KIIFB PROJECT-THALASSERY HERITAGE PROJECT- PHASE 1 - HARBOUR TOWN CIRCUIT - JAGANNATH TEMPLE STREETCAPE

Project KIIFB PROJECT-THALASSERY HERITAGE PROJECT- PHASE 1 - HARBOUR TOWN CIRCUIT - JAGANNATH TEMPLE STREETCAPE
Project Code KNRKIIFB082011P1
Main Project KIIFB PROJECT-THALASSERY HERITAGE PROJECT- PHASE 1 - HARBOUR TOWN CIRCUIT - JAGANNATH TEMPLE STREETCAPE
Work Category
Funding Agency KIIFB
Client Department Tourism Department
Description The project is titled “Thalassery Heritage Project”, as Thalassery city as the epicenter of the project boundary established. The destinations majorly lie along Kannur district under Thalassery, Kannur and a few stretches up to Mananthavady in Wayanad district and Vadakara in Kozhikode district. The project will enhance the tourism experiences of Kerala, and will open up an entirely new region for economic development
Status On-going
District Kannur
Executing Office Office of GM1
TS Amount (Rs) 15633806
TS Number KIIDC/829/Thalassery Heritage-Phase1 -Jagannath Temple/2020
Technical specification
Contractor Joseph R.V (Mob: 8281885011)

Project Review

See All Review messages
Review Date Review Message Review Attended By
02 Feb 2013 Regarding WSS to Ranni, The fee has been remitted to KSEB and by March, 2013, trial run of the scheme can be carried out.The EE stated that out of 6 zones in the WSS to Ranni project, expenditure for the works under 5 zones is expected to be made in this Fin Year. Managing director,Technical Member,FM,CAO P&M,CE etc

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 09/08/2020
Scheduled date of Completion as per agreement 03 Aug 2022
Expected date of Completion Date is not specified

Processing Dates

TS Date 05 Nov 2020
Date Of Site Handover 08 Aug 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 jagannath temple-streetscape 14817938.56 100 % 47.42 L

Project Status Updations See All Status Updations

Ebin Solomon
Date: 22/04/2024

Work in progress | 99% Completed

jagannath temple-streetscape 100% Physically completed as per Estimate..

Ebin Solomon
Date: 22/04/2024

Work in progress | 99% Completed

jagannath temple-streetscape 100% Physically completed as per Estimate..