Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Sep 2022 | The contractor has filed a Writ Petition No 1217/2021 in the Hon’ble High Court of Kerala to stay all coercive steps like termination pursuant to the demand for extension of Bank Guarantee as seen in Ext.P17,till the disposal of this Writ petition. Court directed the 6th respondant (vigilance) to submit report on the matter. Vigilance made an enquiry regarding the matter and they will submit the report to the honourable court. Final decision will be taken according to the verdict from the court. | Sijo Varghese | |
17 Sep 2022 | The contractor has filed a Writ Petition No 1217/2021 in the Hon’ble High Court of Kerala to stay all coercive steps like termination pursuant to the demand for extension of Bank Guarantee as seen in Ext.P17,till the disposal of this Writ petition. Court directed the 6th respondant (vigilance) to submit report on the matter. Vigilance made an enquiry regarding the matter and they will submit the report to the honourable court. Final decision will be taken according to the verdict from the court. | Sijo Varghese |