Rahul V R
Date: 24/03/2025

Work in progress | 12% Completed

% |0% Completed

reinforcement works for fountain pool ongoing.

Attached images

img

Rahul V R
Date: 17/03/2025

Work in progress | 10% Completed

% |0% Completed

pcc for fountain pool completed reinforcement work for pool ongoing

Attached images

img

Rahul V R
Date: 10/03/2025

Work in progress | 7% Completed

% |0% Completed

Reinforcement and shuttering works for fountain pit progressing.

Attached images

img

Rahul V R
Date: 17/02/2025

Work in progress | 4% Completed

% |0% Completed

Site clearing completed PCC for Fountain pool completed

Attached images

img

Rahul V R
Date: 24/03/2025

Work in progress | 0% Completed

reinforcement works for fountain pool ongoing.

Attached images

img

Rahul V R
Date: 17/03/2025

Work in progress | 0% Completed

pcc for fountain pool completed reinforcement work for pool ongoing

Attached images

img

Rahul V R
Date: 10/03/2025

Work in progress | 0% Completed

Reinforcement and shuttering works for fountain pit progressing.

Attached images

img

Rahul V R
Date: 17/02/2025

Work in progress | 0% Completed

Site clearing completed PCC for Fountain pool completed

Attached images

img