KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026

Project KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026
Project Code EKMTDK092180P1
Main Project KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026
Work Category
Funding Agency TDK
Client Department Water Resource Department
Description KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026
Status On-going
District Ernakulam
Executing Office Chellanam PMU
TS Amount (Rs) 25420000
TS Number G.O.(Rt)No.527/2021/WRD
Technical specification
Contractor M/S Uralungal Labour Contract Co-op Society Ltd (Mob: 9446002401)

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 08 Oct 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Component Progress Summary

# Component Name Component Amount Updated Percentage Updated Amount in Lakhs
1 Dismantling stones 14225 0 % 0
2 Tree cutting 500 100 % 500
3 Earthwork in Excavation 32520 0 % 0
4 Supplying and installation of Geomat for Seawall 73500 3 % 1470
5 Supplying and laying Core Layer(10-50 kg) 207593 100 % 1.35 L
6 Supplying and laying Toe layer(200-400) 41863.64 100 % 0.42 L
7 Supplying and laying Secondary Layer(150-200 kg) 103854.03 100 % 0
8 Supplying and laying Secondary layer(250-350 kg) 162996.53 100 % 0
9 Supplying and laying Toe Layer(350-700) 57393.7 100 % 0
10 Moulding and Supplying 2T Tetrapod(0.8 cum) 58783.75 0 % 0
11 Conveying and placing 2T Tetrapod(0.8 cum) 58783.75 100 % 0
12 Moulding and supplying 3T Tetrapod(1.2 cum) 77190.63 0 % 0
13 Conveying and placing 3T Tetrapod(1.2 cum) 77190.63 0 % 0
14 PCC concrete 1:4:8- Levelling course 3307.5 30 % 0
15 Walkway M25 grade for RCC 12755.5 18 % 0
16 Walkway M30 grade 12755.5 18 % 0
17 Centering and shuttering 26070 30 % 0
18 Reinforcement Work-HCR Fe500d or more 637775 30 % 0
19 DR Masonry 15030.75 0 % 0
20 Filling of quarry muck 11025 0 % 0

Project Status Updations See All Status Updations

Sreelakshmi S
Date: 26/07/2024

Work in progress | 95% Completed

Overall physical Progress is 90.50%* (relative to approved Revised Estimate-2 *Rs.362.65/-) & financial progress achieved is 89.03% (c.c 10th and part bill- submitted but not approved). 791637 MT (97%) boulders are supplied. 60982nos (100%) of 2T tetrapods are cast & 60139nos (98.62%) are placed. 51854nos (97.73%) of 3.5T tetrapods are cast & 51651nos (97.35%) are placed. 7386nos (100%) of 5T tetrapods are cast and 7350nos (99.51%) are placed. B-SG2, B-TG4, B-TG3, B-TG2, B-SG1 completed. Balance 1 groynes BTG1 work in progress 70% . 2T and 5T tetrapods are being placed in BTG1. Construction of walkway in progress, PCC and RCC work of walkway in both Harbor and Abad reaches are in progress. 3500m PCC and 3350m RCC completed in total..

Attached images

img img img

Sreelakshmi S
Date: 26/07/2024

Work in progress | 95% Completed

Overall physical Progress is 90.50%* (relative to approved Revised Estimate-2 *Rs.362.65/-) & financial progress achieved is 89.03% (c.c 10th and part bill- submitted but not approved). 791637 MT (97%) boulders are supplied. 60982nos (100%) of 2T tetrapods are cast & 60139nos (98.62%) are placed. 51854nos (97.73%) of 3.5T tetrapods are cast & 51651nos (97.35%) are placed. 7386nos (100%) of 5T tetrapods are cast and 7350nos (99.51%) are placed. B-SG2, B-TG4, B-TG3, B-TG2, B-SG1 completed. Balance 1 groynes BTG1 work in progress 70% . 2T and 5T tetrapods are being placed in BTG1. Construction of walkway in progress, PCC and RCC work of walkway in both Harbor and Abad reaches are in progress. 3500m PCC and 3350m RCC completed in total..

Attached images

img img img