UPGRADATION OF GOVERNMENT ITI DHANUVACHAPURAM ON PAR WITH INTERNATIONAL STANDARDS
Project Code
TVMGOK121642
Work Category
Buildings
Funding Agency
KIIFB
Client Department
KASE
Description
It aims in providing Modern facilities in campus including International standard
roads, pathways, gardens, lighting etc. Construction of a new Main building with
Smart Class Rooms with integrated provisions for learning including modernized IT
ready classrooms. The new Main building serves as an upgraded Administration
Block for the Institute with all facilities ready to welcome International guests,
Multinational Companies for setting up Production Centres.
Status
On-going
District
Thiruvananthapuram
Executing Office
Office of GM1
AS Amount (Rs)
271600000
AS Number
GO(rt) No.1568/2016/Lbr
TS Amount (Rs)
118698400
TS Number
KASE-20/2016
Actual Project Completion Date
30 Sep 2022
Coverage
Packages
No.
Project Name
Location
View
1
UPGRADATION OF GOVERNMENT ITI DHANUVACHAPURAM ON PAR WITH INTERNATIONAL STANDARDS
Office of GM1
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
17 Sep 2022
The construction works of main building, sump tank, front gate, security cabin, sewage system its electrical works and ELV works were completed. Works of road, water supply rain water drainage are ongoing. the works of fire fighting is not started since approval is not got from SPV side till September 13 2022. SPV gave instructions to contractor to do the work as early as possible
Atheesh.P. Mohan
17 Sep 2022
COMPLETED WORKS
1)MAIN BUILDING CIVIL WORKS
2) MAIN BUILDING - ELECTRICAL WORKS
3) SUMP TANK CIVIL WORKS
4) FRONT GATE WITH SECURITY CABIN CIVIL WORKS
5) FRONT GATE WITH SECURITY CABIN M AND E WORKS
6) COMPOUND WALL
7) MAIN BUILDING 1 HVAC SYSTEM
8) MAIN BUILDING FURNITURE
9) MAIN BUILDING - ELV WORKS
10) NEW SMART CLASSROOM - ELV WORKS
11) LAND DEVELOPMENT
12) EXTERNAL SEWERAGE SYSTEM
13) EXTERNAL LIGHTING
14) DG, CHANGE OVER PANEL AND MODIFICATION OF EXISTING PANEL
15) RELOCATION OF W/S ELECTRICAL WORKS
16) EXISTING CLASS ROOM CONVERTED TO SMART CLASS ROOM
17) DEMOLITION WORKS
18) TEMPORARY BUILDING FOR STORE
19) EXISTING SMART CLASS ROOM- ELECTRICAL AND ELV WORKS
20) SIGNAGE AND BOARDS
ON GOING
1) ROAD AND ANCILLARY WORKS
2) EXTERNAL WATER SUPPLY
3) RAIN WATER DRAINAGE
NOT STARTED
1) MAIN BUILDING FIRE FIGHTING WORK