Project | CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath. |
---|---|
Project Code | ALPKIIFB021919P1 |
Main Project | CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath. |
Work Category | Funding Agency | KIIFB |
Client Department | Water Resource Department |
Description | CONSTRUCTION OF 30 number Groynes in 3.2 kms Between CESCP 645 and 672 (Ch 77.34 km to Ch. 82.74 km) at Ambalapuzha South, North Panchayath and Punnapra South Panchayath with 305 m Sea wall |
Status | On-going |
District | Alappuzha |
Executing Office | Office of GM1 |
TS Amount (Rs) | 439650000 |
TS Number | 253/KIIDC/KIIFB/GROYNE/AMZA-PRA/S&N/2017 |
Technical specification | |
Contractor | M/S Ramalingam Construction Company Pvt.Ltd & Dharti Dredging and Infrastructure Ltd. (Mob: 8277366889) |
Project Progress Status |
Project Progress Status |
Date of start of Package | 23/02/2019 |
---|---|
Scheduled date of Completion as per agreement | 29 Jan 2022 |
Expected date of Completion | 31/01/2023 |
TS Date | 02 Jul 2019 |
---|---|
Date Of Site Handover | 30 Jul 2020 |
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Dismantling of stones | 1253374.98 | 100 % | 12.53 L |
2 | Earthwork Excavation | 9880475.5 | 65 % | 0 |
3 | Supply and laying of Boulders | 226628208.8 | 100 % | 0 |
4 | Casting of tetrapods | 223478000 | 100 % | 0 |
5 | Laying of tetrapods | 30952520 | 80 % | 247.62 L |
6 | Laying of geomat | 20828838 | 35 % | 0 |
Lekshmi priya |
Date: 12/08/2024 |
Work in progress | 87% Completed
no work at site..
Lekshmi priya |
Date: 12/08/2024 |
Work in progress | 87% Completed
no work at site..