CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath.

Project CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath.
Project Code ALPKIIFB021919P1
Main Project CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath.
Work Category
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF 30 number Groynes in 3.2 kms Between CESCP 645 and 672 (Ch 77.34 km to Ch. 82.74 km) at Ambalapuzha South, North Panchayath and Punnapra South Panchayath with 305 m Sea wall
Status On-going
District Alappuzha
Executing Office Office of GM1
TS Amount (Rs) 439650000
TS Number 253/KIIDC/KIIFB/GROYNE/AMZA-PRA/S&N/2017
Technical specification
Contractor M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 23/02/2019
Scheduled date of Completion as per agreement 29 Jan 2022
Expected date of Completion 31/01/2023

Processing Dates

TS Date 02 Jul 2019
Date Of Site Handover 30 Jul 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Dismantling of stones 1253374.98 100 % 12.53 L
2 Earthwork Excavation 9880475.5 65 % 0
3 Supply and laying of Boulders 226628208.8 100 % 0
4 Casting of tetrapods 223478000 100 % 0
5 Laying of tetrapods 30952520 80 % 247.62 L
6 Laying of geomat 20828838 35 % 0

Project Status Updations See All Status Updations

Lekshmi priya
Date: 12/08/2024

Work in progress | 87% Completed

no work at site..

Lekshmi priya
Date: 12/08/2024

Work in progress | 87% Completed

no work at site..