CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath.

Project CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath.
Project Code ALPKIIFB021919
Work Category Coastal Protection Works
Funding Agency KIIFB
Client Department Water Resource Department
Description CONSTRUCTION OF 30 number Groynes in 3.2 kms Between CESCP 645 and 672 (Ch 77.34 km to Ch. 82.74 km) at Ambalapuzha South, North Panchayath and Punnapra South Panchayath with 305 m Sea wall
Status On-going
District Alappuzha
Executing Office Office of GM1
AS Amount (Rs) 533580000
AS Number WRD001-01-PA-01
TS Amount (Rs) 439650000
TS Number 253/KIIDC/KIIFB/GROYNE/AMZA-PRA/S&N/2017
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 CONSTRUCTION OF Groyne at Ambalapuzha South, North anchayath and Punnapra South Panchayath. Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 Now the work progress is very slow due to the design changes and excess of quantity for various items.RE was prepared and submitted to HQ on 28.06.2022 Silppa R

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/02/2019
Scheduled date of Completion of the Project 29 Jan 2021
Expected date of Completion 31/01/2023

Processing Dates

AS Date 23 Feb 2019
TS Date 02 Jul 2019

Other details