Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

UPGRADATION OF GOVERNMENT ITI DHANUVACHAPURAM ON PAR WITH INTERNATIONAL STANDARDS

Project UPGRADATION OF GOVERNMENT ITI DHANUVACHAPURAM ON PAR WITH INTERNATIONAL STANDARDS
Project Code TVMGOK121642
Work Category Buildings
Funding Agency KIIFB
Client Department KASE
Description It aims in providing Modern facilities in campus including International standard roads, pathways, gardens, lighting etc. Construction of a new Main building with Smart Class Rooms with integrated provisions for learning including modernized IT ready classrooms. The new Main building serves as an upgraded Administration Block for the Institute with all facilities ready to welcome International guests, Multinational Companies for setting up Production Centres.
Status On-going
District Thiruvananthapuram
Executing Office Office of GM1
AS Amount (Rs) 271600000
AS Number GO(rt) No.1568/2016/Lbr
TS Amount (Rs) 118698400
TS Number KASE-20/2016
Actual Project Completion Date 30 Sep 2022
Coverage

Packages

No. Project Name Location View
1 UPGRADATION OF GOVERNMENT ITI DHANUVACHAPURAM ON PAR WITH INTERNATIONAL STANDARDS Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 The construction works of main building, sump tank, front gate, security cabin, sewage system its electrical works and ELV works were completed. Works of road, water supply rain water drainage are ongoing. the works of fire fighting is not started since approval is not got from SPV side till September 13 2022. SPV gave instructions to contractor to do the work as early as possible Atheesh.P. Mohan
17 Sep 2022 COMPLETED WORKS 1)MAIN BUILDING CIVIL WORKS 2) MAIN BUILDING - ELECTRICAL WORKS 3) SUMP TANK CIVIL WORKS 4) FRONT GATE WITH SECURITY CABIN CIVIL WORKS 5) FRONT GATE WITH SECURITY CABIN M AND E WORKS 6) COMPOUND WALL 7) MAIN BUILDING 1 HVAC SYSTEM 8) MAIN BUILDING FURNITURE 9) MAIN BUILDING - ELV WORKS 10) NEW SMART CLASSROOM - ELV WORKS 11) LAND DEVELOPMENT 12) EXTERNAL SEWERAGE SYSTEM 13) EXTERNAL LIGHTING 14) DG, CHANGE OVER PANEL AND MODIFICATION OF EXISTING PANEL 15) RELOCATION OF W/S ELECTRICAL WORKS 16) EXISTING CLASS ROOM CONVERTED TO SMART CLASS ROOM 17) DEMOLITION WORKS 18) TEMPORARY BUILDING FOR STORE 19) EXISTING SMART CLASS ROOM- ELECTRICAL AND ELV WORKS 20) SIGNAGE AND BOARDS ON GOING 1) ROAD AND ANCILLARY WORKS 2) EXTERNAL WATER SUPPLY 3) RAIN WATER DRAINAGE NOT STARTED 1) MAIN BUILDING FIRE FIGHTING WORK Atheesh.P. Mohan

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/12/2016
Scheduled date of Completion of the Project 08 Mar 2021
Expected date of Completion 30/09/2022

Processing Dates

AS Date 23 Dec 2016
TS Date 27 Dec 2019

Other details

Project Officers View