KIIFB PROJECT: CONSTRUCTION OF REGULATOR WITH LOCK ACROSS ANCHARAKANDY RIVER AT PARAPRAM IN PINARAYI PANCHAYATH, KANNUR DISTRICT

Project KIIFB PROJECT: CONSTRUCTION OF REGULATOR WITH LOCK ACROSS ANCHARAKANDY RIVER AT PARAPRAM IN PINARAYI PANCHAYATH, KANNUR DISTRICT
Project Code KNRKIIFB07204
Work Category RCB(Regulator Cum Bridge)
Funding Agency KIIFB
Client Department Water Resource Department
Description The regulator across Anjarakandy River at Parapram in Pinarayi Panchayath is proposed in view of preventing saltwater intrusion into about 1200 acres of land spread in Pinarayi, Vengad, Ancharakandy and Peralasseri villages and to use the fresh water on upstream side of the regulator for irrigation. The implementation of the project will solve the drinking water scarcity in this area and in similar other areas in the basin. The Regulator connects Peralassery and Pinarayi panchaths by means of foot bridge .it plays a major role by assuring the drinking water availability provided by the KWA pumping stations at Keezzhallur .
Status Physically Completed
District Kannur
Executing Office Office of GM1
AS Amount (Rs) 463700000
AS Number WRD022-11/APR-6/2020/KIIFB
TS Amount (Rs) 498385599
TS Number KIIDC/300/KIIFB-RCB-ANJKY/2018-19
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 KIIFB PROJECT: CONSTRUCTION OF REGULATOR WITH LOCK ACROSS ANCHARAKANDY RIVER AT PARAPRAM IN PINARAYI PANCHAYATH, KANNUR DISTRICT Office of GM1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Sep 2022 Plastering and Tile works for generator switch room completed. Pier,P4 to P5 , Foot bridge slab and beam completed. RR Masonry in right bank, U/S , work in progress. Pier,P6 , further works were delayed due to heavy rainfall, construction of earth bund started again and hope to finish other works as soon as possible. Sijo Varghese
17 Sep 2022 Plastering and Tile works for generator switch room completed. Pier,P4 to P5 , Foot bridge slab and beam completed. Pier,P6 , further works delayed due to heavy rainfall. Hope, to start it as soon as possible. Sijo Varghese

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/11/2020
Scheduled date of Completion of the Project 21 Nov 2022
Expected date of Completion 30/06/2023