Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Review Messages

Review Date Review Message Review Added By Review Attended By
02 Feb 2013 Regarding WSS to Ranni, The fee has been remitted to KSEB and by March, 2013, trial run of the scheme can be carried out.The EE stated that out of 6 zones in the WSS to Ranni project, expenditure for the works under 5 zones is expected to be made in this Fin Year. Managing director,Technical Member,FM,CAO P&M,CE etc
02 Feb 2013 WSS to Ranni, The fee has been remitted to KSEB and by March, 2013, trial run of the scheme can be carried out. Managing director,Technical Member,FM,CAO P&M,EE etc