Project | KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026 |
---|---|
Project Code | EKMTDK092180P1 |
Main Project | KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026 |
Work Category | Funding Agency | TDK |
Client Department | Water Resource Department |
Description | KIIFB PROJECT- REFORMATION OF DAMAGED SUNKEN SEA WALL AT CHELLANAM USING TETRAPODS AND RUBBLE IN BETWEEN CP STONE 976 AND 1052 FOR 10 KM STRETCHES ALONG CHELLANAM COAST IN ERNAKULAM DISTRICT - PHASE I FOR A LENGTH OF 7/350 KM IN BETWEEN CP 986 AND CP 1026 |
Status | On-going |
District | Ernakulam |
Executing Office | Chellanam PMU |
TS Amount (Rs) | 25420000 |
TS Number | G.O.(Rt)No.527/2021/WRD |
Technical specification | |
Contractor | M/S Uralungal Labour Contract Co-op Society Ltd (Mob: 9446002401) |
Project Progress Status |
Project Progress Status |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 08 Oct 2021 |
---|
# | Component Name | Component Amount | Updated Percentage | Updated Amount in Lakhs |
---|---|---|---|---|
1 | Dismantling stones | 14225 | 0 % | 0 |
2 | Tree cutting | 500 | 100 % | 500 |
3 | Earthwork in Excavation | 32520 | 0 % | 0 |
4 | Supplying and installation of Geomat for Seawall | 73500 | 3 % | 1470 |
5 | Supplying and laying Core Layer(10-50 kg) | 207593 | 100 % | 1.35 L |
6 | Supplying and laying Toe layer(200-400) | 41863.64 | 100 % | 0.42 L |
7 | Supplying and laying Secondary Layer(150-200 kg) | 103854.03 | 100 % | 0 |
8 | Supplying and laying Secondary layer(250-350 kg) | 162996.53 | 100 % | 0 |
9 | Supplying and laying Toe Layer(350-700) | 57393.7 | 100 % | 0 |
10 | Moulding and Supplying 2T Tetrapod(0.8 cum) | 58783.75 | 0 % | 0 |
11 | Conveying and placing 2T Tetrapod(0.8 cum) | 58783.75 | 100 % | 0 |
12 | Moulding and supplying 3T Tetrapod(1.2 cum) | 77190.63 | 0 % | 0 |
13 | Conveying and placing 3T Tetrapod(1.2 cum) | 77190.63 | 0 % | 0 |
14 | PCC concrete 1:4:8- Levelling course | 3307.5 | 30 % | 0 |
15 | Walkway M25 grade for RCC | 12755.5 | 18 % | 0 |
16 | Walkway M30 grade | 12755.5 | 18 % | 0 |
17 | Centering and shuttering | 26070 | 30 % | 0 |
18 | Reinforcement Work-HCR Fe500d or more | 637775 | 30 % | 0 |
19 | DR Masonry | 15030.75 | 0 % | 0 |
20 | Filling of quarry muck | 11025 | 0 % | 0 |
Sreelakshmi S |
Date: 26/07/2024 |
Work in progress | 95% Completed
Overall physical Progress is 90.50%* (relative to approved Revised Estimate-2 *Rs.362.65/-) & financial progress achieved is 89.03% (c.c 10th and part bill- submitted but not approved). 791637 MT (97%) boulders are supplied. 60982nos (100%) of 2T tetrapods are cast & 60139nos (98.62%) are placed. 51854nos (97.73%) of 3.5T tetrapods are cast & 51651nos (97.35%) are placed. 7386nos (100%) of 5T tetrapods are cast and 7350nos (99.51%) are placed. B-SG2, B-TG4, B-TG3, B-TG2, B-SG1 completed. Balance 1 groynes BTG1 work in progress 70% . 2T and 5T tetrapods are being placed in BTG1. Construction of walkway in progress, PCC and RCC work of walkway in both Harbor and Abad reaches are in progress. 3500m PCC and 3350m RCC completed in total..
Attached images
Sreelakshmi S |
Date: 26/07/2024 |
Work in progress | 95% Completed
Overall physical Progress is 90.50%* (relative to approved Revised Estimate-2 *Rs.362.65/-) & financial progress achieved is 89.03% (c.c 10th and part bill- submitted but not approved). 791637 MT (97%) boulders are supplied. 60982nos (100%) of 2T tetrapods are cast & 60139nos (98.62%) are placed. 51854nos (97.73%) of 3.5T tetrapods are cast & 51651nos (97.35%) are placed. 7386nos (100%) of 5T tetrapods are cast and 7350nos (99.51%) are placed. B-SG2, B-TG4, B-TG3, B-TG2, B-SG1 completed. Balance 1 groynes BTG1 work in progress 70% . 2T and 5T tetrapods are being placed in BTG1. Construction of walkway in progress, PCC and RCC work of walkway in both Harbor and Abad reaches are in progress. 3500m PCC and 3350m RCC completed in total..
Attached images