Work in progress | 12% Completed
% |0% Completed
reinforcement works for fountain pool ongoing.
Attached images
Work in progress | 10% Completed
pcc for fountain pool completed reinforcement work for pool ongoing
Work in progress | 7% Completed
Reinforcement and shuttering works for fountain pit progressing.
Work in progress | 4% Completed
Site clearing completed PCC for Fountain pool completed
Work in progress | 0% Completed