Work in progress | 32% Completed
% |0% Completed
fountain pool civil works 90% completed Shuttering works for Dg cum pump room main slab ongoing.
Attached images
Work in progress | 12% Completed
reinforcement works for fountain pool ongoing.
Work in progress | 10% Completed
pcc for fountain pool completed reinforcement work for pool ongoing
Work in progress | 7% Completed
Reinforcement and shuttering works for fountain pit progressing.
Work in progress | 4% Completed
Site clearing completed PCC for Fountain pool completed
Work in progress | 0% Completed