| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Sep 2025 | building renovation works are ongoing | Swathy.G | |
| 29 Aug 2025 | kitchen and staff quarters renovation works are ongoing | Swathy.G | |
| 06 Aug 2025 | -Handrail installation is ongoing. - Exhaust fittings in all bathrooms are completed. - Air vent pipes from the duct have been installed; but the top portion of the vent can nit open due to rain. - Roofing for the staff quarters are completed -construction of toilet at outside is ongoing | Swathy.G | |
| 17 Jul 2025 | Ongoing works include handrail installation, roofing for staff quarters, and construction of toilets, with one toilet's foundation complete and another at brickwork level, Replacement of 14 distribution boards (DBs) and 5 earth leakage circuit breakers (ELCBs) has been completed. | Swathy.G | |