kitchen and staff quarters renovation works are ongoing
Swathy.G
06 Aug 2025
-Handrail installation is ongoing.
- Exhaust fittings in all bathrooms are completed.
- Air vent pipes from the duct have been installed; but the top portion of the vent can nit open due to rain.
- Roofing for the staff quarters are completed -construction of toilet at outside is ongoing
Swathy.G
17 Jul 2025
Ongoing works include handrail installation, roofing for staff quarters, and construction of toilets, with one toilet's foundation complete and another at brickwork level, Replacement of 14 distribution boards (DBs) and 5 earth leakage circuit breakers (ELCBs) has been completed.
Swathy.G
17 Jul 2025
Ongoing works include handrail installation, roofing for staff quarters, and construction of toilets, with one toilet's foundation complete and another at brickwork level.