M A Faseela Nasar
Date: 26/08/2024

Work in progress | 10% Completed

% |0% Completed

Work has been stopped for last one year and waiting for RE approval

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 10% Completed

% |0% Completed

waiting for RE sanction

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 10% Completed

% |0% Completed

RE is in KIIFB. Another drawings came from IITM today. hence the Final RE is not yet completed.

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 10% Completed

% |0% Completed

work was not yet started. design and RE was not finalized till date.

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 10% Completed

% |0% Completed

emergency works is in progress for Ambalappuzha, Kattoor and Ottamassery

Attached images

img img img img img img

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 10% Completed

% |0% Completed

emergency works is in progress for Ambalappuzha, Kattoor and Ottamassery

Attached images

img img img img img img

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 10% Completed

% |0% Completed

emergency works is in progress for Ambalappuzha, Kattoor and Ottamassery

Attached images

img img img img img img

Silppa R
Date: 29/05/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Silppa R
Date: 22/05/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Silppa R
Date: 14/05/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 1% Completed

% |0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 1% Completed

% |0% Completed

Initially, the casting of 5T and 2T tetrapods was started at the site .Due to deviation from the previous survey in the bathymetry survey conducted prior to the commencement of the work ,the IIT has has given the redesign of the Groynes and submitted a revised estimate to KIIFB for the approval of the increased amount ,but the approval has not been received till date ,so the work has been stopped .

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 1% Completed

% |0% Completed

Initially, the casting of 5T and 2T tetrapods was started at the site .Due to deviation from the previous survey in the bathymetry survey conducted prior to the commencement of the work ,the IIT has has given the redesign of the Groynes and submitted a revised estimate to KIIFB for the approval of the increased amount ,but the approval has not been received till date ,so the work has been stopped .

Attached images

img

M A Faseela Nasar
Date: 26/08/2024

Work in progress | 0% Completed

Work has been stopped for last one year and waiting for RE approval

M A Faseela Nasar
Date: 20/05/2024

Work in progress | 0% Completed

waiting for RE sanction

M A Faseela Nasar
Date: 22/04/2024

Work in progress | 0% Completed

RE is in KIIFB. Another drawings came from IITM today. hence the Final RE is not yet completed.

M A Faseela Nasar
Date: 08/04/2024

Work in progress | 0% Completed

work was not yet started. design and RE was not finalized till date.

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

emergency works is in progress for Ambalappuzha, Kattoor and Ottamassery

Attached images

img img img img img img

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

emergency works is in progress for Ambalappuzha, Kattoor and Ottamassery

Attached images

img img img img img img

M A Faseela Nasar
Date: 10/07/2023

Work in progress | 0% Completed

emergency works is in progress for Ambalappuzha, Kattoor and Ottamassery

Attached images

img img img img img img

Silppa R
Date: 29/05/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Silppa R
Date: 22/05/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Silppa R
Date: 14/05/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Attached images

img

Silppa R
Date: 08/05/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB

Attached images

img

Silppa R
Date: 30/04/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB.

Attached images

img

Silppa R
Date: 23/04/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB.

Attached images

img

Silppa R
Date: 16/04/2023

Work in progress | 0% Completed

The casting of 5T and 2T tertapods were started at site, but was stopped for want of sanction of RE .The RE was prepared due to the changes in design consequent to the deviation in the bathymetry survey. The sanction for the same is not yet received from KIIFB.

Attached images

img

Silppa R
Date: 09/04/2023

Work in progress | 0% Completed

Initially, the casting of 5T and 2T tetrapods was started at the site .Due to deviation from the previous survey in the bathymetry survey conducted prior to the commencement of the work ,the IIT has has given the redesign of the Groynes and submitted a revised estimate to KIIFB for the approval of the increased amount ,but the approval has not been received till date ,so the work has been stopped .

Attached images

img

Silppa R
Date: 02/04/2023

Work in progress | 0% Completed

Initially, the casting of 5T and 2T tetrapods was started at the site .Due to deviation from the previous survey in the bathymetry survey conducted prior to the commencement of the work ,the IIT has has given the redesign of the Groynes and submitted a revised estimate to KIIFB for the approval of the increased amount ,but the approval has not been received till date ,so the work has been stopped .

Attached images

img