Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Sep 2022 | Plastering and Tile works for generator switch room completed. Pier,P4 to P5 , Foot bridge slab and beam completed. RR Masonry in right bank, U/S , work in progress. Pier,P6 , further works were delayed due to heavy rainfall, construction of earth bund started again and hope to finish other works as soon as possible. | Sijo Varghese | |
17 Sep 2022 | Plastering and Tile works for generator switch room completed. Pier,P4 to P5 , Foot bridge slab and beam completed. Pier,P6 , further works delayed due to heavy rainfall. Hope, to start it as soon as possible. | Sijo Varghese |