963605.6 | 26 % | 724.91 L |
2 | bank protection works | 155192677.5 | 27 % | 403.5 L |
3 | road works | 66844928.1 | 0 % | 0 |
4 | switch room cum watchman room | 4484238 | 0 % | 0 |
5 | electrical works | 1937760 | 0 % | 0 |
6 | mechanical works | 92910923.97 | 0 % | 0 |
ANUPAMA S |
Date: 09/09/2024 |
Work has started | 0% Completed
Work has currently stopped due to delay in finalizing the ring bund design.
ANUPAMA S |
Date: 09/09/2024 |
Work has started | 0% Completed
Work has currently stopped due to delay in finalizing the ring bund design.