Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 The construction works of main building, sump tank, front gate, security cabin, sewage system its electrical works and ELV works were completed. Works of road, water supply rain water drainage are ongoing. the works of fire fighting is not started since approval is not got from SPV side till September 13 2022. SPV gave instructions to contractor to do the work as early as possible Atheesh.P. Mohan
17 Sep 2022 COMPLETED WORKS 1)MAIN BUILDING CIVIL WORKS 2) MAIN BUILDING - ELECTRICAL WORKS 3) SUMP TANK CIVIL WORKS 4) FRONT GATE WITH SECURITY CABIN CIVIL WORKS 5) FRONT GATE WITH SECURITY CABIN M AND E WORKS 6) COMPOUND WALL 7) MAIN BUILDING 1 HVAC SYSTEM 8) MAIN BUILDING FURNITURE 9) MAIN BUILDING - ELV WORKS 10) NEW SMART CLASSROOM - ELV WORKS 11) LAND DEVELOPMENT 12) EXTERNAL SEWERAGE SYSTEM 13) EXTERNAL LIGHTING 14) DG, CHANGE OVER PANEL AND MODIFICATION OF EXISTING PANEL 15) RELOCATION OF W/S ELECTRICAL WORKS 16) EXISTING CLASS ROOM CONVERTED TO SMART CLASS ROOM 17) DEMOLITION WORKS 18) TEMPORARY BUILDING FOR STORE 19) EXISTING SMART CLASS ROOM- ELECTRICAL AND ELV WORKS 20) SIGNAGE AND BOARDS ON GOING 1) ROAD AND ANCILLARY WORKS 2) EXTERNAL WATER SUPPLY 3) RAIN WATER DRAINAGE NOT STARTED 1) MAIN BUILDING FIRE FIGHTING WORK Atheesh.P. Mohan