Review Date | Review Message | Review Added By | Review Attended By |
---|---|---|---|
02 Feb 2013 | Regarding WSS to Ranni, The fee has been remitted to KSEB and by March, 2013, trial run of the scheme can be carried out.The EE stated that out of 6 zones in the WSS to Ranni project, expenditure for the works under 5 zones is expected to be made in this Fin Year. | Managing director,Technical Member,FM,CAO P&M,CE etc | |
02 Feb 2013 | WSS to Ranni, The fee has been remitted to KSEB and by March, 2013, trial run of the scheme can be carried out. | Managing director,Technical Member,FM,CAO P&M,EE etc |