Rahul V R
Date: 16/07/2025

Work in progress | 80% Completed

% |0% Completed

Stair fabrication works completed plastering of fertigation room is under progress.

Attached images

img

Anu IT Admin
Date: 08/07/2025

Work in progress | 78% Completed

% |0% Completed

Civil:- Excavation for foundation completed Foundation Works Completed Plinth beam and verticals completed Roof slab of GF Completed Column at GF have been casted Roof slab of FF concreting completed Brick Work Completed Steel stair fabrication completed Plastering under progress will finish by next week Pending Works:- Sump well works Electrical works Commissioning and handover

Rahul V R
Date: 24/03/2025

Work in progress | 69% Completed

% |0% Completed

reinforcement and shuttering works for plinth beam ongoing

Attached images

img

Rahul V R
Date: 17/03/2025

Work in progress | 69% Completed

% |0% Completed

shuttering works for plinth beam

Attached images

img

Rahul V R
Date: 10/03/2025

Work in progress | 68% Completed

% |0% Completed

concreting or foundation completed, reinforcement and shuttering works for plinth beam progressing

Attached images

img

Rahul V R
Date: 17/02/2025

Work in progress | 65% Completed

% |0% Completed

Main-submain and laterals work completed Excavation for isolated footing for fertigation room completed. trial run has been done successfully.

Attached images

img

Rahul V R
Date: 25/07/2024

Work in progress | 2% Completed

% |0% Completed

Land Registration has been completed. GFC drawings were issued. Farmers association was formed. Heavy rainfall in the vicinity causing delay to start the fertigation room work.

Attached images

img img

Rahul V R
Date: 16/07/2025

Work in progress | 0% Completed

Stair fabrication works completed plastering of fertigation room is under progress.

Attached images

img

Anu IT Admin
Date: 08/07/2025

Work in progress | 0% Completed

Civil:- Excavation for foundation completed Foundation Works Completed Plinth beam and verticals completed Roof slab of GF Completed Column at GF have been casted Roof slab of FF concreting completed Brick Work Completed Steel stair fabrication completed Plastering under progress will finish by next week Pending Works:- Sump well works Electrical works Commissioning and handover

Rahul V R
Date: 24/03/2025

Work in progress | 0% Completed

reinforcement and shuttering works for plinth beam ongoing

Attached images

img

Rahul V R
Date: 17/03/2025

Work in progress | 0% Completed

shuttering works for plinth beam

Attached images

img

Rahul V R
Date: 10/03/2025

Work in progress | 0% Completed

concreting or foundation completed, reinforcement and shuttering works for plinth beam progressing

Attached images

img

Rahul V R
Date: 17/02/2025

Work in progress | 0% Completed

Main-submain and laterals work completed Excavation for isolated footing for fertigation room completed. trial run has been done successfully.

Attached images

img

Rahul V R
Date: 25/07/2024

Work in progress | 0% Completed

Land Registration has been completed. GFC drawings were issued. Farmers association was formed. Heavy rainfall in the vicinity causing delay to start the fertigation room work.

Attached images

img img