Rahul V R |
Date: 16/07/2025 |
Anu IT Admin |
Date: 08/07/2025 |
Work in progress | 78% Completed
|0% Completed
Civil:- Excavation for foundation completed Foundation Works Completed Plinth beam and verticals completed Roof slab of GF Completed Column at GF have been casted Roof slab of FF concreting completed Brick Work Completed Steel stair fabrication completed Plastering under progress will finish by next week Pending Works:- Sump well works Electrical works Commissioning and handover
Rahul V R |
Date: 24/03/2025 |
Rahul V R |
Date: 17/03/2025 |
Rahul V R |
Date: 10/03/2025 |
Rahul V R |
Date: 17/02/2025 |